| Owner | Filings | Most Recent |
|---|---|---|
| Essen Healthcare | 3 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 07/08/2016 | $550K | — | MEDIWAY ENTERPRISES, LLC → 2702 THIRD AVENUE REALTY, LLC | $156/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Asda Architecture + Design | 1 | 07/20/2022 |
| Vilas Parab | 5 | 03/11/2022 |
| Joel Phagoo P.E | 3 | 11/10/2021 |
| Paul Perdek, Prof. Engineering | 1 | 11/10/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| A1 Expediting Service | 8 | 03/21/2026 |
| Julian Alberto Gomez | 5 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Yarks NYC | Scaffold | 10 | 07/08/2026 |
| KDL Construction & Development | General Contractor | 3 | 07/08/2026 |
| KDL Construction & Development | Scaffold | 2 | 07/08/2026 |
| Corporate Electric Group | Electrical | 1 | 03/21/2026 |
| Ace Electrical Construction | Electrical | 1 | 03/22/2026 |
| Ace Electrical Construction | Electrical | 1 | 03/21/2026 |
| Service Sign Erectors Co | Sign hanger | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Joel Phagoo, PE | 2416 | 2 | 11/10/2021 |
| Chong Engineering | 7411 | 4 | 10/20/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sign | Permit Issued | Service Sign Erectors Co | 07/22/2022 |
| DOB NOW | Structural | Permit Issued | KDL Construction & Development | 05/24/2022 |
| DOB NOW | Construction Fence | Permit Issued | KDL Construction & Development | 05/17/2022 |
| DOB NOW | Construction Fence | Permit Issued | KDL Construction & Development | 03/31/2022 |
| DOB NOW | Sidewalk Shed | Permit Issued | Yarks NYC | 02/24/2022 |
| DOB NOW | Supported Scaffold | Permit Issued | Yarks NYC | 02/23/2022 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Yarks NYC | 02/22/2022 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Yarks NYC | 11/12/2021 |
| DOB NOW | Supported Scaffold | Permit Issued | Yarks NYC | 08/20/2021 |
| DOB NOW | Sidewalk Shed | Permit Issued | Yarks NYC | 08/10/2021 |
| DOB NOW | Structural | Permit Issued | KDL Construction & Development | 05/10/2021 |
| DOB NOW | Structural | Permit Issued | KDL Construction & Development | 04/30/2021 |
| BIS | OT | ISSUED | KDL Construction & Development | 05/16/2022 |
| BIS | PL | ISSUED | Courtesy Plumbing | 01/07/2022 |
| BIS | OT | ISSUED | KDL Construction & Development | 10/13/2020 |
| BIS | OT | ISSUED | KDL Construction & Development | 09/06/2019 |
| BIS | OT | ISSUED | KDL Construction & Development | 05/15/2019 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/11/2022 | Permit Issued | Corporate Electric Group | — |
| 01/06/2022 | Permit Issued | Ace Electrical Construction | General Wiring |
| 08/03/2021 | Complete | Richard Neu | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/26/2021 | Permit Issued | KDL Construction & Development | Steel, Concrete, Masonry |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/08/2022 | Final | Alfonso DElia | progress |
| 11/16/2021 | Post-installed Anchors | JOEL PHAGOO | special |
| 10/12/2021 | Post-installed Anchors | JOEL PHAGOO | special |
| 10/03/2021 | Energy Code Compliance Inspections | Tae Chong | progress |
| 09/10/2021 | Fire-Resistant Penetrations and Joints | Tae Chong | special |
| 05/20/2021 | Metering | Tae Chong | energy_progress |
| 05/16/2021 | Sprinkler Systems | Tae Chong | special |
| 05/08/2021 | Energy Code Compliance Inspections | Tae Chong | progress |
| 04/05/2021 | Energy Code Compliance Inspections | Tae Chong | progress |
| 04/05/2021 | Sprayed fire-resistant materials | Tae Chong | special |
| 04/05/2021 | Structural Steel - Details | Tae Chong | special |
| 02/28/2021 | Fire-Resistant Penetrations and Joints | Tae Chong | special |
| 02/28/2021 | Structural Steel - Welding | Tae Chong | special |
| 02/28/2021 | Structural Stability – Alterations of existing buildings | Tae Chong | special |
| 02/28/2021 | Concrete - Cast-In-Place | Tae Chong | special |
| 01/07/2021 | Final | Tae Chong | progress |
| 01/07/2021 | Structural Cold-Formed Steel | Tae Chong | special |
| 01/07/2021 | Masonry | Tae Chong | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Essen Medical Center | Medical / Healthcare | Cellar, Floors 1–3, Roof | Project X00522992 Project X00559698 Project X00518689 Project X00450062 |