← Back
One story retail building
260-07 HILLSIDE AVENUE
QUEENS · Glen Oaks-Floral Park-New Hyde Park · BIN 4179426
💬 Discuss this project
1951Year Built
1Stories
K1Building Class
R3-2Zoning
800 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
One story retail building · 1,450 sf lot · 0.55 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Roof2p · 1 filing · 10 docs
Floor 12p · 2 filings · 16 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SERDAR CEYLAN ARCHITECT, PC311/17/2022
KORMAN DESIGN & BUILD407/28/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
KENNY LEE ARCHITECT403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
KORMAN DESIGN & BUILDGeneral Contractor307/08/2026
SKINNER PLUMBING & HEATINGPlumbing207/08/2026
HYDRAULICS MECHANICAL INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ARCHITECTURAL CONCEPT3642311/17/2022
KORMAN DESIGN & BUILD2055307/14/2022
Building Lifecycle
All (41)Filed (7)Permit Issued (5)Signed Off (4)Violation (2)Inspection (3)Special Inspection (20)
03/18/2025
Violation issued (FDNY_ORDER, closed)
03/18/2025
Violation issued (FDNY_ORDER, closed)
02/06/2023
Signed off — Alteration
REGISTER 1 FURNACE AND 1 HOT WATER HEATER AS PER PLANS SUBMITTED. NO CHANGE IN USE EGRESS OR OCCUPANCY.
Q07998155-I1
02/02/2023
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/02/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/20/2022
Special inspection requirement — Energy Code Compliance Inspections
SERDAR CEYLAN
11/20/2022
Special inspection requirement — HVAC-R and service water heating equipment
SERDAR CEYLAN
11/20/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
MUZAFFAR JAMAL
11/17/2022
Filed — Alteration
REGISTER 1 FURNACE AND 1 HOT WATER HEATER AS PER PLANS SUBMITTED. NO CHANGE IN USE EGRESS OR OCCUPANCY.
Q07998155-P2
11/17/2022
Special inspection requirement — HVAC-R and service water heating equipment
SERDAR CEYLAN
11/17/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
MUZAFFAR JAMAL
11/17/2022
Special inspection requirement — Energy Code Compliance Inspections
SERDAR CEYLAN
11/14/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/02/2022
Filed — Alteration
REGISTER 1 FURNACE AND 1 HOT WATER HEATER AS PER PLANS SUBMITTED. NO CHANGE IN USE EGRESS OR OCCUPANCY.
Q07998155-P1
11/02/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
MUZAFFAR JAMAL
11/02/2022
Special inspection requirement — HVAC-R and service water heating equipment
SERDAR CEYLAN
11/02/2022
Special inspection requirement — Energy Code Compliance Inspections
SERDAR CEYLAN
10/31/2022
Signed off — Alteration
Q00779700-I1
10/24/2022
Permit issued — Plumbing
Q07998155-I1-PL
09/30/2022
Filed — Alteration
REGISTER 1 FURNACE AND 1 HOT WATER HEATER AS PER PLANS SUBMITTED. NO CHANGE IN USE EGRESS OR OCCUPANCY.
Q07998155-I1
08/02/2022
Permit issued — General Construction
Q00779700-I1-GC
07/28/2022
Filed — Alteration
Q00779700-I1
07/26/2022
Signed off — Alteration
INSTALLATION OF A/C UNITS
Q00768323-I1
07/22/2022
Permit issued — Mechanical Systems
Q00768323-I1-MS
07/22/2022
Special inspection requirement — Final
DAVID UH
07/14/2022
Filed — Alteration
INSTALLATION OF A/C UNITS
Q00768323-I1
07/14/2022
Special inspection requirement — HVAC-R and service water heating system controls
DAVID UH
07/14/2022
Special inspection requirement — HVAC-R and service water heating equipment
DAVID UH
07/14/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
DAVID UH
07/01/2022
Special inspection requirement — Final
DAVID UH
07/01/2022
Special inspection requirement — Mechanical Systems
DAVID UH
07/01/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
DAVID UH
05/24/2021
Signed off — Alteration
INSTALLATION OF PLUMBING FIXTURES & GAS NON-RESIDENTIAL KITCHEN EQUIPMENT
Q00384062-I1
04/28/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
DAVID UH
04/28/2021
Special inspection requirement — Energy Code Compliance Inspections
DAVID UH
04/14/2021
Filed — Alteration
INSTALLATION OF PLUMBING FIXTURES & GAS NON-RESIDENTIAL KITCHEN EQUIPMENT
Q00384062-P1
04/12/2021
Special inspection requirement — Energy Code Compliance Inspections
DAVID UH
04/12/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
DAVID UH
11/19/2020
Permit issued — Plumbing
Q00384062-I1-PL
10/22/2020
Permit issued — Plumbing
Q00384062-I1-PL
09/11/2020
Filed — Alteration
INSTALLATION OF PLUMBING FIXTURES & GAS NON-RESIDENTIAL KITCHEN EQUIPMENT
Q00384062-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offHYDRAULICS MECHANICAL INC10/24/2022
DOB NOWGeneral ConstructionSigned-offKORMAN DESIGN & BUILD08/02/2022
DOB NOWMechanical SystemsSigned-offKORMAN DESIGN & BUILD07/22/2022
DOB NOWPlumbingSigned-offSKINNER PLUMBING & HEATIN11/19/2020
DOB NOWPlumbingSigned-offSKINNER PLUMBING & HEATIN10/22/2020
BISOTISSUEDHUNT B CONSTRUCTION INC11/17/2020
BISOTISSUEDJRC ARCHICON08/08/2002
BISPLISSUEDPLUMBING & HTG DOCTOR INC04/10/2002
BISOTISSUEDJRC ARCHICON08/13/2001
Nothing on file for this building.
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
02/02/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/02/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/14/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 20
DateRequirementInspectorRole
11/20/2022Energy Code Compliance InspectionsSERDAR CEYLANprogress
11/20/2022HVAC-R and service water heating equipmentSERDAR CEYLANenergy_progress
11/20/2022Fire-Resistant Penetrations and JointsMUZAFFAR JAMALspecial
11/17/2022HVAC-R and service water heating equipmentSERDAR CEYLANenergy_progress
11/17/2022Fire-Resistant Penetrations and JointsMUZAFFAR JAMALspecial
11/17/2022Energy Code Compliance InspectionsSERDAR CEYLANprogress
11/02/2022Fire-Resistant Penetrations and JointsMUZAFFAR JAMALspecial
11/02/2022HVAC-R and service water heating equipmentSERDAR CEYLANenergy_progress
11/02/2022Energy Code Compliance InspectionsSERDAR CEYLANprogress
07/22/2022FinalDAVID UHprogress
07/14/2022HVAC-R and service water heating system controlsDAVID UHenergy_progress
07/14/2022HVAC-R and service water heating equipmentDAVID UHenergy_progress
07/14/2022HVAC-R and service water piping design and insulationDAVID UHenergy_progress
07/01/2022FinalDAVID UHprogress
07/01/2022Mechanical SystemsDAVID UHspecial
07/01/2022Fire-Resistant Penetrations and JointsDAVID UHspecial
04/28/2021Fire-Resistant Penetrations and JointsDAVID UHspecial
04/28/2021Energy Code Compliance InspectionsDAVID UHprogress
04/12/2021Energy Code Compliance InspectionsDAVID UHprogress
04/12/2021Fire-Resistant Penetrations and JointsDAVID UHspecial
▾Documents — 53 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch5
08/26/2026Q00768323-I1Request digital key ↗
08/26/2026Q00779700-I1Request digital key ↗
08/25/2026Q07998155-P2Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Plumbing2
08/28/2026Q00384062-I1Request digital key ↗
08/15/2026Q00384062-P1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
09/23/2020440620918Open ↗
▸BISWORK PERMIT APPLICATION1
11/17/2020440620918Open ↗
▸Seals & Professional Certifications26
▸DOB NOWProgress Inspector Seal & Signature11
09/02/2026Q07998155-P1Open ↗
09/02/2026Q07998155-P1Open ↗
08/29/2026Q07998155-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/28/2026Q00384062-P1Open ↗
08/28/2026Q00384062-I1Open ↗
08/25/2026Q07998155-P2Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/02/2026Q07998155-P1Open ↗
08/29/2026Q07998155-I1Open ↗
08/26/2026Q00384062-I1Open ↗
Showing 3 of 6 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
09/23/2020440620918Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
09/23/2020440620918Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/28/2026Q00384062-I1Open ↗
08/28/2026Q00384062-P1Open ↗
08/25/2026Q07998155-P2Open ↗
Showing 3 of 6 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
09/23/2020440620918Open ↗
▸Energy Compliance4
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
05/24/2021440620918Open ↗
11/17/2020440620918Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
05/24/2021440620918Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
09/23/2020440620918Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
05/24/2021440620918Open ↗
11/17/2020440620918Open ↗
▸Approvals, Objections & Sign-offs1
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
05/24/2021440620918Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
05/24/2021440620918Open ↗
09/23/2020440620918Open ↗
▸Filing & Intake Forms2
▸BISADDITIONAL INFORMATION1
10/09/2020440620918Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
09/23/2020440620918Open ↗