270 SEAMAN AVENUE
MANHATTAN · Inwood · BIN 1065083
💬 Discuss this project
1926Year Built
6Stories
D4Building Class
R7AZoning
50,066 sfGross Floor Area
50Units
LL97 CoveredRent Stabilized2 Active Violations ▸FISP: SAFE
Elevator cooperative · Owner of record: 270 Seaman Avenue Owners · 12,929 sf lot · 3.87 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalPlumbingEquipmentGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Floor 67p · 1 filing · 17 docs
Floor 5
Floor 4Under Construction10p · 2 filings · 20 docs
Floor 3Under Construction11p · 4 filings · 20 docs
Floor 2
Floor 1
Sub-Basement270 Seaman Column Repairs and Shoring1 filing · 6 docs
Site & exteriorHoulihan Parnes Properties13p · 3 filings · 14 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Houlihan Parnes Properties1907/08/2026
270 Seaman Owners903/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
F360 Architecture409/25/2026
Brennan Walsh104/08/2026
Enthink Engineers109/22/2023
Seth P. Roye Architect103/21/2023
Arcadian Design Services201/31/2023
Lab Architecture412/09/2022
PCS Engineering106/17/2022
Ashraf103/18/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Up Design Services203/21/2026
Mbe Code & Zoning403/21/2026
PCS Engineering103/21/2026
Expediting103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Topline NYC ContractingScaffold807/08/2026
Johannisburg CNSTNGeneral Contractor407/08/2026
Urban Design GroupGeneral Contractor303/21/2026
Phoenix Sutton STRScaffold207/08/2026
A.goldnerPlumbing203/22/2026
AK Premier ContractingGeneral Contractor208/30/2026
Brandl ElectricElectrical103/22/2026
New Era Mechanical ServicesPlumbing107/08/2026
R & L SystemsElectrical103/21/2026
New Force ConstructionGeneral Contractor107/08/2026
Orchid ConstructionGeneral Contractor107/08/2026
ILG Mechanical ServicesPlumbing108/12/2026
Mes ConstructionPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Jose A Santos PE3292309/25/2026
PCS Engineering3745204/08/2026
Walsh Engineering9393102/27/2026
Building Consulting Engineering1034103/21/2023
Seth P Roye Architect8554103/21/2023
Lab Architecture3653412/09/2022
Building Lifecycle
02/20/2028
Facade inspection report due (FISP Cycle 9, sub-cycle B)
The filing window opened 02/21/2026. No Cycle 9 filing on record yet
09/25/2026
Filed — Alteration
plumbing application related to interior renovation and merger of apts D3 and E3
M01342176-P2
09/14/2026
Special inspection requirement — Energy Code Compliance Inspections
Jose Cruz
09/14/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jose Santos
09/10/2026
Elevator Category 1 inspection report filed
199 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralPermit IssuedAK Premier Contracting08/27/2026
DOB NOWPlumbingPermit IssuedILG Mechanical Services08/11/2026
DOB NOWGeneral ConstructionPermit IssuedAK Premier Contracting07/28/2026
DOB NOWGeneral ConstructionSigned-offJohannisburg Construction10/08/2024
DOB NOWSidewalk ShedSigned-offPhoenix Sutton STR09/19/2024
DOB NOWSuspended ScaffoldSigned-offJohannisburg Construction04/04/2024
DOB NOWGeneral ConstructionSigned-offJohannisburg Construction10/31/2023
DOB NOWSidewalk ShedSigned-offPhoenix Sutton STR09/22/2023
DOB NOWGeneral ConstructionSigned-offOrchid Construction02/03/2023
DOB NOWPlumbingSigned-offNew Era Mechanical Services02/02/2023
DOB NOWPlumbingSigned-offMes Construction09/19/2022
DOB NOWGeneral ConstructionSigned-offUrban Design Group08/04/2022
DOB NOWGeneral ConstructionSigned-offNew Force Construction Co06/24/2022
DOB NOWSidewalk ShedPermit IssuedTopline NYC Contracting05/06/2021
DOB NOWSidewalk ShedPermit IssuedTopline NYC Contracting04/27/2020
DOB NOWSidewalk ShedPermit IssuedTopline NYC Contracting12/30/2019
DOB NOWSidewalk ShedPermit IssuedTopline NYC Contracting03/20/2019
BISOTISSUEDAAA Contracting Services08/12/2020
BISOTISSUEDAAA Contracting Services08/07/2019
BISOTISSUEDAAA Contracting Services05/31/2019
BISPLISSUEDBauer Mechancial08/06/2018
BISOTISSUEDStandard Maintenance08/06/2018
BISOTISSUEDAriston Chimney08/06/2018
BISEQISSUEDJ & G GNRL Contracting10/29/2013
BISEQISSUEDColgate Scaffolding & Eq02/13/2002
1 project · most recent 09/25/2026
Gas Water/Sanitary
FiledStatusContractorScope
09/25/2026Permit IssuedILG Mechanical ServicesGas, Water/Sanitary
3 projects · most recent 09/18/2023
General Wiring
FiledStatusContractorScope
09/18/2023CompleteElpo Electrical Contg—
01/31/2023CompleteBrandl ElectricGeneral Wiring
03/18/2019Permit IssuedRichard Neu—
1 project · most recent 03/18/2019
Sidewalk Shed
FiledStatusContractorScope
03/18/2019Permit IssuedTopline NYC ContractingSidewalk Shed
1 project · most recent 03/04/2024
Suspended Scaffold (SC)
FiledStatusContractorScope
03/04/2024Signed-offJohannisburg CNSTNSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
09/08/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/23/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/23/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/09/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/04/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/28/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 26
DateRequirementInspectorRole
09/14/2026Energy Code Compliance InspectionsJose Cruzprogress
09/14/2026Fire-Resistant Penetrations and JointsJose Santosspecial
06/03/2026Energy Code Compliance InspectionsJose Cruzprogress
06/03/2026Fire-Resistant Penetrations and JointsJose Santosspecial
04/08/2026Structural Steel - DetailsMichael Walshspecial
04/08/2026PreliminaryBrennan Walshprogress
04/08/2026Structural Wood FrameBrennan Walshprogress
04/08/2026Wood – Seismic ResistanceMichael Walshspecial
04/06/2026Designated Seismic SystemMichael Walshspecial
04/02/2026FinalBrennan Walshprogress
01/25/2023FinalMELISSA ROTONDAROprogress
01/25/2023Fire-Resistance Rated ConstructionMELISSA ROTONDAROprogress
12/24/2022Fire-Resistant Penetrations and JointsLeslie Barnettspecial
12/24/2022FinalLeslie Barnettprogress
12/24/2022Fire-Resistance Rated ConstructionLeslie Barnettprogress
12/24/2022Energy Code Compliance InspectionsLeslie Barnettprogress
12/24/2022Lighting in dwelling unitsLeslie Barnettenergy_progress
12/12/2022Energy Code Compliance InspectionsSeth Royeprogress
12/12/2022Tenant Protection Plan ComplianceTONY ONYEAGOROspecial
12/12/2022Fire-Resistant Penetrations and JointsSeth Royespecial
12/12/2022MasonrySeth Royespecial
12/12/2022FinalSeth Royeprogress
12/09/2022Fire-Resistant Penetrations and JointsLeslie Barnettspecial
06/17/2022Structural Stability – Alterations of existing buildingsMichael Walshspecial
06/17/2022MasonryMichael Walshspecial
Latest 25 of 26.