2646 EAST 18TH STREET
BROOKLYN · BIN 3204974
💬 Discuss this project
2021Year Built
7Stories
H3Building Class
C4-2Zoning
20,376 sfGross Floor Area
1Units
Rent Stabilized0 Active ViolationsFDNY Report ↗
Limited service hotel, often national chain · Owner of record: Sheepshead Capital · 5,700 sf lot · 3.57 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentLandscapeCivilGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofMechanical system installation28p · 5 filings · 20 docs
BulkheadMechanical system installation7p · 3 filings · 20 docs
Floor 7Mechanical system installation28p · 4 filings · 20 docs
Floor 6Mechanical system installation27p · 4 filings · 20 docs
Floor 5Mechanical system installation25p · 4 filings · 20 docs
Floor 4Mechanical system installation25p · 4 filings · 20 docs
Floor 3Mechanical system installation25p · 4 filings · 20 docs
Floor 2Mechanical system installation25p · 4 filings · 20 docs
Floor 1Mechanical system installation27p · 4 filings · 20 docs
CellarMechanical system installation27p · 4 filings · 20 docs
Site & exteriorBychoicehotels75p · 7 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Rathod2207/08/2026
Sheepshead Capital1303/22/2026
850 Fourth Ave Associates503/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/09/2019$1.5M—2103 AVENUE Z LLC → SHEEPSHEAD CAPITAL LLC— not available
06/16/2015$332K—Private party → 2103 AVENUE Z LLC— not available
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Green Studio1403/21/2026
Michael Kang Architect P1003/21/2026
CNY Engineering603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
All Borough Group ServiceGeneral Contractor907/08/2026
Dynamic InstallationScaffold807/08/2026
All Borough Group ServiceScaffold407/08/2026
RRP PlumbingPlumbing307/08/2026
RRP PlumbingFire Protection307/08/2026
Michael KangElectrical203/21/2026
Service Sign Erectors CoSign hanger107/08/2026
Kwong Ming ElectricElectrical103/22/2026
Dynamic InstallationGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Triangle Inspection & Tes7495803/21/2023
MJ Engineering & Design5546508/20/2021
Building Lifecycle
All (168)Filed (17)Permit Issued (18)Signed Off (10)Violation (24)Inspection (9)Objection (60)Special Inspection (30)
07/01/2026
Violation issued (ECB, closed)
Boilers
02/06/2025
Violation issued (HPD, closed)
C
02/06/2025
Violation issued (HPD, closed)
A
09/14/2023
Violation issued (FDNY_ORDER, closed)
09/14/2023
Violation issued (FDNY_ORDER, closed)
06/27/2023
Signed off — Alteration
B00816562-I1
06/20/2023
Signed off — Alteration
B00370119-I1
05/17/2023
Signed off — Alteration
INSTALL NEW HVAC SYSTEM IN 7 STORIES WITH CELLAR HOTEL. NO CHANGE OF USE, EGRESS AND OCCUPANCY. FILED IN CONJUNCTION WITH NB#322019828.
B00339271-I1
03/23/2023
Special inspection requirement — Electrical motors
Rajasekhar Sakhamuri
03/23/2023
Special inspection requirement — Maintenance information
Rajasekhar Sakhamuri
03/23/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Rajasekhar Sakhamuri
03/23/2023
Special inspection requirement — Mechanical Systems
Rajasekhar Sakhamuri
03/23/2023
Special inspection requirement — Fire-Resistance Rated Construction
Rajasekhar Sakhamuri
03/23/2023
Special inspection requirement — Energy Code Compliance Inspections
Rajasekhar Sakhamuri
03/23/2023
Special inspection requirement — Final
Rajasekhar Sakhamuri
03/23/2023
Special inspection requirement — HVAC and service water heating equipment
Rajasekhar Sakhamuri
03/23/2023
Special inspection requirement — HVAC and service water heating system controls
Rajasekhar Sakhamuri
03/23/2023
Special inspection requirement — HVAC insulation and sealing
Rajasekhar Sakhamuri
03/23/2023
Special inspection requirement — Shutoff dampers
Rajasekhar Sakhamuri
03/21/2023
Filed — Alteration
INSTALL NEW HVAC SYSTEM IN 7 STORIES WITH CELLAR HOTEL. NO CHANGE OF USE, EGRESS AND OCCUPANCY. FILED IN CONJUNCTION WITH NB#322019828.
B00339271-P2
03/17/2023
Special inspection requirement — HVAC insulation and sealing
Rajasekhar Sakhamuri
03/17/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Rajasekhar Sakhamuri
03/17/2023
Special inspection requirement — Mechanical Systems
Rajasekhar Sakhamuri
03/17/2023
Special inspection requirement — Energy Code Compliance Inspections
Rajasekhar Sakhamuri
03/17/2023
Special inspection requirement — Final
Rajasekhar Sakhamuri
03/17/2023
Special inspection requirement — Fire-Resistance Rated Construction
Rajasekhar Sakhamuri
03/17/2023
Special inspection requirement — Electrical motors
Rajasekhar Sakhamuri
03/17/2023
Special inspection requirement — HVAC and service water heating equipment
Rajasekhar Sakhamuri
03/17/2023
Special inspection requirement — Shutoff dampers
Rajasekhar Sakhamuri
03/17/2023
Special inspection requirement — Maintenance information
Rajasekhar Sakhamuri
03/17/2023
Special inspection requirement — HVAC and service water heating system controls
Rajasekhar Sakhamuri
03/02/2023
Objection resolved — Addressed
02/28/2023
Objection raised — Other
02/23/2023
Filed — Alteration
INSTALL NEW HVAC SYSTEM IN 7 STORIES WITH CELLAR HOTEL. NO CHANGE OF USE, EGRESS AND OCCUPANCY. FILED IN CONJUNCTION WITH NB#322019828.
B00339271-P1
02/13/2023
Signed off — Alteration
Install new plumbing and sprinkler system for new building in conjunction with NB job #322019828. No change in use,egress and occupancy.
B00339075-I1
02/13/2023
Signed off — Alteration
B00357055-I1
02/13/2023
Signed off — Alteration
INSTALL FUEL STORAGE TANK, OIL TRANSFER PUMP, OIL TRANSFER PIPING AND GENERATOR FOR 7 STORIES HOTEL IN CONJUNCTION OF DOB NB# 322019828. NO CHANGE OF USE,EGRESS AND OCCUPANCY.
B00353154-I1
02/13/2023
Special inspection requirement — Maintenance information
Rajasekhar Sakhamuri
02/13/2023
Special inspection requirement — Shutoff dampers
Rajasekhar Sakhamuri
02/13/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Rajasekhar Sakhamuri
02/13/2023
Special inspection requirement — Mechanical Systems
Rajasekhar Sakhamuri
02/13/2023
Special inspection requirement — Energy Code Compliance Inspections
Rajasekhar Sakhamuri
02/13/2023
Special inspection requirement — Final
Rajasekhar Sakhamuri
02/13/2023
Special inspection requirement — Fire-Resistance Rated Construction
Rajasekhar Sakhamuri
02/13/2023
Special inspection requirement — HVAC and service water heating equipment
Rajasekhar Sakhamuri
02/02/2023
Permit issued — Mechanical Systems
B00339271-I1-MS
01/27/2023
Permit issued — Structural
B00370119-I1-ST
01/24/2023
Permit issued — Sign
B00816562-I1-SG
01/23/2023
Filed — Alteration
B00816562-I1
01/13/2023
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
01/13/2023
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
01/12/2023
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
01/10/2023
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
12/23/2022
Objection resolved — Addressed
12/22/2022
Objection raised — Other
12/19/2022
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
12/09/2022
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
12/08/2022
Violation issued (ECB, closed)
Boilers
12/06/2022
Filed — Alteration
INSTALL FUEL STORAGE TANK, OIL TRANSFER PUMP, OIL TRANSFER PIPING AND GENERATOR FOR 7 STORIES HOTEL IN CONJUNCTION OF DOB NB# 322019828. NO CHANGE OF USE,EGRESS AND OCCUPANCY.
B00353154-P1
12/01/2022
Objection resolved — Addressed
Latest 60 of 168 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offAll Borough Group Service02/02/2023
DOB NOWStructuralSigned-offAll Borough Group Service01/27/2023
DOB NOWSignSigned-offService Sign Erectors Co01/24/2023
DOB NOWPlumbingSigned-offRRP Plumbing11/28/2022
DOB NOWSprinklersSigned-offRalph W. Landolfi JR11/14/2022
DOB NOWConstruction FenceSigned-offAll Borough Group Service09/16/2022
DOB NOWBoiler EquipmentSigned-offNew York Heating06/17/2022
DOB NOWConstruction FenceSigned-offAll Borough Group Service10/01/2021
DOB NOWPlumbingSigned-offRRP Plumbing08/13/2021
DOB NOWSprinklersSigned-offRalph W. Landolfi JR08/12/2021
DOB NOWProtection and Mechanical MethodsSigned-offDynamic Installation07/29/2021
DOB NOWProtection and Mechanical MethodsSigned-offDynamic Installation07/19/2021
DOB NOWPlumbingSigned-offRRP Plumbing06/10/2021
DOB NOWSprinklersSigned-offRalph W. Landolfi JR06/09/2021
DOB NOWGeneral ConstructionSigned-offDynamic Installation04/13/2021
DOB NOWSupported ScaffoldSigned-offDynamic Installation04/02/2021
DOB NOWSupported ScaffoldSigned-offDynamic Installation04/02/2021
DOB NOWConstruction FenceSigned-offAll Borough Group Service10/26/2020
BIS—ISSUEDAll Borough Group Service09/16/2022
BIS—ISSUEDAll Borough Group Service09/28/2021
BIS—ISSUEDAll Borough Group Service09/28/2021
BIS—ISSUEDAll Borough Group Service01/22/2021
BIS—ISSUEDAll Borough Group Service01/22/2021
BIS—ISSUEDDynasty Contracting01/08/2021
BIS—ISSUEDDynasty Contracting01/08/2021
BIS—ISSUEDDynasty Contracting12/15/2020
BIS—ISSUEDDynasty Contracting12/15/2020
3 projects · most recent 02/03/2023
General Wiring
FiledStatusContractorScope
02/03/2023CompleteRightway ElectricalGeneral Wiring
05/07/2021CompleteRichard Neu—
04/22/2021CompleteKwong Ming Electric—
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
01/13/2023Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
01/13/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/12/2023Pass-Final PL - Up to 9 Requested FloorsPassView ↗
01/10/2023Pass-Final Boiler Equipment InspectionPassView ↗
12/19/2022Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
12/09/2022Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/18/2022Fail-Final Boiler Equipment InspectionFailView ↗
02/02/2022Pass-Final PL - Up to 9 Requested FloorsPassView ↗
09/30/2021Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 43
DateRequirementInspectorRole
03/23/2023Electrical motorsRajasekhar Sakhamurienergy_progress
03/23/2023Maintenance informationRajasekhar Sakhamurienergy_progress
03/23/2023Fire-Resistant Penetrations and JointsRajasekhar Sakhamurispecial
03/23/2023Mechanical SystemsRajasekhar Sakhamurispecial
03/23/2023Fire-Resistance Rated ConstructionRajasekhar Sakhamuriprogress
03/23/2023Energy Code Compliance InspectionsRajasekhar Sakhamuriprogress
03/23/2023FinalRajasekhar Sakhamuriprogress
03/23/2023HVAC and service water heating equipment Rajasekhar Sakhamurienergy_progress
03/23/2023HVAC and service water heating system controls Rajasekhar Sakhamurienergy_progress
03/23/2023HVAC insulation and sealing Rajasekhar Sakhamurienergy_progress
03/23/2023Shutoff dampersRajasekhar Sakhamurienergy_progress
03/17/2023HVAC insulation and sealing Rajasekhar Sakhamurienergy_progress
03/17/2023Fire-Resistant Penetrations and JointsRajasekhar Sakhamurispecial
03/17/2023Mechanical SystemsRajasekhar Sakhamurispecial
03/17/2023Energy Code Compliance InspectionsRajasekhar Sakhamuriprogress
03/17/2023FinalRajasekhar Sakhamuriprogress
03/17/2023Fire-Resistance Rated ConstructionRajasekhar Sakhamuriprogress
03/17/2023Electrical motorsRajasekhar Sakhamurienergy_progress
03/17/2023HVAC and service water heating equipment Rajasekhar Sakhamurienergy_progress
03/17/2023Shutoff dampersRajasekhar Sakhamurienergy_progress
03/17/2023Maintenance informationRajasekhar Sakhamurienergy_progress
03/17/2023HVAC and service water heating system controls Rajasekhar Sakhamurienergy_progress
02/13/2023Maintenance informationRajasekhar Sakhamurienergy_progress
02/13/2023Shutoff dampersRajasekhar Sakhamurienergy_progress
02/13/2023Fire-Resistant Penetrations and JointsRajasekhar Sakhamurispecial
Latest 25 of 43.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
BychoicehotelsHotel / Lodging—
Project B00816562 Alteration · LOC Issued · 01/23/2023
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 206 on file (BIS + DOB NOW)
▸Plans & Drawings19
▸DOB NOWPlans/Sketch8
09/01/2026B00498629-I1Request digital key ↗
09/01/2026B00556897-I1Request digital key ↗
09/01/2026B00516342-P1Request digital key ↗
Showing 3 of 8 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems3
09/02/2026B00339271-I1Request digital key ↗
09/02/2026B00339271-P2Request digital key ↗
08/14/2026B00339271-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Boiler Equipment2
08/28/2026B00353154-I1Request digital key ↗
08/14/2026B00353154-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing2
09/02/2026B00339075-I1Request digital key ↗
08/15/2026B00339075-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler2
09/02/2026B00339075-I1Request digital key ↗
08/15/2026B00339075-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
09/02/2026B00357055-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural1
09/02/2026B00370119-I1Request digital key ↗
▸Applications & Permits24
▸BISPLAN / WORK APPROVAL APPLICATION11
09/14/2023322019828Open ↗
09/08/2023322019828Open ↗
02/14/2023322019828Open ↗
Showing 3 of 11 on file for this type
▸BISWORK PERMIT APPLICATION8
01/27/2021322019828Open ↗
01/27/2021322019828Open ↗
12/23/2020322019828Open ↗
Showing 3 of 8 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION4
10/26/2023322019828Open ↗
05/01/2023322019828Open ↗
03/08/2023322019828Open ↗
Showing 3 of 4 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation1
06/13/2022340734058Open ↗
▸Zoning, Tax Lot & Property Records7
▸BISTAX LOT: FINAL LOT NUMBER ISSUED1
06/10/2022340734058Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
07/22/2020322019828Open ↗
▸BISVERIFY TAX LOT1
10/26/2023322019828Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
02/23/2023322019828Open ↗
▸BISZONING DIAGRAM1
07/22/2020322019828Open ↗
▸BISFLOOD ZONE DESIGN CERTIFICATION1
07/22/2020322019828Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
07/22/2020322019828Open ↗
▸Seals & Professional Certifications62
▸DOB NOWProgress Inspector Seal & Signature30
09/29/2026B00339271-P2Open ↗
09/29/2026B00339271-P2Open ↗
09/29/2026B00339271-P2Open ↗
Showing 3 of 30 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature17
08/27/2026B00816562-I1Open ↗
08/13/2026B00516342-P1Open ↗
08/13/2026B00478971-P2Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature13
09/29/2026B00339271-P2Open ↗
09/29/2026B00339271-P2Open ↗
09/01/2026B00516342-P1Open ↗
Showing 3 of 13 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
05/13/2020322019828Open ↗
12/24/2019322019828Open ↗
▸Trade Schedules & Equipment4
▸BISHVAC & SERVICE WATER HEATING EQUIPMENT1
01/19/2023322019828Open ↗
▸BISFIRE ALARM/SIGNAL SYSTEM (FA) SIGNOFF1
02/23/2023322019828Open ↗
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS1
01/19/2023322019828Open ↗
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
02/28/2023322019828Open ↗
▸Safety & Tenant Protection7
▸BISSTREET TREE SIGNOFF2
06/15/2023340734058Open ↗
02/23/2023322019828Open ↗
▸BISSTREET TREE CHECKLIST2
06/10/2022340734058Open ↗
12/24/2019322019828Open ↗
▸BISBPP: STREET TREES SITE PLAN1
06/13/2022340734058Open ↗
▸BISSTREET TREES SITE PLAN1
06/10/2022340734058Open ↗
▸BISEXCAVATION - SHEETING, SHORING, AND BRACING1
01/12/2022322019828Open ↗
▸Energy Compliance15
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
02/28/2023322019828Open ↗
11/05/2020322019828Open ↗
07/22/2020322019828Open ↗
▸BISINTERIOR LIGHTING POWER1
01/19/2023322019828Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
01/19/2023322019828Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
01/19/2023322019828Open ↗
▸BISFENESTRATION AREAS1
01/19/2023322019828Open ↗
▸BISAIR SEALING AND INSULATION - TESTING1
02/28/2023322019828Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
01/19/2023322019828Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
02/23/2023322019828Open ↗
▸BISLIGHTING CONTROLS1
01/19/2023322019828Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
12/24/2019322019828Open ↗
▸BISEXTERIOR LIGHTING POWER1
01/19/2023322019828Open ↗
▸BISFENESTRATION AIR LEAKAGE1
01/19/2023322019828Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026B00339271-I1Open ↗
▸Inspections & Test Reports18
▸BISTECHNICAL REPORT: RESPONSIBILITY9
11/23/2021322019828Open ↗
11/23/2021322019828Open ↗
07/26/2021322019828Open ↗
Showing 3 of 9 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
03/09/2023322019828Open ↗
12/23/2020322019828Open ↗
▸BISTR3: CONCRETE DESIGN MIX TECHNICAL REPORT1
12/30/2020322019828Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
02/23/2023322019828Open ↗
▸BISSUBGRADE INSP / SOILS-SITE PREP1
01/12/2022322019828Open ↗
▸BISSOIL REPORT1
07/22/2020322019828Open ↗
▸BISFOOTING AND FOUNDATION INSPECTION1
01/12/2022322019828Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
07/22/2020322019828Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
12/23/2020322019828Open ↗
▸Approvals, Objections & Sign-offs9
▸BISSCHEDULE A - OCCUPANCY / USE9
09/14/2023322019828Open ↗
09/08/2023322019828Open ↗
12/22/2022322019828Open ↗
Showing 3 of 9 on file for this type
▸Cost, Insurance & Ownership7
▸BISPROJECT SPECIFIC GENERAL LIABILITY INSURANCE3
11/12/2020322019828Open ↗
10/30/2020322019828Open ↗
10/30/2020322019828Open ↗
▸BISPROJECT-SPECIFIC GL INSURANCE2
01/27/2021322019828Open ↗
12/23/2020322019828Open ↗
▸BISAcord 25 (Acord Certificate of Liability Insurance)2
01/27/2021322019828Open ↗
12/23/2020322019828Open ↗
▸Filing & Intake Forms12
▸BISADDITIONAL INFORMATION8
10/26/2023322019828Open ↗
03/09/2023322019828Open ↗
02/21/2023322019828Open ↗
Showing 3 of 8 on file for this type
▸BISEFILING COVER SHEET2
05/13/2020322019828Open ↗
12/24/2019322019828Open ↗
▸BISBOROUGH INTAKE FORM2
01/27/2021322019828Open ↗
12/23/2020322019828Open ↗
▸Other Documents14
▸BISBPP - SUPPORTING DOCUMENTATION3
06/10/2022340734058Open ↗
06/10/2022340734058Open ↗
06/10/2022340734058Open ↗
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION2
07/22/2020322019828Open ↗
07/22/2020322019828Open ↗
▸BISSUSTAINABLE ROOF ZONE FORM1
07/22/2020322019828Open ↗
▸BISLOWEST FLOOR ELEVATION1
02/23/2023322019828Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
12/24/2019322019828Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
06/10/2022340734058Open ↗
▸BISMAINTENANCE INFORMATION1
01/19/2023322019828Open ↗
▸BISHVAC & SERVICE WATER PIPING DESIGN AND INSULATION1
01/19/2023322019828Open ↗
▸BISEMERGENCY GENERATOR1
02/21/2023322019828Open ↗
▸BISPLOT DIAGRAM1
07/22/2020322019828Open ↗
▸BISFEMA ELEVATION CERT (086-0-33)/ FLOODPROOFING CERT (086-0-34)1
02/21/2023322019828Open ↗