| Owner | Filings | Most Recent |
|---|---|---|
| US RENAL CARE NORTH FLUSHING DIALYS | 7 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ALEX ROUSH ARCHITECTS, INC. | 5 | 01/26/2023 |
| SHEPHERD HARVEY & ASSOC. | 7 | 05/09/2022 |
| LEON SKVIRSKY PE | 3 | 03/29/2022 |
| WAVIC ENGINEERING PLLC | 1 | 07/30/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| BOHLER ENGINEERING | 13 | 03/21/2026 |
| BUILDING BROTHERS | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ECC GROUP INC | General Contractor | 10 | 07/08/2026 |
| PAUL SIGNS | Scaffold | 3 | 07/08/2026 |
| R.J.C. MECHANICAL CORP | Plumbing | 2 | 07/08/2026 |
| EMPIRE STATE ELECTL CORP | Electrical | 1 | 03/22/2026 |
| FULL CAPACITY FIRE CORP | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ROYAL CONSTRUCTION P.E. S | 462 | 10 | 01/26/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sign | Signed-off | PAUL SIGNS, INC | 04/01/2022 |
| DOB NOW | Sign | Signed-off | PAUL SIGNS, INC | 04/01/2022 |
| DOB NOW | Sign | Signed-off | PAUL SIGNS, INC | 04/01/2022 |
| DOB NOW | Plumbing | Signed-off | R.J.C. MECHANICAL CORP | 01/05/2022 |
| DOB NOW | General Construction | Permit Issued | ECC GROUP INC | 11/27/2021 |
| DOB NOW | Mechanical Systems | Signed-off | ECC GROUP INC | 11/23/2021 |
| DOB NOW | Mechanical Systems | Signed-off | ECC GROUP INC | 08/11/2021 |
| DOB NOW | Sprinklers | Signed-off | FULL CAPACITY FIRE CORP | 08/10/2021 |
| DOB NOW | Plumbing | Signed-off | R.J.C. MECHANICAL CORP | 08/05/2021 |
| DOB NOW | General Construction | Permit Issued | ECC GROUP INC | 07/30/2021 |
| BIS | OT | ISSUED | MIDWOOD SIGN AND DESIGN INC | 09/21/1998 |
| BIS | OT | ISSUED | LUIS FERMIN | 05/15/1998 |
| BIS | — | ISSUED | ULTIMATE SIGNS&DESIGNS CO | 05/08/1998 |
| BIS | — | ISSUED | ULTIMATE SIGNS&DESIGNS CO | 05/08/1998 |
| BIS | SP | ISSUED | CAPITOL FIRE SPKL CO,INC | 03/04/1997 |
| BIS | MH | ISSUED | HOWARD STERN MECHANICAL INC | 08/15/1996 |
| BIS | SP | ISSUED | CAPITOL FIRE SPKL CO,INC | 11/01/1995 |
| BIS | EQ | ISSUED | DAN-HOLLY CORP | 09/12/1995 |
| BIS | OT | ISSUED | DAN-HOLLY CORP | 09/12/1995 |
| BIS | OT | ISSUED | BASILICA REALTY DEVELOPMENT CORP | 07/24/1995 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 01/26/2023 | Permit Issued | ECC GROUP INC | Air Conditioning Systems, Associated Ducts and Piping, Heating Systems, Ventilation Systems | Cooling Mitsubishi Electric TRUYA0121KA70NA / TPKA0A0121HA70A 425 CFM ×2 Heating Trane YHD-150G3RHD4CFM* 250,000 BTU · Rooftop Unit ×2 YHD-180G3RHD4CFM* 350,000 BTU · Rooftop Unit ×2 Ventilation Ducts & Piping |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/26/2023 | Signed-off | GREAT OAKS MECHANICAL INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/13/2022 | Complete | HABER ELECTRIC CO., INC. | General Wiring |
| 04/05/2022 | Complete | EMPIRE STATE ELECTL CORP | — |
| 04/05/2022 | Complete | EMPIRE STATE ELECTL CORP | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/22/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/28/2022 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/18/2022 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/21/2022 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/27/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/18/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/12/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/07/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/01/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/24/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/12/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/08/2023 | Structural Stability – Alterations of existing buildings | EBRAHIM MIANDOABI | special |
| 02/08/2023 | Fire-Resistant Penetrations and Joints | EBRAHIM MIANDOABI | special |
| 02/08/2023 | Concrete - Cast-In-Place | EBRAHIM MIANDOABI | special |
| 02/08/2023 | Exterior Insulation and Finish Systems (EIFS) | EBRAHIM MIANDOABI | special |
| 02/08/2023 | Preliminary | SRINIVAS THIMMAPPA | progress |
| 02/08/2023 | Energy Code Compliance Inspections | SRINIVAS THIMMAPPA | progress |
| 02/08/2023 | Fire-Resistance Rated Construction | SRINIVAS THIMMAPPA | progress |
| 02/08/2023 | Air barrier — testing | SRINIVAS THIMMAPPA | energy_progress |
| 02/08/2023 | Protection of exposed foundation insulation | SRINIVAS THIMMAPPA | energy_progress |
| 02/08/2023 | Fenestration areas | SRINIVAS THIMMAPPA | energy_progress |
| 02/08/2023 | Air barrier - visual inspection | SRINIVAS THIMMAPPA | energy_progress |
| 02/08/2023 | Insulation placement and R values | SRINIVAS THIMMAPPA | energy_progress |
| 02/08/2023 | Vestibules | SRINIVAS THIMMAPPA | energy_progress |
| 02/08/2023 | Fenestration and door U-factor and product ratings | SRINIVAS THIMMAPPA | energy_progress |
| 02/08/2023 | Fenestration air leakage | SRINIVAS THIMMAPPA | energy_progress |
| 02/08/2023 | Air barrier continuity plan testing | SRINIVAS THIMMAPPA | energy_progress |
| 05/25/2022 | Air barrier - visual inspection | SRINIVAS THIMMAPPA | energy_progress |
| 05/25/2022 | Fire-Resistance Rated Construction | SRINIVAS THIMMAPPA | progress |
| 05/25/2022 | Preliminary | SRINIVAS THIMMAPPA | progress |
| 05/25/2022 | Fenestration areas | SRINIVAS THIMMAPPA | energy_progress |
| 05/25/2022 | Insulation placement and R values | SRINIVAS THIMMAPPA | energy_progress |
| 05/25/2022 | Fenestration and door U-factor and product ratings | SRINIVAS THIMMAPPA | energy_progress |
| 05/25/2022 | Air barrier — testing | SRINIVAS THIMMAPPA | energy_progress |
| 05/25/2022 | Vestibules | SRINIVAS THIMMAPPA | energy_progress |
| 05/25/2022 | Protection of exposed foundation insulation | SRINIVAS THIMMAPPA | energy_progress |