1920Year Built
2Stories
S1Building Class
C4-4DZoning
3,000 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Primarily 1 family with 1 store or office · Owner of record: 4000 HOLDINGS LLC · 2,800 sf lot · 1.07 FAR built · Flood zone X
Locations of Work
Mechanical
Roof1p · 1 filing · 16 docs
Floor 33p · 1 filing · 16 docs
Floor 23p · 1 filing · 16 docs
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
ASCO GROUP1207/08/2026
ATLANTIC KING RLTY CORP403/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/14/2017$938K—ATLANTIC-KING REALTY CORP. → ATLANABE LLC$312/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ADROIT ENGINEERING PLLC306/16/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
N TECH DESIGN OF AMERICAGeneral Contractor407/08/2026
WYTON DEVELOPERS LLCGeneral Contractor207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ADROIT ENGINEERING PLLC8885105/05/2025
Building Lifecycle
All (17)Filed (3)Permit Issued (4)Signed Off (1)Violation (5)Objection (2)Special Inspection (2)
07/10/2026
Signed off — Full Demolition
MECHANICAL MEANS SUBMITTED FOR USE OF MECHANICAL EQUIPMENT ON GRADE AT THE TIME OF DEMOLITION
B01173500-I1
01/30/2026
Permit issued — Construction Fence
B01227220-I1-FN
07/18/2025
Permit issued — Full Demolition
B01173500-I1-FD
07/17/2025
Permit issued — Protection and Mechanical Methods
B01173500-S1-PMM
06/19/2025
Objection resolved — Addressed
06/16/2025
Filed — Full Demolition
MECHANICAL MEANS SUBMITTED FOR USE OF MECHANICAL EQUIPMENT ON GRADE AT THE TIME OF DEMOLITION
B01173500-S1
05/30/2025
Permit issued — Construction Fence
B01227220-I1-FN
05/21/2025
Filed — Alteration
PROPOSED 8FT CONSTRUCTION FENCE. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01227220-I1
05/19/2025
Objection raised — Structural
05/05/2025
Filed — Full Demolition
MECHANICAL MEANS SUBMITTED FOR USE OF MECHANICAL EQUIPMENT ON GRADE AT THE TIME OF DEMOLITION
B01173500-I1
05/05/2025
Special inspection requirement — Demolition
DUY HOANG
05/05/2025
Special inspection requirement — Structural Stability – Alterations of existing Buildings
DUY HOANG
05/17/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/15/2017
Violation issued (ECB, closed)
Construction
04/15/2017
Violation issued (ECB, closed)
Construction
02/14/2017
Violation issued (ECB, closed)
Construction
02/14/2017
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FenceSigned-offWYTON DEVELOPERS LLC01/30/2026
DOB NOWFull DemolitionSigned-offN TECH DESIGN OF AMERICA07/18/2025
DOB NOWProtection and Mechanical MethodsSigned-offN TECH DESIGN OF AMERICA07/17/2025
DOB NOWConstruction FenceSigned-offWYTON DEVELOPERS LLC05/30/2025
BISPLISSUEDC.R.U. MECHAN & HEAT INC11/25/2003
BISMHISSUEDWEXLER PLG. HTNG INC06/03/1999
BISPLISSUEDWEXLER PLG. HTNG INC06/03/1999
1 project · most recent 05/21/2025
Fence
FiledStatusContractorScope
05/21/2025Signed-offWYTON DEVELOPERS LLCFence
▾Special Inspection Requirements (DOB NOW) — 2
DateRequirementInspectorRole
05/05/2025DemolitionDUY HOANGspecial
05/05/2025Structural Stability – Alterations of existing BuildingsDUY HOANGspecial
▾Documents — 18 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/21/2026B01227220-I1Request digital key ↗
08/21/2026B01173500-I1Request digital key ↗
08/21/2026B01173500-S1Request digital key ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/21/2026B01227220-I1Open ↗
08/21/2026B01173500-I1Open ↗
08/21/2026B01173500-S1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/27/2026B01173500-I1Open ↗
08/27/2026B01173500-I1Open ↗
▸Trade Schedules & Equipment4
▸DOB NOWElectric Cut-Off1
08/13/2026B01173500-I1Open ↗
▸DOB NOWWater Cut-Off1
08/13/2026B01173500-I1Open ↗
▸DOB NOWGas Cut-Off1
08/13/2026B01173500-I1Open ↗
▸DOB NOWSewer Cut-Off1
08/13/2026B01173500-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/21/2026B01173500-I1Open ↗
▸DOB NOWRodent Control1
08/13/2026B01173500-I1Open ↗
▸Other Documents4
▸DOB NOWCommunity Board Notification1
08/13/2026B01173500-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/21/2026B01173500-I1Open ↗
▸DOB NOWFull Demo: 10-Day Notice1
08/13/2026B01173500-I1Open ↗
▸DOB NOWStructure Photographs1
08/13/2026B01173500-I1Open ↗