| Owner | Filings | Most Recent |
|---|---|---|
| RELIABLE ENTERPRISES | 11 | 07/08/2026 |
| BRIGHTON 11TH ST DEV | 6 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 09/21/2021 | $1.2M | — | SLK LAND, LLC. → BRIGHTON 11TH ST DEV LLC | — not available |
| 04/02/2015 | $670K | — | Private party → Private party | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| RSLN ARCHITECTURE PLLC | 7 | 12/26/2024 |
| ENGINEERING GROUP ASSOCIATES, PC | 4 | 02/09/2024 |
| MJE PROFESSIONAL SERVICES | 2 | 07/19/2023 |
| ENTHINK ENGINEERS LLC | 1 | 01/30/2023 |
| PETER TAUBERER, PE | 1 | 09/13/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| RSLN ARCHITECTURE | 12 | 03/21/2026 |
| AVALON DESIGN | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BUILD R US CORP | General Contractor | 17 | 07/08/2026 |
| RELIABLE ENTERPRISES INC | General Contractor | 5 | 07/08/2026 |
| AMOK INC | Fire Protection | 2 | 07/08/2026 |
| AMOK INC | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ZARINA KINDO, RA | 4900 | 8 | 12/26/2024 |
| STEEL CORE ENGINEERING PL | 1098 | 2 | 01/03/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | BUILD R US | 09/20/2024 |
| DOB NOW | General Construction | Permit Issued | BUILD R US | 08/06/2024 |
| DOB NOW | Sprinklers | Signed-off | AMOK INC | 03/07/2024 |
| DOB NOW | Plumbing | Signed-off | AMOK INC | 03/07/2024 |
| DOB NOW | Construction Fence | Signed-off | BUILD R US | 11/20/2023 |
| DOB NOW | General Construction | Permit Issued | BUILD R US | 11/20/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | RELIABLE ENTERPRISES INC | 07/19/2023 |
| DOB NOW | Supported Scaffold | Signed-off | RELIABLE ENTERPRISES INC | 07/07/2023 |
| DOB NOW | Mechanical Systems | Signed-off | BUILD R US | 06/11/2023 |
| DOB NOW | Structural | Signed-off | BUILD R US | 02/13/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | RELIABLE ENTERPRISES INC | 01/30/2023 |
| DOB NOW | Sprinklers | Signed-off | AMOK INC | 01/17/2023 |
| DOB NOW | Plumbing | Signed-off | AMOK INC | 01/17/2023 |
| DOB NOW | General Construction | Permit Issued | BUILD R US | 10/24/2022 |
| DOB NOW | General Construction | Permit Issued | BUILD R US | 10/14/2022 |
| DOB NOW | General Construction | Permit Issued | BUILD R US | 08/05/2022 |
| DOB NOW | Support of Excavation | Signed-off | BUILD R US | 05/17/2022 |
| DOB NOW | Foundation | Signed-off | BUILD R US | 05/17/2022 |
| DOB NOW | General Construction | Permit Issued | BUILD R US | 05/12/2022 |
| BIS | — | ISSUED | BUILD R US CORP | 12/13/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/28/2024 | Complete | MAC ELECT'L CONTR. INC. | General Wiring |
| 02/01/2023 | Complete | RICHARD NEU | — |
| 09/27/2022 | Complete | STAR ELEC'L CONTRACTORS C | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/26/2024 | Permit Issued | BUILD R US CORP | Concrete, Masonry |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/17/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/22/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 10/08/2024 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 10/08/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/19/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/10/2024 | Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test | Certified | View ↗ |
| 05/10/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/08/2024 | Certified Sprinkler (SP) - Booster Pump Test | Certified | View ↗ |
| 05/08/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/17/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 01/20/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 01/20/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/07/2025 | Fire-Resistant Penetrations and Joints | ZARINA KINDO | special |
| 01/07/2025 | Lighting in dwelling units | ZARINA KINDO | energy_progress |
| 01/07/2025 | Metering | ZARINA KINDO | energy_progress |
| 01/07/2025 | Insulation placement and R values | ZARINA KINDO | energy_progress |
| 01/07/2025 | Fenestration areas | ZARINA KINDO | energy_progress |
| 01/07/2025 | Air barrier - visual inspection | ZARINA KINDO | energy_progress |
| 01/07/2025 | Air barrier — testing | ZARINA KINDO | energy_progress |
| 01/07/2025 | Fenestration air leakage | ZARINA KINDO | energy_progress |
| 01/07/2025 | Fenestration and door U-factor and product ratings | ZARINA KINDO | energy_progress |
| 01/07/2025 | Lighting controls | ZARINA KINDO | energy_progress |
| 01/07/2025 | Interior lighting power | ZARINA KINDO | energy_progress |
| 01/07/2025 | Maintenance information | ZARINA KINDO | energy_progress |
| 01/07/2025 | Exterior lighting power | ZARINA KINDO | energy_progress |
| 01/07/2025 | Lowest Floor Elevation | ZARINA KINDO | progress |
| 01/07/2025 | Fire-Resistance Rated Construction | ZARINA KINDO | progress |
| 01/07/2025 | Energy Code Compliance Inspections | ZARINA KINDO | progress |
| 01/07/2025 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | ZARINA KINDO | special |
| 01/07/2025 | Wall Panels, Curtain Walls, and Veneers | ZARINA KINDO | special |
| 01/07/2025 | Exterior Insulation and Finish Systems (EIFS) | ZARINA KINDO | special |
| 12/26/2024 | Lighting controls | ZARINA KINDO | energy_progress |
| 12/26/2024 | Fenestration areas | ZARINA KINDO | energy_progress |
| 12/26/2024 | Fenestration air leakage | ZARINA KINDO | energy_progress |
| 12/26/2024 | Air barrier - visual inspection | ZARINA KINDO | energy_progress |
| 12/26/2024 | Insulation placement and R values | ZARINA KINDO | energy_progress |
| 12/26/2024 | Maintenance information | ZARINA KINDO | energy_progress |