| Owner | Filings | Most Recent |
|---|---|---|
| 261 East 78th Realty | 95 | 03/21/2026 |
| LT 78th St | 10 | 03/21/2026 |
| Okada & Company | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/23/2017 | $17.0M | — | 261 EAST 78 STREET LOFTS LLC → PERFECT JSK CORP. | $965/sf building |
| 02/27/2014 | $16.0M | — | 261 EAST 78 REALTY CORP. → 261 EAST 78 STREET LOFTS LLC | $908/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| All City Engineering | 6 | 12/21/2022 |
| MW Professional Engineering | 4 | 05/12/2022 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Kedc | General Contractor | 6 | 07/08/2026 |
| Asco Sprinkler Co | Fire Protection | 4 | 07/08/2026 |
| Katan P & H | Plumbing | 4 | 07/08/2026 |
| PM Electrical Maintenance | Electrical | 2 | 03/22/2026 |
| Kwong Ming Electric | Electrical | 1 | 03/21/2026 |
| LT 78th St | General Contractor | 1 | 03/22/2026 |
| Hudson Meridian Construction | General Contractor | 1 | 03/22/2026 |
| Angelo S NG | Electrical | 1 | 03/21/2026 |
| Delco Electrical | Electrical | 1 | 03/21/2026 |
| Ralph Mottola | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| All City Engineering | 7115 | 6 | 12/21/2022 |
| MW Professional Engineering | 570 | 4 | 05/12/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Signed-off | Asco Sprinkler Co | 08/04/2022 |
| DOB NOW | Sprinklers | Signed-off | Asco Sprinkler Co | 08/04/2022 |
| DOB NOW | Plumbing | Signed-off | Katan P & H | 01/16/2022 |
| DOB NOW | Plumbing | Signed-off | Katan P & H | 01/16/2022 |
| DOB NOW | Sprinklers | Signed-off | Asco Sprinkler Co | 08/24/2021 |
| DOB NOW | Sprinklers | Signed-off | Asco Sprinkler Co | 08/24/2021 |
| DOB NOW | Plumbing | Signed-off | Katan P & H | 08/05/2021 |
| DOB NOW | Mechanical Systems | Signed-off | Kedc | 08/03/2021 |
| DOB NOW | Mechanical Systems | Signed-off | Kedc | 08/03/2021 |
| DOB NOW | Plumbing | Signed-off | Katan P & H | 06/16/2021 |
| DOB NOW | General Construction | Signed-off | Kedc | 05/26/2021 |
| DOB NOW | General Construction | Signed-off | Kedc | 05/26/2021 |
| BIS | — | ISSUED | LT 78th St | 02/05/2024 |
| BIS | PL | ISSUED | Water Dynamic P & H | 03/25/2016 |
| BIS | MH | ISSUED | Superior Builders II | 03/25/2016 |
| BIS | SP | ISSUED | Anesis Services | 03/24/2016 |
| BIS | SP | ISSUED | Doval Plumbing & Heating | 03/18/2016 |
| BIS | PL | ISSUED | Aqueduct Plumbing & Mechanical | 02/11/2016 |
| BIS | SP | ISSUED | Aqueduct Plumbing & Mechanical | 02/11/2016 |
| BIS | OT | ISSUED | Superior Builders II | 01/28/2016 |
| BIS | PL | ISSUED | Dyckman Plumbing and Heating | 07/17/2015 |
| BIS | MH | ISSUED | Super Power Construction | 07/17/2015 |
| BIS | SP | ISSUED | Dyckman Plumbing and Heating | 01/13/2015 |
| BIS | MH | ISSUED | Super Power Construction | 12/19/2014 |
| BIS | OT | ISSUED | Super Power Construction | 12/09/2014 |
| BIS | PL | ISSUED | Tri State Plumbing & Heating | 12/09/2014 |
| BIS | SP | ISSUED | Aggressive Fire Protection | 11/07/2014 |
| BIS | OT | ISSUED | Legacy Builders/Developers | 06/28/2013 |
| BIS | MH | ISSUED | Legacy Builders/Developers | 06/28/2013 |
| BIS | PL | ISSUED | Senid PL & Heating | 03/13/2013 |
| BIS | MH | ISSUED | Legacy Builders/Developers | 01/29/2013 |
| BIS | OT | ISSUED | Legacy Builders/Developers | 01/29/2013 |
| BIS | SP | ISSUED | Approved Plumbing and Fire PR | 07/24/2012 |
| BIS | SP | ISSUED | Approved Plumbing and Fire PR | 07/11/2012 |
| BIS | PL | ISSUED | Par Plumbing Co | 06/19/2012 |
| BIS | MH | ISSUED | 200 E 79th Street Construction | 06/15/2012 |
| BIS | OT | ISSUED | 200 E 79th Street Construction | 06/15/2012 |
| BIS | SP | ISSUED | Demar Plumbing | 03/15/2011 |
| BIS | SP | ISSUED | Demar Plumbing | 03/15/2011 |
| BIS | PL | ISSUED | Demar Plumbing | 01/31/2011 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/08/2021 | Complete | PM Electrical Maintenance | General Wiring |
| 06/08/2021 | Complete | PM Electrical Maintenance | — |
| 10/13/2020 | Complete | Bay Electric | 7 new_meters |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/04/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/08/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/04/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/17/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/16/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/20/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/22/2022 | Fire-Resistant Penetrations and Joints | Liangkai Xia | special |
| 12/22/2022 | HVAC-R and service water piping design and insulation | Liangkai Xia | energy_progress |
| 12/22/2022 | Energy Code Compliance Inspections | Liangkai Xia | progress |
| 12/22/2022 | Sprinkler Systems | Liangkai Xia | special |
| 12/16/2022 | Sprinkler Systems | Liangkai Xia | special |
| 12/16/2022 | HVAC-R and service water piping design and insulation | Liangkai Xia | energy_progress |
| 12/16/2022 | Energy Code Compliance Inspections | Liangkai Xia | progress |
| 12/16/2022 | Fire-Resistant Penetrations and Joints | Liangkai Xia | special |
| 05/12/2022 | Fire-Resistance Rated Construction | MING WAI WONG | progress |
| 05/12/2022 | Fire-Resistant Penetrations and Joints | MING WAI WONG | special |
| 05/12/2022 | Final | MING WAI WONG | progress |
| 05/12/2022 | Interior lighting power | MING WAI WONG | energy_progress |
| 05/04/2022 | Fire-Resistant Penetrations and Joints | MING WAI WONG | special |
| 05/04/2022 | Fire-Resistant Penetrations and Joints | MING WAI WONG | special |
| 05/04/2022 | Final | MING WAI WONG | progress |
| 05/04/2022 | Interior lighting power | MING WAI WONG | energy_progress |
| 05/04/2022 | Fire-Resistance Rated Construction | MING WAI WONG | progress |
| 05/04/2022 | Interior lighting power | MING WAI WONG | energy_progress |
| 05/04/2022 | Fire-Resistance Rated Construction | MING WAI WONG | progress |
| 05/04/2022 | Final | MING WAI WONG | progress |
| 10/21/2021 | Fire-Resistant Penetrations and Joints | Liangkai Xia | special |
| 10/21/2021 | Energy Code Compliance Inspections | Liangkai Xia | progress |
| 10/21/2021 | HVAC-R and service water piping design and insulation | Liangkai Xia | energy_progress |
| 10/21/2021 | Sprinkler Systems | Liangkai Xia | special |
| 03/31/2021 | Energy Code Compliance Inspections | Liangkai Xia | progress |