← Back
Cape Cod
269-20 UNION TURNPIKE
QUEENS · Glen Oaks-Floral Park-New Hyde Park · BIN 4177231
💬 Discuss this project
1955Year Built
1.5Stories
A0Building Class
R2AZoning
1,280 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Cape Cod · 4,200 sf lot · 0.3 FAR built · Flood zone X
Locations of Work
Architecture
Cellar1p · 1 filing · 9 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BLOOM CONSTRUCTION1007/08/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ARCHITECTURAL CONCEPT305/18/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BLOOM CONSTRUCTION403/21/2026
ARCHITECTUAL CONCEPT203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BLOOM CONSTRUCTION INCGeneral Contractor203/21/2026
TRI CITY MECHANICAL GROUP CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ARCHITECTURAL CONCEPT3642305/18/2022
Building Lifecycle
All (35)Filed (3)Permit Issued (2)Signed Off (2)Violation (6)Inspection (9)Objection (2)Special Inspection (11)
04/27/2023
Signed off — Alteration
Q00552812-I1
03/28/2023
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
03/01/2023
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
11/30/2022
Signed off — Alteration
Install new washer and dryer and relocate existing bather fixture and caller level as per drawings.
Q00552838-I1
08/15/2022
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
08/11/2022
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
05/24/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
MUZAFFAR JAMAL
05/24/2022
Special inspection requirement — Energy Code Compliance Inspections
MUZAFFAR JAMAL
05/24/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
MUZAFFAR JAMAL
05/18/2022
Filed — Alteration
Install new washer and dryer and relocate existing bather fixture and caller level as per drawings.
Q00552838-P1
04/01/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
MUZAFFAR JAMAL
04/01/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
MUZAFFAR JAMAL
04/01/2022
Special inspection requirement — Energy Code Compliance Inspections
MUZAFFAR JAMAL
03/24/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
01/21/2022
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
01/21/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/21/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
01/18/2022
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
01/07/2022
Permit issued — Plumbing
Q00552838-I1-PL
11/18/2021
Objection raised — Scope
11/18/2021
Objection resolved — Addressed
11/11/2021
Filed — Alteration
Install new washer and dryer and relocate existing bather fixture and caller level as per drawings.
Q00552838-I1
09/13/2021
Permit issued — General Construction
Q00552812-I1-GC
08/18/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/18/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/18/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/11/2021
Filed — Alteration
Q00552812-I1
07/08/2021
Special inspection requirement — Insulation placement and R values
MUZAFFAR JAMAL
07/08/2021
Special inspection requirement — Air barrier - visual inspection
MUZAFFAR JAMAL
07/08/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
MUZAFFAR JAMAL
07/08/2021
Special inspection requirement — Energy Code Compliance Inspections
MUZAFFAR JAMAL
07/08/2021
Special inspection requirement — Fire-Resistance Rated Construction
MUZAFFAR JAMAL
05/28/2021
Violation issued (ECB, closed)
Construction
05/28/2021
Violation issued (ECB, closed)
Construction
05/28/2021
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offFLAVIO MECHANICAL CORP01/07/2022
DOB NOWGeneral ConstructionSigned-offBLOOM CONSTRUCTION INC09/13/2021
1 project · most recent 06/02/2023
General Wiring
FiledStatusContractorScope
06/02/2023Permit IssuedJOSEPH WEINSTEIN ELECTRICGeneral Wiring
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
03/28/2023Pass-Final General Construction Non-Directive 14PassView ↗
03/01/2023Pass-Final General Construction Non-Directive 14PassView ↗
08/15/2022Fail-Final General Construction Non-Directive 14FailView ↗
08/11/2022Fail-Final General Construction Non-Directive 14FailView ↗
03/24/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
01/21/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
01/21/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/21/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
01/18/2022Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 11
DateRequirementInspectorRole
05/24/2022Fire-Resistant Penetrations and JointsMUZAFFAR JAMALspecial
05/24/2022Energy Code Compliance InspectionsMUZAFFAR JAMALprogress
05/24/2022HVAC-R and service water piping design and insulationMUZAFFAR JAMALenergy_progress
04/01/2022HVAC-R and service water piping design and insulationMUZAFFAR JAMALenergy_progress
04/01/2022Fire-Resistant Penetrations and JointsMUZAFFAR JAMALspecial
04/01/2022Energy Code Compliance InspectionsMUZAFFAR JAMALprogress
07/08/2021Insulation placement and R valuesMUZAFFAR JAMALenergy_progress
07/08/2021Air barrier - visual inspectionMUZAFFAR JAMALenergy_progress
07/08/2021Fire-Resistant Penetrations and JointsMUZAFFAR JAMALspecial
07/08/2021Energy Code Compliance InspectionsMUZAFFAR JAMALprogress
07/08/2021Fire-Resistance Rated ConstructionMUZAFFAR JAMALprogress
▾Documents — 46 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/27/2026Q00552812-I1Request digital key ↗
08/27/2026Q00552838-P1Request digital key ↗
08/15/2026Q00552838-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION2
08/24/2015421183677Open ↗
08/24/2015421183668Open ↗
▸Zoning, Tax Lot & Property Records2
▸BISZONING DIAGRAM2
08/26/2015421183668Open ↗
08/25/2015421183677Open ↗
▸Seals & Professional Certifications18
▸DOB NOWProgress Inspector Seal & Signature8
08/29/2026Q00552838-I1Open ↗
08/29/2026Q00552838-I1Open ↗
08/28/2026Q00552838-P1Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION4
08/21/2015421183677Open ↗
08/21/2015421183677Open ↗
07/17/2015421183668Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/27/2026Q00552812-I1Open ↗
08/13/2026Q00552838-I1Open ↗
08/13/2026Q00552838-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
08/29/2026Q00552838-I1Open ↗
08/28/2026Q00552838-P1Open ↗
08/26/2026Q00552812-I1Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
07/14/2015421183677Open ↗
▸Safety & Tenant Protection2
▸BISSTREET TREE CHECKLIST2
07/17/2015421183668Open ↗
07/14/2015421183677Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/27/2026Q00552812-I1Open ↗
08/13/2026Q00552838-P1Open ↗
08/13/2026Q00552838-I1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
07/14/2015421183677Open ↗
▸Energy Compliance3
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026Q00552838-I1Open ↗
08/13/2026Q00552812-I1Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
07/14/2015421183677Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: SOIL INSPECTION1
08/21/2015421183677Open ↗
▸Approvals, Objections & Sign-offs4
▸BISADMINISTRATIVE OBJECTIONS2
07/17/2015421183668Open ↗
07/14/2015421183677Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE2
08/24/2015421183677Open ↗
07/17/2015421183668Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
08/25/2015421183677Open ↗
07/14/2015421183677Open ↗
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET2
07/17/2015421183668Open ↗
07/14/2015421183677Open ↗
▸Other Documents2
▸BISPLOT DIAGRAM2
07/17/2015421183668Open ↗
07/14/2015421183677Open ↗