Whole building & multi-floor projectsTemporary pipe scaffold for facade repair1 filing
INSTALLATION OF TEMPORARY 192' HIGH PIPE SCAFFOLD ORIGINATING (OFF 2ND FLOOR TERRACE & SETBACKS)FOR FACADE REPAIR WORK AS PER PLAN. NO CHANGE IN USE EGRESS OR OCCUPANCY,PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER#33 OF 2014 THE NY BUILDING CODE.
On file for this project
7 documents
RoofTo Interior Renovation Existing Store1 filing · 20 docs
ArchitectureStructural
Issued Permit Scope
General Construction
TO PROPOSE INTERIOR RENOVATION FOR EXISTING STORE AT MEZZANINE & 001 FLOOR WITH GENERAL CONSTRUCTION AND INSTALL HVAC UNIT WITH MECHANICAL WORK AS PER PLAN FILED HEREWITH. NO CHANGE OF USE, EGRESS OR CERTIFICATE OF OCCUPANCY.
On file for this project
24 documents
Floor 1815th floor demolition and constructionUnder Construction1p · 1 filing · 20 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalStructuralOther
Issued Permit Scope
General Construction · Supported Scaffold
INTERIOR DEMOLITION OF NON-BEARING PARTITIONS & INSTALLATION OF NEW NON-BEARING GYP. BD. PARTITIONS, DOORS & FRAMES & FINISHES. NO CHANGE IN USE OCCUPANY OR EGRESS.
On file for this project
35 documents · 1 drawing sheet
Floor 17West 39-260 Real Estate. LLC2p · 2 filings · 13 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Plumbing · Supported Scaffold
INSTALLATION OF NEW NON-BEARING GYP. BD. PARTITIONS, DOORS & FRAMES & FINISHES. NO CHANGE IN USE OCCUPANY OR EGRESS.
On file for this project
10 documents · 2 drawing sheets
MINOR PLUMBING WORK AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
On file for this project
3 documents
Floor 16Tyler1p · 2 filings · 9 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Plumbing · Supported Scaffold
INSTALLATION OF PLUMBING FIXTURES ON NEW ROUGHING
On file for this project
4 documents · 1 drawing sheet
INTERIOR DEMOLITION OF NON-BEARING PARTITIONS & INSTALLATION OF NEW NON-BEARING GYP. BD. PARTITIONS, DOORS & FRAMES & FINISHES. NO CHANGE IN USE OCCUPANY OR EGRESS.
On file for this project
5 documents · 1 drawing sheet
Floor 1515th floor demolition and constructionUnder Construction3p · 1 filing · 20 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalStructuralOther
Issued Permit Scope
General Construction · Supported Scaffold
INTERIOR DEMOLITION OF NON-BEARING PARTITIONS & INSTALLATION OF NEW NON-BEARING GYP. BD. PARTITIONS, DOORS & FRAMES & FINISHES. NO CHANGE IN USE OCCUPANY OR EGRESS.
On file for this project
35 documents · 3 drawing sheets
Floor 14Interior signage installation1 filing · 5 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalStructuralOther
Issued Permit Scope
General Construction · Supported Scaffold
INTERIOR DEMOLITION OF NON-BEARING PARTITIONS & INSTALLATION OF NEW NON-BEARING GYP. BD. PARTITIONS, DOORS & FRAMES & FINISHES. NO CHANGE IN USE OCCUPANY OR EGRESS.
On file for this project
5 documents
Floor 13
Floor 1215th floor demolition and constructionUnder Construction1 filing · 20 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalStructuralOther
Issued Permit Scope
General Construction · Supported Scaffold
INTERIOR DEMOLITION OF NON-BEARING PARTITIONS & INSTALLATION OF NEW NON-BEARING GYP. BD. PARTITIONS, DOORS & FRAMES & FINISHES. NO CHANGE IN USE OCCUPANY OR EGRESS.
On file for this project
35 documents
Floor 1115th floor demolition and constructionUnder Construction1p · 3 filings · 20 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalStructuralOther
Issued Permit Scope
General Construction · Supported Scaffold
INTERIOR DEMOLITION OF NON-BEARING PARTITIONS & INSTALLATION OF NEW NON-BEARING GYP. BD. PARTITIONS, DOORS & FRAMES & FINISHES. NO CHANGE IN USE OCCUPANY OR EGRESS.
On file for this project
35 documents
INTERIOR DEMOLITION OF NON-BEARING PARTITIONS & INSTALLATION OF NEW NON-BEARING GYP. BD. PARTITIONS, DOORS & FRAMES & FINISHES. NO CHANGE IN USE OCCUPANY OR EGRESS.
On file for this project
4 documents · 1 drawing sheet
INTERIOR DEMOLITION OF NON-BEARING PARTITIONS & INSTALLATION OF NEW NON-BEARING GYP. BD. PARTITIONS, DOORS & FRAMES & FINISHES. NO CHANGE IN USE OCCUPANY OR EGRESS.
On file for this project
4 documents
Floor 10Interior partition demolition and installation1p · 1 filing · 5 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalStructuralOther
Issued Permit Scope
General Construction · Supported Scaffold
INTERIOR DEMOLITION OF NON-BEARING PARTITIONS & INSTALLATION OF NEW NON-BEARING GYP. BD. PARTITIONS, DOORS & FRAMES & FINISHES. NO CHANGE IN USE OCCUPANY OR EGRESS.
On file for this project
5 documents · 1 drawing sheet
Floor 915th floor demolition and constructionUnder Construction1 filing · 20 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalStructuralOther
Issued Permit Scope
General Construction · Supported Scaffold
INTERIOR DEMOLITION OF NON-BEARING PARTITIONS & INSTALLATION OF NEW NON-BEARING GYP. BD. PARTITIONS, DOORS & FRAMES & FINISHES. NO CHANGE IN USE OCCUPANY OR EGRESS.
On file for this project
35 documents
Floor 8New York Marriott plumbing work1 filing · 3 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
Plumbing · Supported Scaffold
JOB FILED HEREWITH TO Install new roughing and plumbing fixtures for relocation of existing toilets, installation of new ADA toilet and pantry. No change in use, occupancy or egress.
On file for this project
3 documents
Floor 715th floor demolition and constructionUnder Construction1p · 1 filing · 20 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalStructuralOther
Issued Permit Scope
General Construction · Supported Scaffold
INTERIOR DEMOLITION OF NON-BEARING PARTITIONS & INSTALLATION OF NEW NON-BEARING GYP. BD. PARTITIONS, DOORS & FRAMES & FINISHES. NO CHANGE IN USE OCCUPANY OR EGRESS.
On file for this project
35 documents · 1 drawing sheet
Floor 6West 39-260 Real Estate, LLC.4p · 2 filings · 16 docs
ArchitectureDMElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Plumbing · Supported Scaffold
INTERIOR DEMOLITION OF NON-BEARING PARTITIONS & INSTALLATION OF NEW NON-BEARING GYP. BD. PARTITIONS, DOORS & FRAMES & FINISHES. NO CHANGE IN USE OCCUPANY OR EGRESS.
On file for this project
9 documents · 4 drawing sheets
MINOR PLUMBING WORK AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, EGRESS.
On file for this project
7 documents
Floor 515th floor demolition and constructionUnder Construction1 filing · 20 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalStructuralOther
Issued Permit Scope
General Construction · Supported Scaffold
INTERIOR DEMOLITION OF NON-BEARING PARTITIONS & INSTALLATION OF NEW NON-BEARING GYP. BD. PARTITIONS, DOORS & FRAMES & FINISHES. NO CHANGE IN USE OCCUPANY OR EGRESS.
On file for this project
35 documents
Floor 4
Floor 3
Floor 2Demolition and relocation of doors1 filing · 10 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Supported Scaffold
INTERIOR RENOVATION TO BE DONE AS PER PLANS. NO CHANGE IN USE, EGRESS, OCCUPANCY.
On file for this project
10 documents
Floor 1Drama Bookstore3p · 7 filings · 20 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
Construction Fence · General Construction · Mechanical Systems · Plumbing · Sprinklers · Supported Scaffold
TO PROPOSE INTERIOR RENOVATION FOR EXISTING STORE AT MEZZANINE & 001 FLOOR WITH GENERAL CONSTRUCTION AND INSTALL HVAC UNIT WITH MECHANICAL WORK AS PER PLAN FILED HEREWITH. NO CHANGE OF USE, EGRESS OR CERTIFICATE OF OCCUPANCY.
On file for this project
24 documents
Modification to Sprinkler systems as per plans filed herewith. No change in use, occupancy or egress.
On file for this project
4 documents · 1 drawing sheet
Modify existing sprinkler system as per plan. No change to use, egress or occupancy under this application.
On file for this project
10 documents
Latest 3 of 7 filings on this floor.
MezzanineDrama Bookstore4p · 3 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalOther
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
TO PROPOSE INTERIOR RENOVATION FOR EXISTING STORE AT MEZZANINE & 001 FLOOR WITH GENERAL CONSTRUCTION AND INSTALL HVAC UNIT WITH MECHANICAL WORK AS PER PLAN FILED HEREWITH. NO CHANGE OF USE, EGRESS OR CERTIFICATE OF OCCUPANCY.
On file for this project
24 documents · 3 drawing sheets
Modify existing sprinkler system as per plan. No change to use, egress or occupancy under this application.
On file for this project
10 documents · 1 drawing sheet
Install new HVAC system and ventilation in existing retail space as per plan. No change to use egress or occupancy under this application.
On file for this project
6 documents
CellarThe Drama Book Shop, Drama Bookstore4p · 5 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
ESTABLISHING RETAIL USE AT CELLAR LEVEL WITH MINOR DEMOLITION OF DOORS AND NON-LOAD BEARING PARTIONS.
On file for this project
12 documents · 2 drawing sheets
Modification to Sprinkler systems as per plans filed herewith. No change in use, occupancy or egress.
On file for this project
4 documents · 1 drawing sheet
Modify existing sprinkler system as per plan. No change to use, egress or occupancy under this application.
On file for this project
10 documents
Latest 3 of 5 filings on this floor.
Site & exteriorPipe scaffold installation2 filings · 9 docs
ElectricalGeneralStructural
Issued Permit Scope
Sidewalk Shed · Supported Scaffold
INSTALLATION OF TEMPORARY 120' HIGH PIPE SCAFFOLD ORIGINATING (OFF SHED) FOR FACADE REPAIR WORK AS PER PLAN. NO CHANGE IN USE EGRESS OR OCCUPANCY,PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER#33 OF 2014 THE NY BUILDING CODE.HEAVY DUTY SIDEWALK SHED FILED UNDER
On file for this project
5 documents · 4 drawing sheets
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE.LIVE LOAD 300PSF.
On file for this project
4 documents · 4 drawing sheets