DOB11/06/2024OBSERVED EXCESSIVE EXCAVATING THOUGHT THE BASEMENT WITHOUT A PERMIT ON FILE. VIOLATION ISSUED WORK WITHOUT A PERMIT
ECB12/03/2024ATOI OBSERVED ALTERATIONS MADE TO BLDG ENVELOPE WITH REMOVAL OF EXISTING WINDOW & IT'S STRUCTURE. OBSERVED OPENING APPROX 8FTX3FT AT EXPO-2 CELLAR/FOUNDATION WALL. DEPT RECORDS INDICATE NO CONSTRUCTION PERMIT FNothing owed — awaiting certificate of correction
ECB12/03/2024ATOI OBSERVED EXCAVATION/REMOVAL OF EARTH, NEW CONCRETE SLAB POURED, ELECTRICAL WIRING/TEMP LIGHTING & ALTERATIONS/RELOCATION OF PIPE PLUMBING SYSTEM AT CELLAR LEVEL & ALTERATIONS OF EXTERIOR BLDG ENVELOPE AT ENothing owed — awaiting certificate of correction
ECB12/03/2024ATOI OBSERVED INADEQUATE HOUSEKEEPING MAINTAINED DURING CONSTRUCTION OPERATIONS. EXCESSIVE AMOUNTS OF CONSTRUCTION DEBRIS, DIRT, DUST OBSERVED THROUGHOUT EXPO-3 REAR & EXPO-2 SIDE YARDS. SITE NOT ENCLOSED & CONNothing owed — awaiting certificate of correction
ECB12/03/2024ATOI OBSERVED BX ELECTRICAL WIRING, TEMP PIGTAIL LIGHT FIXTURES, WIRED ELECTRICAL RECEPTACLES & JUNCTIONS INSTALLED THROUGHOUT ENTIRE CELLAR LEVEL. DEPT RECORDS INDICATE NO ELECTRICAL PERMIT FILED FOR ALTERATIONothing owed — awaiting certificate of correction
ECB12/03/2024OBSERVED APPROX 15FT OF VERTICAL&HORIZONTAL PIPING REMOVED & REPLACED WITH NEW 2" PIPE-FITTINGS-FUSED CONNECTIONS AT CELLAR. EXISTING PLUMBING RELOCATED FROM GRADE LEVEL RAISED TO CEILING HEIGHT FOR CLEARANCE/ANothing owed — awaiting certificate of correction