LL97 CoveredRent Stabilized69 Open Violations 46 unresolved · 23 paperwork only ▸FISP: SWARMPFDNY Report ↗
Elevator cooperative · Owner of record: MITCHELL GARDENS #3 COOPERATIVE · 431,000 sf lot · 1.16 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingGeneral
Roof1p · 1 filing · 10 docs
Bulkhead1p · 1 filing · 10 docs
Cellar1p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
KINGS GROUP NY1607/08/2026
MITCHELL GARDENS#3 COOPER403/22/2026
MITCHELL GARDENS #COOPERA103/22/2026
MITCHELL GARDENS NO 3 COOP1003/22/2026
MITCHELL GARDENS #3 CO103/22/2026
MITCHELL GARDENSSEC 3203/21/2026
SKILL CONSTRUCTION203/21/2026
KAJ NY CONSTRUCTION203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JOSEPH K. BLUM CO. LLP206/29/2026
ROBERT GERMAIN JR. PE608/26/2025
AG ENGINEERING PLLC111/15/2023
SYED ENGINEERING, P.C.106/30/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ARSENAL BUILDING CONSULTANTS LLC203/21/2026
D D EXPEDITORS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SKYLINE BUILDERS GROUP LLGeneral Contractor1607/08/2026
KINGS GROUP NY CORPGeneral Contractor1607/08/2026
CAM ENERGY HTG&MECH CORPPlumbing307/08/2026
KANHAI, ONEILElectrical203/21/2026
CUOMO, FElectrical203/21/2026
AGGRESSIVE HEATING INCGeneral Contractor107/08/2026
MICHAEL BAPTISTEElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JOSEPH K. BLUM CO. LLP1741206/29/2026
ROBERT F. GERMAIN JR. PE5100608/26/2025
Building Lifecycle
All (130)Filed (10)Permit Issued (18)Signed Off (2)Facade (FISP) (18)Violation (60)Inspection (9)Special Inspection (13)
06/29/2026
Filed — Alteration
Repair/replace all facades to include masonry, pointing, lintels, sills, scrape and paint fire escapes
Q00480050-P1
06/14/2026
Special inspection requirement — Fenestration air leakage
Dane Barnes
06/14/2026
Special inspection requirement — Final
Dane Barnes
06/14/2026
Special inspection requirement — Air barrier - visual inspection
Dane Barnes
06/14/2026
Special inspection requirement — Energy Code Compliance Inspections
Dane Barnes
06/14/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Dane Barnes
06/14/2026
Special inspection requirement — Masonry
Dane Barnes
03/12/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/21/2026
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
12/29/2025
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
12/01/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
10/24/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/14/2025
Inspection — Fail-Final Boiler Equipment Inspection
Fail
View inspection ↗
10/08/2025
Permit issued — Plumbing
Q00977727-S1-PL
08/28/2025
Special inspection requirement — Fuel-Oil Storage and Fuel-Oil Piping Systems
Robert Germain Jr.
08/26/2025
Filed — Alteration
Q00977727-P3
08/26/2025
Special inspection requirement — Final
Robert Germain Jr.
08/26/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Robert Germain Jr.
08/26/2025
Special inspection requirement — Chimneys and vents
Robert Germain Jr.
08/25/2025
Filed — Alteration
Q00977727-P1
08/25/2025
Filed — Alteration
Q00977727-P2
08/13/2025
Violation issued (FDNY_NOV, closed)
08/04/2025
Special inspection requirement — Chimneys and vents
Robert Germain Jr.
08/04/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Robert Germain Jr.
08/04/2025
Special inspection requirement — Final
Robert Germain Jr.
07/22/2025
Violation issued (FDNY_NOV, closed)
07/22/2025
Violation issued (FDNY_NOV, closed)
04/10/2025
Permit issued — Boiler Equipment
Q00977727-S2-BE
03/21/2025
Signed off — Alteration
INSTALLATION OF HEAVY DUTY SIDEWALK SHED. NO CHANGE IN USE, OCCUPANCY OR EGRESS. WORK SHALL COMPLY WITH CHAPTER 33 OF NYCC.
Q00546036-I1
02/11/2025
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
01/15/2025
Permit issued — General Construction
Q00480050-I1-GC
01/11/2025
Violation issued (FDNY_NOV, closed)
12/30/2024
Permit issued — Plumbing
Q00977727-S1-PL
11/21/2024
Cycle 9 facade report signed — SWARMP
11/14/2024
Signed off — Alteration
installation of pipe scaffolding. no change in use, occupancy or egress. work shall comply with chapter 33 of nycc.
Q00963404-I1
11/14/2024
Permit issued — Supported Scaffold
Q00963404-I1-SF
10/21/2024
Cycle 9 facade inspection completed
09/11/2024
Violation issued (FDNY_NOV, closed)
06/26/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/13/2024
Permit issued — Sidewalk Shed
Q00546036-I1-SH
05/24/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
04/23/2024
Violation issued (ECB, open)
Construction
04/04/2024
Cycle 9 facade report submitted
04/02/2024
Permit issued — Boiler Equipment
Q00977727-S2-BE
04/02/2024
Permit issued — Plumbing
Q00977727-S1-PL
03/18/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
03/13/2024
Filed — Alteration
Q00977727-S2
03/13/2024
Filed — Alteration
Q00977727-S1
02/23/2024
Permit issued — General Construction
Q00977727-I1-GC
02/08/2024
Filed — Alteration
Q00977727-I1
01/16/2024
Violation issued (ECB, open)
Local Law
01/12/2024
Permit issued — General Construction
Q00480050-I1-GC
11/16/2023
Permit issued — Supported Scaffold
Q00963404-I1-SF
11/15/2023
Filed — Alteration
installation of pipe scaffolding. no change in use, occupancy or egress. work shall comply with chapter 33 of nycc.
Q00963404-I1
06/15/2023
Permit issued — Sidewalk Shed
Q00546036-I1-SH
02/02/2023
Permit issued — General Construction
Q00480050-I1-GC
12/29/2022
Cycle 9 facade report submitted
12/29/2022
Cycle 9 facade report signed — UNSAFE
12/19/2022
Cycle 9 facade inspection completed
09/07/2022
Permit issued — General Construction
Q00480050-I1-GC
Latest 60 of 130 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offCAM ENERGY HTG&MECH CORP10/08/2025
DOB NOWBoiler EquipmentPermit IssuedRICHARD MORTMAN04/10/2025
DOB NOWGeneral ConstructionSigned-offSKYLINE BUILDERS GROUP LL01/15/2025
DOB NOWPlumbingSigned-offCAM ENERGY HTG&MECH CORP12/30/2024
DOB NOWSupported ScaffoldSigned-offKINGS GROUP NY CORP11/14/2024
DOB NOWSidewalk ShedSigned-offKINGS GROUP NY CORP06/13/2024
DOB NOWBoiler EquipmentPermit IssuedAGGRESSIVE HEATING INC04/02/2024
DOB NOWPlumbingSigned-offCAM ENERGY HTG&MECH CORP04/02/2024
DOB NOWGeneral ConstructionPermit IssuedAGGRESSIVE HEATING INC02/23/2024
DOB NOWGeneral ConstructionSigned-offSKYLINE BUILDERS GROUP LL01/12/2024
DOB NOWSupported ScaffoldSigned-offKINGS GROUP NY CORP11/16/2023
DOB NOWSidewalk ShedSigned-offKINGS GROUP NY CORP06/15/2023
DOB NOWGeneral ConstructionSigned-offSKYLINE BUILDERS GROUP LL02/02/2023
DOB NOWGeneral ConstructionSigned-offSKYLINE BUILDERS GROUP LL09/07/2022
DOB NOWSidewalk ShedSigned-offKINGS GROUP NY CORP06/21/2022
DOB NOWGeneral ConstructionSigned-offSKYLINE BUILDERS GROUP LL09/09/2021
DOB NOWGeneral ConstructionSigned-offSKYLINE BUILDERS GROUP LL08/30/2021
DOB NOWSidewalk ShedSigned-offKINGS GROUP NY CORP06/30/2021
BISOTISSUEDSKILL CONSTRUCTION CORP11/21/2017
BISEQISSUEDKAJ NY CONSTRUCTION INC09/26/2017
BISSPISSUEDALKLEM PLUMBING INC.02/07/2005
BISOTISSUEDAPOGEE ENTERPRISES04/18/2003
1 project · most recent 06/20/2023
FiledStatusContractorScope
06/20/2023CompleteHIGH QUALITY ELECTRIC OF—
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
03/12/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/21/2026Fail-Final CND-Occupancy InspectionFailView ↗
12/29/2025Fail-Final CND-Occupancy InspectionFailView ↗
12/01/2025Pass-Final CND-Occupancy InspectionPassView ↗
10/24/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/14/2025Fail-Final Boiler Equipment InspectionFailView ↗
02/11/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
05/24/2024Pass-Final CND-Occupancy InspectionPassView ↗
03/18/2024Pass-Final CND-Occupancy InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 13
DateRequirementInspectorRole
06/14/2026Fenestration air leakageDane Barnesenergy_progress
06/14/2026FinalDane Barnesprogress
06/14/2026Air barrier - visual inspectionDane Barnesenergy_progress
06/14/2026Energy Code Compliance InspectionsDane Barnesprogress
06/14/2026Structural Stability – Alterations of existing buildingsDane Barnesspecial
06/14/2026MasonryDane Barnesspecial
08/28/2025Fuel-Oil Storage and Fuel-Oil Piping SystemsRobert Germain Jr.special
08/26/2025FinalRobert Germain Jr.progress
08/26/2025Fire-Resistant Penetrations and JointsRobert Germain Jr.special
08/26/2025Chimneys and ventsRobert Germain Jr.special
08/04/2025Chimneys and ventsRobert Germain Jr.special
08/04/2025Fire-Resistant Penetrations and JointsRobert Germain Jr.special
08/04/2025FinalRobert Germain Jr.progress
▾Documents — 58 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch10
08/27/2026Q00480050-P1Request digital key ↗
08/27/2026Q00480050-I1Request digital key ↗
08/27/2026Q00546036-I1Request digital key ↗
Showing 3 of 10 on file for this type
▸Applications & Permits6
▸BISWORK PERMIT APPLICATION4
11/21/2017440449285Open ↗
11/17/2017440449285Open ↗
09/26/2017440436636Open ↗
Showing 3 of 4 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION2
11/17/2017440449285Open ↗
09/24/2017440436636Open ↗
▸Seals & Professional Certifications26
▸DOB NOWDPL-1: Design Professional Seal & Signature10
08/27/2026Q00480050-P1Open ↗
08/23/2026Q00963404-I1Open ↗
08/23/2026Q00977727-I1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/23/2026Q00977727-S2Open ↗
09/12/2026Q00977727-S1Open ↗
09/05/2026Q00977727-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/05/2026Q00977727-P1Open ↗
08/27/2026Q00480050-P1Open ↗
08/27/2026Q00480050-P1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
11/17/2017440449285Open ↗
09/24/2017440436636Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
11/17/2017440449285Open ↗
09/24/2017440436636Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
11/17/2017440449285Open ↗
09/24/2017440436636Open ↗
▸Safety & Tenant Protection2
▸BISTENANT PROTECTION PLAN AND NOTES2
11/17/2017440449285Open ↗
09/24/2017440436636Open ↗
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/27/2026Q00480050-P1Open ↗
08/23/2026Q00977727-S1Open ↗
08/23/2026Q00977727-S2Open ↗
Showing 3 of 8 on file for this type
▸Energy Compliance2
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
09/24/2017440436636Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/27/2026Q00480050-I1Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: RESPONSIBILITY1
11/17/2017440449285Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
11/17/2017440449285Open ↗
▸Filing & Intake Forms2
▸BISEFILING JOB APPLICATION COVER SHEET2
11/17/2017440449285Open ↗
09/24/2017440436636Open ↗