| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/05/2021 | $1.2M | — | — → — | $673/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SQUARE ARCH, LLC | 2 | 11/18/2025 |
| BENJAMIN HORST | 1 | 10/05/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| W J PROFESSIONAL EXPEDITING COMPANY | 2 | 03/21/2026 |
| KAMTECH RESTORATION CORP | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AA JEDSON COMPANY LLC | General Contractor | 2 | 07/08/2026 |
| KAMTECH RESTORATION CORP | General Contractor | 2 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SQ. ARCH, LLC | 4802 | 2 | 11/18/2025 |
| RICHMOND TESTING LAB | 263 | 1 | 10/05/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | KAMTECH RESTORATION CORP | 10/15/2025 |
| DOB NOW | General Construction | Signed-off | AA JEDSON COMPANY LLC | 05/09/2023 |
| DOB NOW | General Construction | Signed-off | AA JEDSON COMPANY LLC | 11/02/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/18/2025 | Complete | BERGER QUALITY ELEC'L CON | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/28/2025 | Fire-Resistant Penetrations and Joints | Kaijin Liang | special |
| 11/28/2025 | Energy Code Compliance Inspections | Kaijin Liang | progress |
| 11/28/2025 | Final | Kaijin Liang | progress |
| 11/28/2025 | Air barrier - visual inspection | Kaijin Liang | energy_progress |
| 10/03/2022 | Fire-Resistant Penetrations and Joints | RICHARD LEMANSKY | special |
| 10/03/2022 | Lighting controls | RICHARD LEMANSKY | energy_progress |
| 10/03/2022 | Energy Code Compliance Inspections | RICHARD LEMANSKY | progress |
| 10/03/2022 | Final | RICHARD LEMANSKY | progress |
| 10/03/2022 | Lighting in dwelling units | RICHARD LEMANSKY | energy_progress |