← Back
One family attached or semi-detached
2715 SEYMOUR AVENUE
BRONX · Pelham Gardens · BIN 2054379
💬 Discuss this project
1955Year Built
2Stories
A5Building Class
R4Zoning
992 sfGross Floor Area
1Units
2 Open Violations ▸FDNY Report ↗
One family attached or semi-detached · 2,500 sf lot · 0.4 FAR built · Flood zone X
Locations of Work
Architecture
Filed — no permit issued7p · 1 filing · 8 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
2715 SEYMOUR103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
08/26/2025$685K—— → —$691/sf building
10/04/2024$400K—— → —$403/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CHANDA ENGINEERING CONSULTANT PC111/29/2025
Building Lifecycle
All (34)Filed (1)Violation (4)Objection (19)Special Inspection (10)
04/05/2026
Objection resolved — Addressed
03/19/2026
Objection resolved — Addressed
03/19/2026
Objection resolved — Addressed
03/19/2026
Objection resolved — Resolved
03/19/2026
Objection resolved — Resolved
03/19/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
02/24/2026
Objection resolved — Addressed
02/24/2026
Objection resolved — Addressed
02/24/2026
Objection resolved — Addressed
02/24/2026
Objection resolved — Resolved
12/08/2025
Objection raised — Scope
12/08/2025
Objection raised — Scope
12/08/2025
Objection raised — Zoning
12/08/2025
Objection raised — Mechanical
12/08/2025
Objection raised — Structural
12/08/2025
Objection raised — Structural
12/08/2025
Objection raised — Energy
12/08/2025
Objection raised — Scope
12/08/2025
Objection raised — Structural
12/08/2025
Objection raised — Structural
11/29/2025
Filed — Alteration
PROPOSED TO LEGALIZE HORIZONTAL EXTENSION IN CELLAR & 1ST FLOOR REAR SIDE OF THE BUILDING TO COMPLY ECB VIOLATION# 39161244R & DOB VIOLATION#VIO25-02196. NO CHANGE IN USE, EGRESS & OCCUPANCY WITH THIS APPLICATION.
X01322280-I1
11/29/2025
Special inspection requirement — Fenestration areas
11/28/2025
Special inspection requirement — Energy Code Compliance Inspections
11/28/2025
Special inspection requirement — Fire-Resistance Rated Construction
11/28/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
11/28/2025
Special inspection requirement — Fenestration air leakage
11/28/2025
Special inspection requirement — Air barrier - visual inspection
11/28/2025
Special inspection requirement — Insulation placement and R values
11/28/2025
Special inspection requirement — Interior lighting power
11/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
10/21/2025
Violation issued (ECB, open)
Construction
09/23/2025
Violation issued (ECB, closed)
Construction
09/23/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/10/1993
Violation issued (ECB, closed)
Zoning
Nothing on file for this building.
1 project · most recent 11/29/2025
FiledStatusContractorScope
11/29/2025——1 scope_items
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
03/19/2026Structural Stability – Alterations of existing buildings—special
11/29/2025Fenestration areas—energy_progress
11/28/2025Energy Code Compliance Inspections—progress
11/28/2025Fire-Resistance Rated Construction—progress
11/28/2025Fenestration and door U-factor and product ratings—energy_progress
11/28/2025Fenestration air leakage—energy_progress
11/28/2025Air barrier - visual inspection—energy_progress
11/28/2025Insulation placement and R values—energy_progress
11/28/2025Interior lighting power—energy_progress
11/28/2025Fire-Resistant Penetrations and Joints—special
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/17/2026X01322280-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram2
08/17/2026X01322280-I1Open ↗
08/13/2026X01322280-I1Open ↗
▸DOB NOWRestrictive Declaration/Easement 11
08/17/2026X01322280-I1Open ↗
▸Seals & Professional Certifications1
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026X01322280-I1Open ↗
▸Other Documents3
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026X01322280-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026X01322280-I1Open ↗
▸DOB NOWPlot Diagram1
08/13/2026X01322280-I1Open ↗