Hospital, sanitarium, mental institution
NH LIJ ZH Hospital Campus
270-05 76 AVENUE · Glen Oaks-Floral Park-New Hyde Park · BIN 4439542
💬 Discuss this project
1959Year Built
9Stories
I1Building Class
R3-2Zoning
2,014,617 sfGross Floor Area
1Units
LL97 Covered4 Open Violations 2 unresolved · 2 paperwork only ▸FDNY Report ↗
Hospital, sanitarium, mental institution · Owner of record: LONG ISLAND JEWISH HOSPITAL · 1,306,800 sf lot · 1.54 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction41p · 1 filing · 20 docs
Floor 4Under Construction42p · 5 filings · 20 docs
Floor 3Under Construction9p · 1 filing · 20 docs
Floor 2
Floor 13p · 1 filing · 4 docs
MezzanineUnder Construction19p · 1 filing · 20 docs
Cellar30p · 4 filings · 19 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NORTHWELL HEALTH3507/08/2026
NORTHSHORE L I J HEALTH SYSTEM2503/21/2026
NORTHWELL HEALTH SYSTEM103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
DAVID GERARD THOMAS211/19/2025
DOUGLAS P. GONZALEZ111/09/2025
AKF ENGINEERS, LLP211/03/2025
THE LIRO GROUP202/03/2025
PAMELA A. SMITH101/22/2025
GILSANZ MURRAY STEFICEK LLP101/22/2025
LIZARDOS ENGINEERING703/24/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
UPRIGHT EXPEDITERS3203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
GILBANE BUILDING COMPANYGeneral Contractor907/08/2026
CONSIGLI CONSTRUCTION COGeneral Contractor307/08/2026
SIRINA FIRE PROT CORPFire Protection207/08/2026
GAROFALO, SElectrical203/21/2026
GRZEGORZ CORP T/AElectrical203/21/2026
PAR PLUMBING CO., INCPlumbing207/08/2026
ALLIANCE PLUMBING CORPPlumbing107/08/2026
TRISTATE PLBG SVCS CORPPlumbing106/02/2026
CURRENT FIRE PROTECTION INCFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CC@A ENGINEERING P.C18541611/19/2025
Building Lifecycle
All (113)Filed (16)Permit Issued (18)Signed Off (8)Violation (17)Inspection (8)Objection (16)Special Inspection (30)
06/23/2026
Permit issued — Structural
Q01248672-S4-ST
06/23/2026
Permit issued — General Construction
Q01248672-I1-GC
06/23/2026
Permit issued — General Construction
Q01248672-S1-GC
06/23/2026
Permit issued — Mechanical Systems
Q01248672-S2-MS
04/27/2026
Permit issued — General Construction
Q01248672-I1-GC
04/24/2026
Permit issued — Plumbing
Q01248672-S3-PL
04/14/2026
Permit issued — Structural
Q01248672-S4-ST
04/01/2026
Signed off — Alteration
LIJ Northwell Health: LINAC Project: modify existing Mechanical systems to conform with new suite layout due to replacement of LINAC equipment, as per plans filed herewith.
Q01153509-I1
03/17/2026
Objection resolved — Addressed
02/16/2026
Objection resolved — Addressed
02/02/2026
Signed off — Alteration
Northwell LIJ: LINAC Project: modify existing plumbing & sprinkler systems to conform with new medical suite equipment installation as per plans filed herewith.
Q01154673-I1
12/30/2025
Signed off — Alteration
LIJ Northwell Health: LINAC Project: installation of structural support systems and concrete pad for new medical equipment, as per plans filed herewith.
Q01153434-I1
12/09/2025
Special inspection requirement — Shutoff dampers
CHAROULIS CHARALAMBOUS
12/02/2025
Objection raised — Energy
11/21/2025
Objection raised — Cost
11/20/2025
Signed off — Alteration
LIJ Northwell Health: LINAC Project: rearrange interior non-bearing partitions, install hung ceiling, wall & floor finishes @ portion of cellar as per plans filed herewith; no change in use, occupancy or egress under this application.
Q01153421-I1
11/19/2025
Filed — Alteration CO
Northwell LIJ Medical Center - Bone Marrow Transplant (BMT) Project: minor structural scope (installation of roof dunnage framing in support of new mechanical equipment) as per plans filed herewith.
Q01248672-S1
11/19/2025
Objection raised — Energy
11/09/2025
Filed — Alteration CO
Northwell LIJ Medical Center - Bone Marrow Transplant (BMT) Project: minor structural scope (installation of roof dunnage framing in support of new mechanical equipment) as per plans filed herewith.
Q01248672-S4
11/03/2025
Filed — Alteration CO
Northwell LIJ Medical Center - Bone Marrow Transplant (BMT) Project: minor structural scope (installation of roof dunnage framing in support of new mechanical equipment) as per plans filed herewith.
Q01248672-S3
11/03/2025
Filed — Alteration CO
Northwell LIJ Medical Center - Bone Marrow Transplant (BMT) Project: minor structural scope (installation of roof dunnage framing in support of new mechanical equipment) as per plans filed herewith.
Q01248672-S2
10/31/2025
Special inspection requirement — Structural Steel - Welding
CHAROULIS CHARALAMBOUS
10/31/2025
Special inspection requirement — Structural Steel - High Strength Bolting
CHAROULIS CHARALAMBOUS
10/31/2025
Special inspection requirement — Post-installed Anchors
CHAROULIS CHARALAMBOUS
10/30/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
CHAROULIS CHARALAMBOUS
10/29/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
CHAROULIS CHARALAMBOUS
10/29/2025
Special inspection requirement — Maintenance information
CHAROULIS CHARALAMBOUS
10/29/2025
Special inspection requirement — Electrical motors and elevators
CHAROULIS CHARALAMBOUS
10/29/2025
Special inspection requirement — HVAC-R and service water heating system controls
CHAROULIS CHARALAMBOUS
10/29/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
CHAROULIS CHARALAMBOUS
10/29/2025
Special inspection requirement — Energy Code Compliance Inspections
CHAROULIS CHARALAMBOUS
10/29/2025
Special inspection requirement — Duct leakage testing, insulation and design
CHAROULIS CHARALAMBOUS
10/29/2025
Special inspection requirement — HVAC-R and service water heating equipment
CHAROULIS CHARALAMBOUS
10/14/2025
Objection raised — Scope
10/07/2025
Special inspection requirement — Structural Steel - Details
CHAROULIS CHARALAMBOUS
09/29/2025
Filed — Alteration CO
Northwell LIJ Medical Center - Bone Marrow Transplant (BMT) Project: minor structural scope (installation of roof dunnage framing in support of new mechanical equipment) as per plans filed herewith.
Q01248672-I1
09/29/2025
Special inspection requirement — Sprayed fire-resistant materials
CHAROULIS CHARALAMBOUS
09/04/2025
Special inspection requirement — Final
CHAROULIS CHARALAMBOUS
09/04/2025
Special inspection requirement — Sprinkler Systems
CHAROULIS CHARALAMBOUS
09/04/2025
Special inspection requirement — Standpipe Systems
CHAROULIS CHARALAMBOUS
09/03/2025
Special inspection requirement — Mechanical Systems
CHAROULIS CHARALAMBOUS
09/03/2025
Special inspection requirement — Final
CHAROULIS CHARALAMBOUS
08/06/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
07/24/2025
Inspection — Certified Medical Gas - MG - PL - Finish
Certified
View inspection ↗
07/24/2025
Inspection — Certified Medical Gas - MG - PL - Roughing
Certified
View inspection ↗
07/24/2025
Inspection — Certified Medical Gas - MG - PL - Test
Certified
View inspection ↗
07/14/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
CHAROULIS CHARALAMBOUS
07/07/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
07/07/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
03/07/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
03/05/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
02/21/2025
Permit issued — Plumbing
Q01154673-I1-EW-SP
02/20/2025
Permit issued — Sprinklers
Q01154673-I1-PL
02/19/2025
Permit issued — Mechanical Systems
Q01153509-I1-MS
02/19/2025
Permit issued — Structural
Q01153434-I1-ST
02/19/2025
Permit issued — General Construction
Q01153421-I1-GC
02/19/2025
Objection resolved — Addressed
02/05/2025
Objection raised — Fire_Protection
02/03/2025
Filed — Alteration
LIJ Northwell Health: LINAC Project: modify existing Mechanical systems to conform with new suite layout due to replacement of LINAC equipment, as per plans filed herewith.
Q01153509-I1
02/03/2025
Filed — Alteration
Northwell LIJ: LINAC Project: modify existing plumbing & sprinkler systems to conform with new medical suite equipment installation as per plans filed herewith.
Q01154673-I1
Latest 60 of 113 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralPermit IssuedGILBANE BUILDING COMPANY06/23/2026
DOB NOWGeneral ConstructionPermit IssuedGILBANE BUILDING COMPANY06/23/2026
DOB NOWGeneral ConstructionPermit IssuedGILBANE BUILDING COMPANY06/23/2026
DOB NOWMechanical SystemsPermit IssuedGILBANE BUILDING COMPANY06/23/2026
DOB NOWGeneral ConstructionPermit IssuedGILBANE BUILDING COMPANY04/27/2026
DOB NOWPlumbingPermit IssuedTRISTATE PLBG SVCS CORP04/24/2026
DOB NOWStructuralPermit IssuedGILBANE BUILDING COMPANY04/14/2026
DOB NOWPlumbingSigned-offCURRENT FIRE PROTECTION I02/21/2025
DOB NOWSprinklersSigned-offCARDOZA PLUMBING WMBE02/20/2025
DOB NOWMechanical SystemsSigned-offCONSIGLI CONSTRUCTION CO02/19/2025
DOB NOWStructuralSigned-offCONSIGLI CONSTRUCTION CO02/19/2025
DOB NOWGeneral ConstructionSigned-offCONSIGLI CONSTRUCTION CO02/19/2025
DOB NOWSprinklersSigned-offPAR PLUMBING CO., INC04/17/2020
DOB NOWSprinklersSigned-offSIRINA FIRE PROT CORP04/17/2020
DOB NOWMechanical SystemsSigned-offGILBANE BUILDING COMPANY04/09/2020
DOB NOWSprinklersSigned-offSIRINA FIRE PROT CORP10/10/2019
DOB NOWMechanical SystemsSigned-offGILBANE BUILDING COMPANY10/09/2019
DOB NOWSprinklersSigned-offPAR PLUMBING CO., INC10/08/2019
BISOTISSUEDGILBANE BUILDING COMPANY06/22/2020
BISOTISSUEDGILBANE BUILDING COMPANY04/24/2020
BISOTISSUEDGILBANE BUILDING COMPANY10/02/2019
BISOTISSUEDTURNER CONSTRUCTION COMPANY10/26/2016
BISMHISSUEDTURNER CONSTRUCTION COMPANY10/26/2016
BISSPISSUEDSIRINA FIRE PROT CORP09/28/2016
BISPLISSUEDMACCARONE PLUMBING INC09/23/2016
BISSPISSUEDSIRINA FIRE PROT CORP09/19/2016
BISMHISSUEDTURNER CONSTRUCTION COMPANY07/06/2016
BISOTISSUEDTURNER CONSTRUCTION COMPANY07/06/2016
BISPLISSUEDSCALE PLUMBING CORP06/14/2010
BISOTISSUEDJSK CONSTRUCTION CORP06/03/2010
BISMHISSUEDJSK CONSTRUCTION CORP06/03/2010
BISMHISSUEDAXIS CONSTRUCTION CORP02/02/2010
BISOTISSUEDAXIS CONSTRUCTION CORP02/02/2010
BISOTISSUEDAXIS CONSTRUCTION CORP02/02/2010
BISPLISSUEDJ.M. BOTTO INC09/05/2007
BISPLISSUEDJ.M. BOTTO INC09/05/2007
BISOTISSUEDAXIS CONSTRUCTION CORP08/14/2007
BISSPISSUEDSIRINA FIRE PROTECTION CORP06/01/2005
BISOTISSUEDLENDLEASE(US)CONSTRUCTION04/11/2003
BISEQISSUEDLENDLEASE(US)CONSTRUCTION04/11/2003
+ 3 more permits on file
1 project · most recent 11/19/2025
Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
11/19/2025Permit IssuedGILBANE BUILDING COMPANYAir Conditioning Systems, Ventilation Systems
Cooling
Mitsubishi Electric PUZ-A24NHA7 24,000 BTU · Split System ×4
Haakon Custom 13,500 CFM · Ahu ×2
1 project · most recent 11/19/2025
Sprinkler System
FiledStatusContractorScope
11/19/2025——Sprinkler System
1 project · most recent 11/19/2025
Medical Gas Storm Water/Sanitary
FiledStatusContractorScope
11/19/2025Permit IssuedTRISTATE PLBG SVCS CORPMedical Gas, Storm, Water/Sanitary
2 projects · most recent 05/28/2026
General Wiring Lighting
FiledStatusContractorScope
05/28/2026Permit IssuedHATZEL AND BUEHLER, INCGeneral Wiring
06/25/2025CompleteHATZEL AND BUEHLER, INCGeneral Wiring, Lighting
1 project · most recent 11/19/2025
Steel Concrete
FiledStatusContractorScope
11/19/2025Permit IssuedGILBANE BUILDING COMPANYSteel, Concrete
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
08/06/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
07/24/2025Certified Medical Gas - MG - PL - FinishCertifiedView ↗
07/24/2025Certified Medical Gas - MG - PL - RoughingCertifiedView ↗
07/24/2025Certified Medical Gas - MG - PL - TestCertifiedView ↗
07/07/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
07/07/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/07/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
03/05/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 33
DateRequirementInspectorRole
12/09/2025Shutoff dampersCHAROULIS CHARALAMBOUSenergy_progress
10/31/2025Structural Steel - WeldingCHAROULIS CHARALAMBOUSspecial
10/31/2025Structural Steel - High Strength BoltingCHAROULIS CHARALAMBOUSspecial
10/31/2025Post-installed AnchorsCHAROULIS CHARALAMBOUSspecial
10/30/2025HVAC-R and service water piping design and insulationCHAROULIS CHARALAMBOUSenergy_progress
10/29/2025HVAC-R and service water piping design and insulationCHAROULIS CHARALAMBOUSenergy_progress
10/29/2025Maintenance informationCHAROULIS CHARALAMBOUSenergy_progress
10/29/2025Electrical motors and elevatorsCHAROULIS CHARALAMBOUSenergy_progress
10/29/2025HVAC-R and service water heating system controlsCHAROULIS CHARALAMBOUSenergy_progress
10/29/2025Fire-Resistant Penetrations and JointsCHAROULIS CHARALAMBOUSspecial
10/29/2025Energy Code Compliance InspectionsCHAROULIS CHARALAMBOUSprogress
10/29/2025Duct leakage testing, insulation and designCHAROULIS CHARALAMBOUSenergy_progress
10/29/2025HVAC-R and service water heating equipmentCHAROULIS CHARALAMBOUSenergy_progress
10/07/2025Structural Steel - DetailsCHAROULIS CHARALAMBOUSspecial
09/29/2025Sprayed fire-resistant materialsCHAROULIS CHARALAMBOUSspecial
09/04/2025FinalCHAROULIS CHARALAMBOUSprogress
09/04/2025Sprinkler SystemsCHAROULIS CHARALAMBOUSspecial
09/04/2025Standpipe SystemsCHAROULIS CHARALAMBOUSspecial
09/03/2025Mechanical SystemsCHAROULIS CHARALAMBOUSspecial
09/03/2025FinalCHAROULIS CHARALAMBOUSprogress
07/14/2025Fire-Resistant Penetrations and JointsCHAROULIS CHARALAMBOUSspecial
12/11/2024Sprinkler SystemsCHAROULIS CHARALAMBOUSspecial
12/10/2024FinalCHAROULIS CHARALAMBOUSprogress
12/10/2024Mechanical SystemsCHAROULIS CHARALAMBOUSspecial
03/18/2020Sprinkler SystemsCHAROULIS CHARALAMBOUSspecial
Latest 25 of 33.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Northwell | W Health" | SM | LONG ISLAND JEWISH MEDICAL | CENTERMedical / HealthcareBasement
Project Q01153509 Alteration · LOC Issued · 02/03/2025
Project Q01154673 Alteration · LOC Issued · 02/03/2025
Long Island Jewish Medical CenterMedical / HealthcareBasement, Floor 4
Project Q01153434 Alteration · LOC Issued · 01/22/2025
Project Q00334645 Alteration · LOC Issued · 03/24/2020
Northwell HealthMedical / HealthcareFloor 4
Project Q00206840 Alteration · LOC Issued · 08/12/2019
Project Q00206821 Alteration · LOC Issued · 08/08/2019
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 254 on file (BIS + DOB NOW)
▸Plans & Drawings19
▸DOB NOWPlans/Sketch8
08/21/2026Q01153421-I1Request digital key ↗
08/21/2026Q01153434-I1Request digital key ↗
08/21/2026Q01154673-I1Request digital key ↗
Showing 3 of 8 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler4
08/28/2026Q00206840-P2Request digital key ↗
08/28/2026Q00206840-P1Request digital key ↗
08/28/2026Q00334645-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Plumbing4
08/28/2026Q00206840-P2Request digital key ↗
08/28/2026Q00206840-P1Request digital key ↗
08/28/2026Q00334645-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems3
08/28/2026Q00206821-P1Request digital key ↗
08/28/2026Q00334527-I1Request digital key ↗
08/15/2026Q00206821-I1Request digital key ↗
▸Applications & Permits36
▸BISPLAN / WORK APPROVAL APPLICATION19
03/26/2020440590120Open ↗
08/03/2019421737464Open ↗
07/18/2017421314161Open ↗
Showing 3 of 19 on file for this type
▸BISWORK PERMIT APPLICATION17
07/06/2020440590120Open ↗
04/24/2020440590120Open ↗
10/03/2019421737464Open ↗
Showing 3 of 17 on file for this type
▸Seals & Professional Certifications72
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION21
03/07/2020421737464Open ↗
10/03/2019421737464Open ↗
08/03/2019421737464Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature17
09/23/2026Q01154673-I1Open ↗
09/23/2026Q01248672-S2Open ↗
09/23/2026Q01248672-S2Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWProgress Inspector Seal & Signature16
09/23/2026Q01248672-S2Open ↗
09/23/2026Q01248672-S2Open ↗
09/23/2026Q01248672-S2Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature15
08/28/2026Q00206821-P1Open ↗
08/28/2026Q00206821-I1Open ↗
08/28/2026Q00206840-P1Open ↗
Showing 3 of 15 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
10/04/2016421336799Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
03/26/2020440590120Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
10/04/2016421336799Open ↗
▸Trade Schedules & Equipment12
▸BISSELF-CERT PLUMBING NOTICE4
03/16/2011420166028Open ↗
08/02/2010420166028Open ↗
06/30/2010420166028Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE B - PLUMBING3
05/20/2010420166028Open ↗
03/25/2010420166028Open ↗
01/15/2010420127972Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
03/23/2017421314161Open ↗
10/04/2016421336799Open ↗
06/07/2016421314161Open ↗
▸BISPLUMBING - SUPPORTING DOCUMENTATION1
03/16/2011420166028Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
09/25/2017421316533Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/13/2026Q01248672-I1Open ↗
▸Environmental & Asbestos22
▸DOB NOWDEP ACP-5: Asbestos Assessment Report15
08/28/2026Q00206821-P1Open ↗
08/28/2026Q00206840-P2Open ↗
08/28/2026Q00206840-P1Open ↗
Showing 3 of 15 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)5
03/26/2020440590120Open ↗
10/03/2019421737464Open ↗
10/22/2017421316533Open ↗
Showing 3 of 5 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
03/25/2010420166028Open ↗
01/15/2010420127972Open ↗
▸Energy Compliance13
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
03/07/2020421737464Open ↗
10/03/2019421737464Open ↗
08/03/2019421737464Open ↗
Showing 3 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
03/07/2020421737464Open ↗
11/20/2017421314161Open ↗
11/17/2017421314161Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
04/23/2020440590120Open ↗
03/26/2020440590120Open ↗
▸BISINTERIOR LIGHTING POWER1
10/28/2020440590120Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
10/28/2020440590120Open ↗
▸BISLIGHTING CONTROLS1
10/28/2020440590120Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
10/28/2020440590120Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY2
04/23/2020440590120Open ↗
03/26/2020440590120Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
10/28/2020440590120Open ↗
▸Approvals, Objections & Sign-offs33
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter16
08/28/2026Q00206821-P1Open ↗
08/28/2026Q00206840-P2Open ↗
08/28/2026Q00206840-P1Open ↗
Showing 3 of 16 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST7
10/28/2020440590120Open ↗
03/07/2020421737464Open ↗
11/20/2017421314161Open ↗
Showing 3 of 7 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
07/06/2020440590120Open ↗
08/03/2019421737464Open ↗
08/02/2010420166028Open ↗
Showing 3 of 5 on file for this type
▸BISADMINISTRATIVE OBJECTIONS3
10/04/2016421336799Open ↗
01/15/2010420127972Open ↗
06/15/2009420029114Open ↗
▸BISFINAL1
10/28/2020440590120Open ↗
▸BISSUPERSEDING LETTER1
07/18/2017421314161Open ↗
▸Cost, Insurance & Ownership17
▸BISCOST AFFIDAVIT14
04/14/2020440590120Open ↗
03/26/2020440590120Open ↗
03/07/2020421737464Open ↗
Showing 3 of 14 on file for this type
▸BISDEPT OF FINANCE VERIFICATION2
04/14/2020440590120Open ↗
04/08/2020440590120Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
10/28/2020440590120Open ↗
▸Filing & Intake Forms24
▸BISEFILING COVER SHEET12
08/03/2019421737464Open ↗
10/04/2016421336799Open ↗
06/15/2016421316533Open ↗
Showing 3 of 12 on file for this type
▸BISADDITIONAL INFORMATION8
04/14/2020440590120Open ↗
04/08/2020440590120Open ↗
01/16/2020421737464Open ↗
Showing 3 of 8 on file for this type
▸BISBOROUGH INTAKE FORM3
11/20/2017421314161Open ↗
11/17/2017421314161Open ↗
10/22/2017421316533Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
03/26/2020440590120Open ↗
▸Other Documents2
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
10/28/2020440590120Open ↗
▸DOB NOWProperty Ownership Certification1
08/14/2026Q01248672-I1Open ↗