← Back
BuildNYC
Office only, 1 story
258-20 HILLSIDE AVENUE
QUEENS · BIN 4624107
💬 Discuss this project
1973Year Built
1Stories
O1Building Class
R3-2Zoning
3,750 sfGross Floor Area
1Units
0 Active ViolationsFDNY Report ↗
Office only, 1 story · Owner of record: Rai Krupa · 7,325 sf lot · 0.51 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofRai Krupa22p · 3 filings · 20 docs
Floor 1Rai Krupa47p · 5 filings · 20 docs
Site & exteriorRai Krupa21p · 2 filings · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/28/2021$5.1M—Private party → Rai Krupa$1,350/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
M.S. Savani Architect503/13/2023
All City Engineering510/27/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
M.S. Savani Architect803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Mit Brothers ConstructionGeneral Contractor1007/08/2026
Mit Brothers ConstructionScaffold303/21/2026
Whitestone PlumbingFire Protection107/08/2026
Whitestone PlumbingPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
IP Concrete Testing and I6252803/13/2023
Building Lifecycle
All (69)Filed (10)Permit Issued (7)Signed Off (4)Inspection (8)Objection (10)Special Inspection (30)
03/13/2023
Filed — Alteration CO
Application filed for new C of O. Proposed Community Hall (Adult Day Care Center- 4A) with exterior & interior renovation. Change in Metes and Bounds
Q00610022-P2
03/13/2023
Special inspection requirement — Air barrier — testing
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Energy Code Compliance Inspections
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Mastic and Intumescent Fire-resistant Coatings
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Fenestration air leakage
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Exterior lighting power
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Interior lighting power
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Final
NAVEEN KUMAR
03/13/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Lighting controls
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Insulation placement and R values
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Fenestration areas
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Fire-Resistance Rated Construction
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Air barrier - visual inspection
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Masonry
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Energy Code Compliance Inspections
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Final
NAVEEN KUMAR
03/03/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Fire-Resistance Rated Construction
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Mastic and Intumescent Fire-resistant Coatings
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Masonry
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Fenestration air leakage
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Lighting controls
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Insulation placement and R values
INDARDEO PARBHUNATH
02/06/2023
Signed off — Alteration
Mechanical work for fire suppression in the kitchen. Installation of HVAC system. No change in use, egress, or occupancy.
Q00616094-I1
02/03/2023
Signed off — Alteration
Install plumbing fixtures, no change of use, occupancy and egress
Q00616095-I1
12/12/2022
Signed off — Alteration
HEREWITH TO PROPOSE TEMPORARY 8' HIGH WOOD CONSTRUCTION FENCE. NO CHANGES IN OCCUPANCY, USE, GROUP OR EGRESS UNDER THIS APPLICATION.
Q00652311-I1
12/10/2022
Permit issued — Mechanical Systems
Q00616094-I1-MS
12/09/2022
Permit issued — Construction Fence
Q00652311-I1-FN
11/29/2022
Signed off — Alteration
Remove of existing sprinkler for open kitchen, no change of use, occupancy and egress
Q00616096-I1
10/27/2022
Filed — Alteration
Install plumbing fixtures, no change of use, occupancy and egress
Q00616095-P1
10/18/2022
Permit issued — General Construction
Q00610022-I1-GC-CX
10/14/2022
Filed — Alteration
Mechanical work for fire suppression in the kitchen. Installation of HVAC system. No change in use, egress, or occupancy.
Q00616094-P1
10/07/2022
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
10/03/2022
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
09/13/2022
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
08/12/2022
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/22/2022
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
07/22/2022
Objection resolved — Addressed
07/21/2022
Objection raised — Accessibility
07/14/2022
Filed — Alteration CO
Application filed for new C of O. Proposed Community Hall (Adult Day Care Center- 4A) with exterior & interior renovation. Change in Metes and Bounds
Q00610022-P1
06/30/2022
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
04/29/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/29/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
04/12/2022
Objection raised — Fire_Protection
04/12/2022
Objection resolved — Addressed
04/12/2022
Objection raised — Fire_Protection
04/12/2022
Objection resolved — Addressed
04/12/2022
Objection raised — Fire_Protection
04/12/2022
Objection resolved — Addressed
04/12/2022
Objection raised — Scope
04/12/2022
Objection resolved — Addressed
04/07/2022
Permit issued — Structural
Q00610022-I1-GC-CX
Latest 60 of 69 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offMit Brothers Construction12/10/2022
DOB NOWConstruction FenceSigned-offMit Brothers Construction12/09/2022
DOB NOWGeneral ConstructionPermit IssuedMit Brothers Construction10/18/2022
DOB NOWStructuralPermit IssuedMit Brothers Construction04/07/2022
DOB NOWPlumbingSigned-offWhitestone Plumbing03/21/2022
DOB NOWSprinklersSigned-offTemperini Mechanical03/21/2022
DOB NOWGeneral ConstructionPermit IssuedMit Brothers Construction03/04/2022
1 project · most recent 03/24/2022
General Wiring
FiledStatusContractorScope
03/24/2022CompleteNelson & Tom Maintenance Inc DBGeneral Wiring
1 project · most recent 03/13/2023
Masonry Wood
FiledStatusContractorScope
03/13/2023Permit IssuedMit Brothers ConstructionMasonry, Wood
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
10/07/2022Pass-Final CND-Occupancy InspectionPassView ↗
10/03/2022Pass-Final CND-Occupancy InspectionPassView ↗
09/13/2022Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
08/12/2022Pass-Final CND-Occupancy InspectionPassView ↗
07/22/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/30/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/29/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/29/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 77
DateRequirementInspectorRole
03/13/2023Mastic and Intumescent Fire-resistant CoatingsINDARDEO PARBHUNATHspecial
03/13/2023Insulation placement and R valuesINDARDEO PARBHUNATHenergy_progress
03/13/2023Exterior lighting powerINDARDEO PARBHUNATHenergy_progress
03/13/2023Air barrier - visual inspectionINDARDEO PARBHUNATHenergy_progress
03/13/2023Lighting controlsINDARDEO PARBHUNATHenergy_progress
03/13/2023Air barrier — testing INDARDEO PARBHUNATHenergy_progress
03/13/2023Fenestration air leakageINDARDEO PARBHUNATHenergy_progress
03/13/2023Fenestration areasINDARDEO PARBHUNATHenergy_progress
03/13/2023Fenestration and door U-factor and product ratingsINDARDEO PARBHUNATHenergy_progress
03/13/2023Interior lighting powerINDARDEO PARBHUNATHenergy_progress
03/13/2023Fire-Resistance Rated ConstructionINDARDEO PARBHUNATHprogress
03/13/2023Energy Code Compliance InspectionsINDARDEO PARBHUNATHprogress
03/13/2023FinalNAVEEN KUMARprogress
03/13/2023Fire-Resistant Penetrations and JointsINDARDEO PARBHUNATHspecial
03/13/2023MasonryINDARDEO PARBHUNATHspecial
03/13/2023Structural Stability – Alterations of existing buildingsINDARDEO PARBHUNATHspecial
03/13/2023Exterior Insulation and Finish Systems (EIFS)INDARDEO PARBHUNATHspecial
03/13/2023Wall Panels, Curtain Walls, and VeneersINDARDEO PARBHUNATHspecial
03/03/2023Exterior Insulation and Finish Systems (EIFS)INDARDEO PARBHUNATHspecial
03/03/2023Fire-Resistant Penetrations and JointsINDARDEO PARBHUNATHspecial
03/03/2023MasonryINDARDEO PARBHUNATHspecial
03/03/2023Mastic and Intumescent Fire-resistant CoatingsINDARDEO PARBHUNATHspecial
03/03/2023Structural Stability – Alterations of existing buildingsINDARDEO PARBHUNATHspecial
03/03/2023Wall Panels, Curtain Walls, and VeneersINDARDEO PARBHUNATHspecial
03/03/2023Energy Code Compliance InspectionsINDARDEO PARBHUNATHprogress
Latest 25 of 77.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Rai KrupaEducationFloor 1
Project Q00610022 Alteration CO · CO Issued · 10/26/2021
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 123 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch9
08/26/2026Q00652311-I1Request digital key ↗
08/26/2026Q00616096-I1Request digital key ↗
08/26/2026Q00616094-I1Request digital key ↗
Showing 3 of 9 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly1
08/15/2026Q00705459-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records1
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q00610022-I1Open ↗
▸Seals & Professional Certifications87
▸DOB NOWProgress Inspector Seal & Signature53
09/01/2026Q00610022-P2Open ↗
09/01/2026Q00610022-P2Open ↗
09/01/2026Q00610022-P2Open ↗
Showing 3 of 53 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature24
09/01/2026Q00610022-P2Open ↗
09/01/2026Q00610022-P2Open ↗
09/01/2026Q00610022-P2Open ↗
Showing 3 of 24 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature10
08/26/2026Q00652311-I1Open ↗
08/26/2026Q00705459-I1Open ↗
08/25/2026Q00610022-P1Open ↗
Showing 3 of 10 on file for this type
▸Safety & Tenant Protection4
▸DOB NOWStreet Tree Checklist3
08/13/2026Q00610022-P2Open ↗
08/13/2026Q00610022-I1Open ↗
08/13/2026Q00610022-P1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q00610022-I1Open ↗
▸Environmental & Asbestos14
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/25/2026Q00610022-P2Open ↗
08/25/2026Q00610022-I1Open ↗
08/15/2026Q00610022-P1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWOER: Notice of Satisfaction3
08/13/2026Q00610022-I1Open ↗
08/13/2026Q00616094-I1Open ↗
08/13/2026Q00616095-I1Open ↗
▸DOB NOWOER: Notice to Proceed3
08/13/2026Q00610022-I1Open ↗
08/13/2026Q00616094-I1Open ↗
08/13/2026Q00616095-I1Open ↗
▸Energy Compliance2
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026Q00610022-I1Open ↗
08/13/2026Q00616094-I1Open ↗
▸Other Documents5
▸DOB NOWProperty Ownership Certification3
08/25/2026Q00610022-P2Open ↗
08/25/2026Q00610022-I1Open ↗
08/15/2026Q00610022-P1Open ↗
▸DOB NOWPARTIAL DEMO: 10-DAY Notice1
08/13/2026Q00610022-I1Open ↗
▸DOB NOWFinal Survey1
08/13/2026Q00610022-I1Open ↗