1930Year Built
2Stories
A1Building Class
R4Zoning
1,700 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 2,500 sf lot · 0.68 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Roof3p · 1 filing · 7 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
PLATINUM SERVICES NY103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NY BUILDING ASSOCIATES INC108/21/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
S R SOLAR DESIGN203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
VOLTAIR SOLAR LLCGeneral Contractor303/21/2026
B.P. ELECTRIC CORPElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NKM ENGINEERING PLLC6244108/21/2024
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
11/27/2024
Signed off — Alteration
X01088307-I1
08/28/2024
Permit issued — Solar
X01088307-I1-SL
08/21/2024
Filed — Alteration
X01088307-I1
07/30/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
07/30/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
NARESH MAHANGU
07/30/2024
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
07/30/2024
Special inspection requirement — Final
NARESH MAHANGU
07/30/2024
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offVOLTAIR SOLAR LLC08/28/2024
2 projects · most recent 11/05/2024
FiledStatusContractorScope
11/05/2024CompleteB.P. ELECTRIC CORP—
08/22/2024CancelledB.P. ELECTRIC CORP—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
07/30/2024Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
07/30/2024Structural Stability – Alterations of existing buildingsNARESH MAHANGUspecial
07/30/2024Energy Code Compliance InspectionsNARESH MAHANGUprogress
07/30/2024FinalNARESH MAHANGUprogress
07/30/2024Air barrier - visual inspectionNARESH MAHANGUenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/21/2026X01088307-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/23/2026X01088307-I1Open ↗
08/23/2026X01088307-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026X01088307-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/23/2026X01088307-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026X01088307-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026X01088307-I1Open ↗