| Owner | Filings | Most Recent |
|---|---|---|
| PARK CONTRACTING GROUP | 6 | 04/09/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 07/26/2024 | $521K | — | — → — | $342/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ALWAYS FAST SERVICES CORP | 2 | 02/20/2026 |
| A&T CORP | 1 | 07/31/2025 |
| A & T ENGINEERING, P.C. | 6 | 07/15/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| A & T DESIGN GROUP LLC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ZEFI & CO. LLC | General Contractor | 10 | 08/16/2026 |
| ADRIAN ROTARIU | Electrical | 2 | 03/21/2026 |
| RICHARD NEU | Electrical | 1 | 03/21/2026 |
| GO PRO FIRE PROTECTION C | Fire Protection | 1 | 07/08/2026 |
| PARK CONTRACTING GROUP | General Contractor | 1 | 04/09/2026 |
| INFINITI ESC PLUMBING COR | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SJS INSPECTIONS AND CONSU | 8286 | 5 | 07/31/2025 |
| A & T DESIGN GROUP LLC | 1088 | 1 | 09/06/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | ZEFI & CO. LLC | 08/14/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | ZEFI & CO. LLC | 04/07/2026 |
| DOB NOW | Plumbing | Permit Issued | INFINITI ESC PLUMBING COR | 02/24/2026 |
| DOB NOW | Plumbing | Permit Issued | GO PRO FIRE PROTECTION C | 02/23/2026 |
| DOB NOW | General Construction | Permit Issued | ZEFI & CO. LLC | 01/28/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | PARK CONTRACTING GROUP | 12/12/2025 |
| DOB NOW | Construction Fence | Permit Issued | ZEFI & CO. LLC | 10/30/2025 |
| DOB NOW | Earth Work | Permit Issued | ZEFI & CO. LLC | 08/05/2025 |
| DOB NOW | Structural | Permit Issued | ZEFI & CO. LLC | 07/29/2025 |
| DOB NOW | Full Demolition | Signed-off | ZEFI & CO. LLC | 11/07/2024 |
| DOB NOW | Construction Fence | Permit Issued | ZEFI & CO. LLC | 11/04/2024 |
| BIS | OT | ISSUED | TWIN CONTRACTORS | 08/14/2006 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/31/2025 | Permit Issued | ZEFI & CO. LLC | Heating and Air Conditioning Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/31/2025 | Permit Issued | GO PRO FIRE PROTECTION C | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/31/2025 | Permit Issued | INFINITI ESC PLUMBING COR | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/12/2025 | Permit Issued | RICHARD NEU | — |
| 12/05/2025 | Permit Issued | AV GROUP ELECTRICAL LLC | General Wiring |
| 08/07/2025 | Permit Issued | AV GROUP ELECTRICAL LLC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/31/2025 | Permit Issued | ZEFI & CO. LLC | Steel, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/21/2024 | Permit Issued | ZEFI & CO. LLC | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/31/2025 | Permit Issued | ZEFI & CO. LLC | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/06/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/10/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/24/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/17/2026 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 03/06/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 03/06/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 07/28/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/30/2025 | Fire-Resistant Penetrations and Joints | SERGEY BOLOTOV | special |
| 07/30/2025 | Heating Systems | SERGEY BOLOTOV | special |
| 07/30/2025 | Energy Code Compliance Inspections | SERGEY BOLOTOV | progress |
| 07/30/2025 | HVAC-R and service water piping design and insulation | SERGEY BOLOTOV | energy_progress |
| 07/30/2025 | HVAC-R and service water heating system controls | SERGEY BOLOTOV | energy_progress |
| 07/30/2025 | HVAC-R and service water heating equipment | SERGEY BOLOTOV | energy_progress |
| 07/30/2025 | Shutoff dampers | SERGEY BOLOTOV | energy_progress |
| 07/30/2025 | Ventilation and air distribution system | SERGEY BOLOTOV | energy_progress |
| 07/24/2025 | Mechanical Systems | SERGEY BOLOTOV | special |
| 07/24/2025 | Final | SERGEY BOLOTOV | progress |
| 07/14/2025 | Post-installed Anchors | SERGEY BOLOTOV | special |
| 07/03/2025 | Excavations - Sheeting, Shoring, and Bracing | SERGEY BOLOTOV | special |
| 07/03/2025 | Structural Stability – Alterations of existing buildings | SERGEY BOLOTOV | special |
| 07/03/2025 | Subsurface Investigations (Borings/Test Pits) | ROBERT DYKSTRA | special |
| 07/03/2025 | Structural Stability – Alterations of existing buildings | SERGEY BOLOTOV | special |
| 07/03/2025 | Concrete - Cast-In-Place | SERGEY BOLOTOV | special |
| 07/02/2025 | Structural Steel - Welding | SERGEY BOLOTOV | special |
| 07/02/2025 | Masonry | SERGEY BOLOTOV | special |
| 07/02/2025 | Structural Steel - High Strength Bolting | SERGEY BOLOTOV | special |
| 07/02/2025 | Structural Steel - Details | SERGEY BOLOTOV | special |
| 07/02/2025 | Structural Cold-Formed Steel | SERGEY BOLOTOV | special |
| 07/01/2025 | Footing and Foundation | SERGEY BOLOTOV | progress |
| 07/01/2025 | Final | SERGEY BOLOTOV | progress |
| 06/24/2025 | Final | SERGEY BOLOTOV | progress |
| 03/11/2025 | Maintenance information | SERGEY BOLOTOV | energy_progress |