| Owner | Filings | Most Recent |
|---|---|---|
| LBS CONSULTING SERVICES | 56 | 07/08/2026 |
| PROFESSIONAL LINE CORP | 11 | 03/22/2026 |
| 2652 E 18 STREET | 3 | 03/21/2026 |
| 177 WEST END AVE | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KINDO HOLDINGS, LLC | 13 | 07/22/2024 |
| ENTHINK ENGINEERS LLC | 3 | 10/26/2021 |
| DOKA ENGINEERING PC | 2 | 09/10/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| LBS CONSULTING SERVICES | 28 | 03/21/2026 |
| ALEXANDER TRUBIN DESIGN | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NADKOS INC | General Contractor | 8 | 07/08/2026 |
| PROFESSIONAL LINE CORP | General Contractor | 6 | 03/21/2026 |
| G-NADO INC | General Contractor | 6 | 07/08/2026 |
| AMOK INC | Plumbing | 3 | 07/08/2026 |
| CHESAKL ENTERPRISES INC | General Contractor | 3 | 03/21/2026 |
| AMOK INC | Fire Protection | 2 | 07/08/2026 |
| ZARINA KINDO | Electrical | 1 | 03/21/2026 |
| BENJAMIN DREBIN | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ZARINA KINDO, RA | 4900 | 6 | 07/22/2024 |
| A&B WORLD CONSULTING, INC | 5704 | 1 | 06/17/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | NADKOS INC | 10/01/2024 |
| DOB NOW | Plumbing | Signed-off | AMOK INC | 08/27/2024 |
| DOB NOW | Sprinklers | Signed-off | AMOK INC | 09/22/2022 |
| DOB NOW | Mechanical Systems | Signed-off | G-NADO INC | 09/19/2022 |
| DOB NOW | Curb Cut | Signed-off | G-NADO INC | 08/17/2022 |
| DOB NOW | Sprinklers | Signed-off | AMOK INC | 11/19/2021 |
| DOB NOW | Plumbing | Signed-off | AMOK INC | 11/10/2021 |
| DOB NOW | Supported Scaffold | Signed-off | PROFESSIONAL LINE CORP | 10/12/2021 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CHESAKL ENTERPRISES INC | 09/20/2021 |
| DOB NOW | Construction Fence | Signed-off | NADKOS INC | 09/03/2021 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | G-NADO INC | 07/06/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | PROFESSIONAL LINE CORP | 05/25/2021 |
| DOB NOW | Structural | Signed-off | G-NADO INC | 05/21/2021 |
| DOB NOW | Plumbing | Signed-off | AMOK INC | 03/10/2021 |
| DOB NOW | Foundation | Signed-off | G-NADO INC | 02/23/2021 |
| DOB NOW | Construction Fence | Signed-off | NADKOS INC | 01/21/2021 |
| DOB NOW | Construction Fence | Signed-off | NADKOS INC | 10/04/2019 |
| DOB NOW | Construction Fence | Signed-off | NADKOS INC | 07/19/2019 |
| BIS | — | ISSUED | G-NADO INC | 08/31/2022 |
| BIS | — | ISSUED | G-NADO INC | 01/24/2022 |
| BIS | — | ISSUED | G-NADO INC | 01/22/2021 |
| BIS | CC | ISSUED | OWNER | 05/11/1999 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/22/2024 | Permit Issued | NADKOS INC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Cooper & Hunter CH-12SPH-230VO 12,000 BTU · Heat Pump Outdoor ×1 CH-36LCUO 36,000 BTU · Heat Pump Outdoor ×1 Ventilation S&P Usa Ventilation Systems TR-300 300 CFM · Erv ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/22/2024 | Signed-off | AMOK INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/08/2024 | Complete | ACCURATE ELEC'L CORP. | General Wiring |
| 12/28/2022 | Complete | ACCURATE ELEC'L CORP. | General Wiring |
| 01/25/2022 | Complete | STAR ELEC'L CONTRACTORS C | — |
| 05/25/2021 | Complete | RICHARD NEU | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/18/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/18/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/26/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/09/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/30/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/30/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 02/09/2023 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 09/29/2022 | Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test | Certified | View ↗ |
| 09/29/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/26/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/15/2024 | Fire-Resistant Penetrations and Joints | ZARINA KINDO | special |
| 08/10/2024 | HVAC-R and service water heating equipment | ZARINA KINDO | energy_progress |
| 08/10/2024 | HVAC-R and service water piping design and insulation | ZARINA KINDO | energy_progress |
| 08/10/2024 | HVAC-R and service water heating system controls | ZARINA KINDO | energy_progress |
| 08/05/2024 | Maintenance information | ZARINA KINDO | energy_progress |
| 08/05/2024 | HVAC-R and service water heating system controls | ZARINA KINDO | energy_progress |
| 08/05/2024 | HVAC-R and service water piping design and insulation | ZARINA KINDO | energy_progress |
| 08/05/2024 | HVAC-R and service water heating equipment | ZARINA KINDO | energy_progress |
| 08/05/2024 | Air barrier - visual inspection | ZARINA KINDO | energy_progress |
| 07/22/2024 | Tenant Protection Plan Compliance | ZARINA KINDO | special |
| 07/18/2024 | Masonry | ZARINA KINDO | special |
| 07/18/2024 | Lighting controls | ZARINA KINDO | energy_progress |
| 07/18/2024 | Interior lighting power | ZARINA KINDO | energy_progress |
| 07/18/2024 | Insulation placement and R values | ZARINA KINDO | energy_progress |
| 05/01/2024 | Lowest Floor Elevation | ZARINA KINDO | progress |
| 02/19/2024 | Final | JAMES NAPOLI | progress |
| 02/19/2024 | Mechanical Systems | ZARINA KINDO | special |
| 01/08/2021 | Footing and Foundation | ZARINA KINDO | progress |
| 01/08/2021 | Final | ZARINA KINDO | progress |
| 12/17/2020 | HVAC and service water heating equipment | ZARINA KINDO | energy_progress |
| 12/17/2020 | HVAC and service water heating system controls | ZARINA KINDO | energy_progress |
| 12/17/2020 | Final | XIONGCAI GU | progress |
| 12/17/2020 | Mechanical Systems | ZARINA KINDO | special |
| 12/17/2020 | HVAC insulation and sealing | ZARINA KINDO | energy_progress |
| 12/17/2020 | Shutoff dampers | ZARINA KINDO | energy_progress |