| Owner | Filings | Most Recent |
|---|---|---|
| RCR MANAGEMENT GROUP | 10 | 08/29/2026 |
| RCR MANAGEMENT | 40 | 07/08/2026 |
| ROCK GROUP NY | 8 | 07/08/2026 |
| PLATINUM SERVICES NY | 6 | 07/08/2026 |
| TWO-TONE CONTRACTING | 1 | 03/22/2026 |
| THE OWNERS OF PREMISES RE | 1 | 03/22/2026 |
| REGINA COMPANY | 3 | 03/22/2026 |
| SUEHAR REALTY INCORP. | 1 | 03/22/2026 |
| MAYFLOWER DEVELOPMENT | 2 | 03/21/2026 |
| QUANTUM DESIGN | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| RISE ARCHITECTURE NJ LLC | 5 | 06/01/2026 |
| RISE ARCHITECTURE | 1 | 01/24/2025 |
| GREGG ROTHSTEIN ARCHITECT | 7 | 06/07/2023 |
| PORCELLO ENGINEERING, INC. | 1 | 05/31/2023 |
| ASHRAF CORP | 2 | 12/08/2022 |
| NICHOLAS AGNETA AIA | 1 | 06/20/2022 |
| ASIF JAMIL, RA | 1 | 02/27/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| GREEN STUDIO | 6 | 03/21/2026 |
| PS ENGINEERS | 2 | 03/21/2026 |
| JACK JAFFA & ASSOCIATES | 10 | 03/21/2026 |
| WILLOUGHBY CONSULTING | 4 | 03/21/2026 |
| NORTHEAST EXPEDITING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NJF CONTRACTING CORP | General Contractor | 12 | 07/08/2026 |
| PLATINUM SERVICES NY LLC | General Contractor | 7 | 07/08/2026 |
| ROCK GROUP NY CORP | General Contractor | 7 | 07/08/2026 |
| ROBIN ELECTRICAL CO., INC | Electrical | 4 | 03/22/2026 |
| TWO-TONE CONTRACTING CORP. | General Contractor | 3 | 07/08/2026 |
| WYNNE PLBG & HEATING CORP | Plumbing | 3 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BIZ DESIGNS LLC | 6312 | 6 | 06/01/2026 |
| RYAN SPECIAL ENGINEERING | 2018 | 2 | 06/07/2023 |
| BUILDING CONSULTING ENGIN | 1034 | 1 | 05/31/2023 |
| FRED PORCELLO, P.E. DBA P | 531 | 1 | 05/31/2023 |
| GREGG ROTHSTEIN ARCHITECT | 195 | 5 | 07/07/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | NJF CONTRACTING CORP | 06/04/2026 |
| DOB NOW | General Construction | Signed-off | NJF CONTRACTING CORP | 01/28/2026 |
| DOB NOW | General Construction | Signed-off | NJF CONTRACTING CORP | 02/12/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | PLATINUM SERVICES NY LLC | 03/07/2024 |
| DOB NOW | General Construction | Signed-off | NJF CONTRACTING CORP | 02/20/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | TWO-TONE CONTRACTING CORP | 12/22/2023 |
| DOB NOW | Supported Scaffold | Signed-off | PLATINUM SERVICES NY LLC | 11/13/2023 |
| DOB NOW | Plumbing | Signed-off | WYNNE PLBG & HEATING CORP | 07/14/2023 |
| DOB NOW | Mechanical Systems | Signed-off | NJF CONTRACTING CORP | 07/13/2023 |
| DOB NOW | Structural | Signed-off | TWO-TONE CONTRACTING CORP | 06/06/2023 |
| DOB NOW | General Construction | Signed-off | TWO-TONE CONTRACTING CORP | 03/24/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | PLATINUM SERVICES NY LLC | 03/23/2023 |
| DOB NOW | General Construction | Signed-off | NJF CONTRACTING CORP | 01/19/2023 |
| DOB NOW | Supported Scaffold | Signed-off | PLATINUM SERVICES NY LLC | 12/09/2022 |
| DOB NOW | Mechanical Systems | Signed-off | NJF CONTRACTING CORP | 11/03/2022 |
| DOB NOW | General Construction | Signed-off | TWO-TONE CONTRACTING CORP | 09/06/2022 |
| DOB NOW | Plumbing | Signed-off | WYNNE PLBG & HEATING CORP | 08/05/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | PLATINUM SERVICES NY LLC | 04/15/2022 |
| DOB NOW | General Construction | Signed-off | NJF CONTRACTING CORP | 08/25/2021 |
| DOB NOW | Plumbing | Signed-off | WYNNE PLBG & HEATING CORP | 11/07/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | ROCK GROUP NY CORP | 12/19/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | ROCK GROUP NY CORP | 04/04/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | ROCK GROUP NY CORP | 03/01/2018 |
| BIS | — | ISSUED | NJF CONTRACTING CORP | 06/07/2023 |
| BIS | — | ISSUED | NJF CONTRACTING CORP | 06/28/2022 |
| BIS | PL | ISSUED | WYNNE PLBG & HEATING CORP | 01/07/2021 |
| BIS | — | ISSUED | NJF CONTRACTING CORP | 11/25/2020 |
| BIS | — | ISSUED | NJF CONTRACTING CORP | 03/10/2020 |
| BIS | — | ISSUED | NJF CONTRACTING CORP | 02/08/2019 |
| BIS | OT | ISSUED | KAY WATERPROOFING CORP | 03/30/2018 |
| BIS | — | ISSUED | NJF CONTRACTING CORP | 11/30/2017 |
| BIS | — | ISSUED | NJF CONTRACTING CORP | 08/15/2017 |
| BIS | PL | ISSUED | BAUER MECHANCIAL LLC | 05/20/2016 |
| BIS | FS | ISSUED | G. BAUER, INC | 05/20/2016 |
| BIS | PL | ISSUED | WYNNE PLBG & HEATING CORP | 04/15/2016 |
| BIS | OT | ISSUED | NJF CONTRACTING CORP | 04/12/2016 |
| BIS | OT | ISSUED | G. BAUER, INC | 09/19/2014 |
| BIS | — | ISSUED | NJF CONTRACTING CORP | 08/28/2014 |
| BIS | EQ | ISSUED | VLAD RESTORATION LTD | 07/18/2011 |
| BIS | OT | ISSUED | VLAD RESTORATION LTD | 06/27/2011 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/19/2024 | Complete | ROBIN ELECTRICAL CO., INC | General Wiring |
| 10/23/2023 | Complete | ROBIN ELECTRICAL CO., INC | General Wiring |
| 10/23/2023 | Complete | ROBIN ELECTRICAL CO., INC | General Wiring |
| 03/02/2023 | Complete | ROBIN ELECTRICAL CO., INC | General Wiring |
| 08/30/2022 | Complete | ROBIN ELECTRICAL CO., INC | General Wiring |
| 08/30/2022 | Complete | ROBIN ELECTRICAL CO., INC | General Wiring |
| 04/07/2022 | Complete | ILLUMINOUS ELECTRIC CORP. | General Wiring |
| 10/07/2021 | Complete | ROBIN ELECTRICAL CO., INC | General Wiring |
| 12/23/2020 | Complete | ROBIN ELECTRICAL CO., INC | General Wiring |
| 08/04/2020 | Complete | ILLUMINOUS ELECTRIC CORP. | — |
| 08/22/2019 | Complete | ROBIN ELECTRICAL CO., INC | General Wiring |
| 03/19/2019 | Cancelled | ROBIN ELECTRICAL CO., INC | General Wiring |
| 02/08/2018 | Cancelled | LINTECH ELECTRIC, INC. | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/05/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/05/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/19/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/07/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/07/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/31/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/06/2026 | Insulation placement and R values | Jeff Akerman | energy_progress |
| 01/06/2026 | Fire-Resistant Penetrations and Joints | Jeff Akerman | special |
| 01/06/2026 | Tenant Protection Plan Compliance | Jeff Akerman | special |
| 01/06/2026 | Final | Rachel Paskesz | progress |
| 01/06/2026 | Energy Code Compliance Inspections | Jeff Akerman | progress |
| 01/06/2026 | Fire-Resistance Rated Construction | Jeff Akerman | progress |
| 01/06/2026 | Lighting in dwelling units | Jeff Akerman | energy_progress |
| 02/07/2024 | Insulation placement and R values | Jeff Akerman | energy_progress |
| 02/07/2024 | Tenant Protection Plan Compliance | Jeff Akerman | special |
| 02/07/2024 | Final | SHIMON GREENEBAUM | progress |
| 02/07/2024 | Energy Code Compliance Inspections | Jeff Akerman | progress |
| 02/07/2024 | Fire-Resistance Rated Construction | Jeff Akerman | progress |
| 02/07/2024 | Lighting in dwelling units | Jeff Akerman | energy_progress |
| 02/07/2024 | Fire-Resistant Penetrations and Joints | Jeff Akerman | special |
| 05/08/2023 | Tenant Protection Plan Compliance | William Ryan | special |
| 05/08/2023 | Final | William Ryan | progress |
| 05/08/2023 | Mechanical Systems | William Ryan | special |
| 07/06/2022 | Final | Gregg Rothstein | progress |
| 07/06/2022 | Mechanical Systems | Gregg Rothstein | special |
| 06/28/2022 | Fire-Resistant Penetrations and Joints | Gregg Rothstein | special |
| 03/24/2020 | Fire-Resistant Penetrations and Joints | Gregg Rothstein | special |
| 03/24/2020 | Energy Code Compliance Inspections | Gregg Rothstein | progress |
| 11/19/2019 | Energy Code Compliance Inspections | Gregg Rothstein | progress |
| 11/19/2019 | Fire-Resistant Penetrations and Joints | Gregg Rothstein | special |