| Owner | Filings | Most Recent |
|---|---|---|
| 2659 WEBSTER REALTY | 76 | 07/08/2026 |
| NYCSCA | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| YSRAEL A. SEINUK, P.C. | 3 | 05/22/2023 |
| VELOCITY ARCHITECTURAL SERVICES PLL | 6 | 05/09/2023 |
| AK CONSULTING SERVICES, INC | 1 | 11/18/2022 |
| CELIN MUNOZ CONSULTING ENGINEER, PC | 2 | 07/13/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| JMV ASSOCIATES | 18 | 03/21/2026 |
| DALESSANDRO ASSOCIATES | 4 | 03/21/2026 |
| AK CONSULTING SERVICES | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ASHNU INTERNATIONAL INC | General Contractor | 7 | 07/08/2026 |
| ACS SYSTEM ASSOCIATES INC. | General Contractor | 2 | 03/21/2026 |
| C.I. CONTRACTING CORP | General Contractor | 2 | 03/21/2026 |
| MAR-SAL PLBG & HTG, INC | Plumbing | 2 | 07/08/2026 |
| SELECTRIC ELECL CONT CO I | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TWIN PEAKS INC. | 317 | 10 | 05/22/2023 |
| CELIN MUNOZ CONSULTING EN | 1064 | 2 | 07/13/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | ERNEST KURIQI | 07/26/2023 |
| DOB NOW | Construction Fence | Signed-off | ERNEST KURIQI | 01/10/2023 |
| DOB NOW | Structural | Signed-off | ERNEST KURIQI | 12/22/2022 |
| DOB NOW | Plumbing | Signed-off | MAR-SAL PLBG & HTG, INC | 11/15/2022 |
| DOB NOW | Standpipe | Signed-off | MAR-SAL PLBG & HTG, INC | 11/15/2022 |
| DOB NOW | General Construction | Signed-off | ERNEST KURIQI | 10/31/2022 |
| DOB NOW | Mechanical Systems | Signed-off | ACS SYSTEM ASSOCIATES INC. | 10/31/2022 |
| DOB NOW | Structural | Signed-off | C.I. CONTRACTING CORP | 05/19/2022 |
| BIS | — | ISSUED | C.I. CONTRACTING CORP | 06/08/2023 |
| BIS | EQ | ISSUED | C.I. CONTRACTING CORP | 06/03/2022 |
| BIS | — | ISSUED | C.I. CONTRACTING CORP | 05/10/2022 |
| BIS | PL | ISSUED | AQUA PLUMBING & HTNG CORP | 04/21/2022 |
| BIS | — | ISSUED | C.I. CONTRACTING CORP | 10/25/2021 |
| BIS | PL | ISSUED | AQUA PLUMBING & HTNG CORP | 03/25/2021 |
| BIS | — | ISSUED | SANDHA GENERAL CONTRACTING CORP | 10/23/2019 |
| BIS | EQ | ISSUED | SANDHA GENERAL CONTRACTING CORP | 10/23/2019 |
| BIS | SD | ISSUED | CAPITOL FIRE SPKL CO,INC | 05/06/2019 |
| BIS | PL | ISSUED | AQUA PLUMBING & HTNG CORP | 05/08/2018 |
| BIS | MH | ISSUED | SANDHA GENERAL CONTRACTING CORP | 01/23/2018 |
| BIS | — | ISSUED | SANDHA GENERAL CONTRACTING CORP | 11/13/2017 |
| BIS | PL | ISSUED | AQUA PLUMBING & HTNG CORP | 03/13/2017 |
| BIS | — | ISSUED | SANDHA GENERAL CONTRACTING CORP | 01/20/2017 |
| BIS | EQ | ISSUED | C.I. CONTRACTING CORP | 07/13/2015 |
| BIS | — | ISSUED | C.I. CONTRACTING CORP | 07/13/2015 |
| BIS | — | ISSUED | C.I. CONTRACTING CORP | 05/05/2014 |
| BIS | — | ISSUED | C.I. CONTRACTING CORP | 02/26/2013 |
| BIS | — | ISSUED | C.I. CONTRACTING CORP | 03/23/2011 |
| BIS | EQ | ISSUED | C.I. CONTRACTING CORP | 03/23/2011 |
| BIS | PL | ISSUED | AQUA PLUMBING & HTNG CORP | 11/19/2009 |
| BIS | OT | ISSUED | NATIONAL MAINTENANCE INC | 10/14/2009 |
| BIS | OT | ISSUED | NATIONAL MAINTENANCE INC | 10/14/2009 |
| BIS | PL | ISSUED | AQUA PLUMBING & HTNG CORP | 06/16/2009 |
| BIS | — | ISSUED | C.I. CONTRACTING CORP | 04/10/2009 |
| BIS | EQ | ISSUED | C.I. CONTRACTING CORP | 04/10/2009 |
| BIS | SD | ISSUED | CAPITOL FIRE SPKL CO,INC | 06/25/2008 |
| BIS | — | ISSUED | C.I. CONTRACTING CORP | 04/01/2008 |
| BIS | EQ | ISSUED | C.I. CONTRACTING CORP | 04/01/2008 |
| BIS | PL | ISSUED | AQUA PLUMBING & HTNG CORP | 03/25/2008 |
| BIS | EQ | ISSUED | EVEREST SCAFFOLDING INC | 02/11/2008 |
| BIS | EQ | ISSUED | C.I. CONTRACTING CORP | 01/09/2008 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/10/2023 | Complete | SELECTRIC ELECL CONT CO I | General Wiring |
| 10/15/2020 | Complete | JECO ELEC'L SERVICE CORP. | General Wiring |
| 05/16/2018 | Complete | JECO ELEC'L SERVICE CORP. | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/16/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/16/2023 | Pass-Final SD - Up to 3 Requested Floors | Pass | View ↗ |
| 05/11/2023 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 04/18/2023 | Pass-Final SD - Up to 3 Requested Floors | Pass | View ↗ |
| 04/10/2023 | Fail-Final SD - Up to 3 Requested Floors | Fail | View ↗ |
| 03/24/2023 | Fail-Final SD - Up to 3 Requested Floors | Fail | View ↗ |
| 03/24/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/13/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/09/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/23/2023 | Structural Steel - High Strength Bolting | MIKHAIL ZEYGMAN | special |
| 05/23/2023 | Concrete - Cast-In-Place | MIKHAIL ZEYGMAN | special |
| 05/23/2023 | Structural Stability – Alterations of existing buildings | MIKHAIL ZEYGMAN | special |
| 05/23/2023 | Final | MIKHAIL ZEYGMAN | progress |
| 05/23/2023 | Post-installed Anchors | MIKHAIL ZEYGMAN | special |
| 05/23/2023 | Structural Steel - Details | MIKHAIL ZEYGMAN | special |
| 05/23/2023 | Structural Steel - Welding | MIKHAIL ZEYGMAN | special |
| 05/09/2023 | Standpipe Systems | MIKHAIL ZEYGMAN | special |
| 05/09/2023 | Fire-Resistant Penetrations and Joints | MIKHAIL ZEYGMAN | special |
| 05/01/2023 | Standpipe Systems | MIKHAIL ZEYGMAN | special |
| 05/01/2023 | Fire-Resistant Penetrations and Joints | MIKHAIL ZEYGMAN | special |
| 07/14/2022 | Structural Steel - Details | Celin Munoz | special |
| 07/14/2022 | Structural Steel - High Strength Bolting | Celin Munoz | special |
| 07/14/2022 | Structural Stability – Alterations of existing buildings | Celin Munoz | special |
| 07/14/2022 | Structural Steel - Welding | Celin Munoz | special |
| 07/14/2022 | Final | Celin Munoz | progress |
| 07/12/2022 | Structural Steel - Welding | Celin Munoz | special |
| 07/12/2022 | Structural Steel - High Strength Bolting | Celin Munoz | special |
| 07/12/2022 | Structural Steel - Details | Celin Munoz | special |
| 07/12/2022 | Structural Stability – Alterations of existing buildings | Celin Munoz | special |
| 07/12/2022 | Final | Celin Munoz | progress |
| 01/03/2022 | Fire-Resistance Rated Construction | MIKHAIL ZEYGMAN | progress |
| 01/03/2022 | Final | MIKHAIL ZEYGMAN | progress |
| 01/03/2022 | Fire-Resistant Penetrations and Joints | MIKHAIL ZEYGMAN | special |
| 01/03/2022 | Sprayed fire-resistant materials | MIKHAIL ZEYGMAN | special |