← Back
Two family brick
274 3 AVENUE
BROOKLYN · BIN 3323376
💬 Discuss this project
1800Year Built
3Stories
B1Building Class
M1-4/R6BZoning
2,700 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family brick · Owner of record: 274 THIRD LLC · 1,600 sf lot · 1.69 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Roof5p · 3 filings · 20 docs
Bulkhead2p · 2 filings · 12 docs
Floor 31p · 1 filing · 10 docs
Floor 21p · 1 filing · 6 docs
Floor 1
Cellar7p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
274 THIRD3407/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/10/2021$2.7M—Private party → 274 THIRD LLC$1,000/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CES ENGINEERING LLC505/22/2025
JOSEPH K. BLUM CO. LLP110/11/2023
FORMAT ARCHITECTURE OFFICE, PLLC208/29/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
DVA Advisors803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ZOON DEVELOPMENT INCGeneral Contractor807/08/2026
PBS CONSTRUCTION CORPGeneral Contractor504/09/2026
M & M PIPING AND HEATINGPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
INTEGRITY CONSULTING SERV666705/22/2025
Building Lifecycle
All (64)Filed (7)Permit Issued (10)Signed Off (4)Violation (1)Inspection (5)Objection (12)Special Inspection (25)
11/07/2025
Signed off — Alteration
B07995942-I1
11/07/2025
Signed off — Alteration
General Construction at cellar, 1st floor, 2nd floor, and roof as per plans filed herewith. No change in use, egress, or occupancy.
B00774339-I1
10/17/2025
Signed off — Alteration
Additions/Modifications to existing mechanical system. No change to use, egress, or occupancy.
B07998412-I1
10/16/2025
Signed off — Alteration
Additions/Modifications to existing plumbing system. No change to use, egress, or occupancy.
B07998405-I1
06/09/2025
Objection raised — Other
06/09/2025
Objection resolved — Addressed
05/22/2025
Filed — Alteration
Additions/Modifications to existing mechanical system. No change to use, egress, or occupancy.
B07998412-P1
02/07/2025
Filed — Alteration
Additions/Modifications to existing plumbing system. No change to use, egress, or occupancy.
B07998405-P2
01/27/2025
Permit issued — General Construction
B00774339-I1-GC
12/02/2024
Permit issued — Plumbing
B07998405-I1-PL
11/22/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/31/2024
Permit issued — Structural
B07995942-I1-ST
10/31/2024
Permit issued — Mechanical Systems
B07998412-I1-MS
09/13/2024
Permit issued — General Construction
B00774339-I1-GC
08/23/2024
Permit issued — General Construction
B00774339-I1-GC
04/29/2024
Violation issued (ECB, closed)
Construction
03/15/2024
Objection resolved — Addressed
02/29/2024
Objection raised — Scope
02/27/2024
Filed — Alteration
Additions/Modifications to existing plumbing system. No change to use, egress, or occupancy.
B07998405-P1
02/23/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEKSANDR LEVIN
02/23/2024
Special inspection requirement — Maintenance information
ALEKSANDR LEVIN
02/23/2024
Special inspection requirement — Permanent certificate
ALEKSANDR LEVIN
02/23/2024
Special inspection requirement — HVAC-R and service water heating system controls
ALEKSANDR LEVIN
02/23/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
ALEKSANDR LEVIN
02/23/2024
Special inspection requirement — Energy Code Compliance Inspections
ALEKSANDR LEVIN
01/19/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/08/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
01/08/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/08/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
11/29/2023
Permit issued — Plumbing
B07998405-I1-PL
11/13/2023
Permit issued — Structural
B07995942-I1-ST
11/13/2023
Permit issued — Mechanical Systems
B07998412-I1-MS
11/06/2023
Objection resolved — Addressed
10/24/2023
Objection resolved — Addressed
10/20/2023
Objection resolved — Addressed
10/20/2023
Objection resolved — Addressed
10/11/2023
Filed — Alteration
B07995942-I1
10/06/2023
Permit issued — General Construction
B00774339-I1-GC
10/06/2023
Objection raised — Admin
10/06/2023
Objection raised — Admin
10/06/2023
Objection raised — Scope
10/06/2023
Objection raised — Admin
10/06/2023
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
ALEKSANDR LEVIN
10/05/2023
Filed — Alteration
Additions/Modifications to existing mechanical system. No change to use, egress, or occupancy.
B07998412-I1
10/05/2023
Filed — Alteration
Additions/Modifications to existing plumbing system. No change to use, egress, or occupancy.
B07998405-I1
09/22/2023
Special inspection requirement — Masonry
ALEKSANDR LEVIN
09/22/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
ALEKSANDR LEVIN
09/22/2023
Special inspection requirement — Structural Steel - Details
ALEKSANDR LEVIN
09/22/2023
Special inspection requirement — Structural Steel - High Strength Bolting
ALEKSANDR LEVIN
09/22/2023
Special inspection requirement — Structural Steel - Welding
ALEKSANDR LEVIN
08/14/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
08/14/2023
Special inspection requirement — Masonry
08/14/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
08/14/2023
Special inspection requirement — Fenestration areas
08/14/2023
Special inspection requirement — Lighting in dwelling units
08/14/2023
Special inspection requirement — Interior lighting power
08/14/2023
Special inspection requirement — Fenestration air leakage
08/14/2023
Special inspection requirement — Insulation placement and R values
08/14/2023
Special inspection requirement — Lighting controls
08/14/2023
Special inspection requirement — Exterior lighting power
Latest 60 of 64 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offPBS CONSTRUCTION CORP01/27/2025
DOB NOWPlumbingSigned-offM & M PIPING AND HEATING12/02/2024
DOB NOWStructuralSigned-offZOON DEVELOPMENT INC10/31/2024
DOB NOWMechanical SystemsSigned-offZOON DEVELOPMENT INC10/31/2024
DOB NOWGeneral ConstructionSigned-offPBS CONSTRUCTION CORP09/13/2024
DOB NOWGeneral ConstructionSigned-offPBS CONSTRUCTION CORP08/23/2024
DOB NOWPlumbingSigned-offM & M PIPING AND HEATING11/29/2023
DOB NOWStructuralSigned-offZOON DEVELOPMENT INC11/13/2023
DOB NOWMechanical SystemsSigned-offZOON DEVELOPMENT INC11/13/2023
DOB NOWGeneral ConstructionSigned-offZOON DEVELOPMENT INC10/06/2023
1 project · most recent 07/16/2025
General Wiring
FiledStatusContractorScope
07/16/2025Permit IssuedMADISON ELECTRIC, INCGeneral Wiring
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
11/22/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/19/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/08/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
01/08/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/08/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 25
DateRequirementInspectorRole
02/23/2024Fire-Resistant Penetrations and JointsALEKSANDR LEVINspecial
02/23/2024Maintenance informationALEKSANDR LEVINenergy_progress
02/23/2024Permanent certificateALEKSANDR LEVINenergy_progress
02/23/2024HVAC-R and service water heating system controlsALEKSANDR LEVINenergy_progress
02/23/2024HVAC-R and service water piping design and insulationALEKSANDR LEVINenergy_progress
02/23/2024Energy Code Compliance InspectionsALEKSANDR LEVINprogress
10/06/2023Alternative Materials - OTCR Buildings Bulletin NumberALEKSANDR LEVINspecial
09/22/2023MasonryALEKSANDR LEVINspecial
09/22/2023Structural Stability – Alterations of existing buildingsALEKSANDR LEVINspecial
09/22/2023Structural Steel - DetailsALEKSANDR LEVINspecial
09/22/2023Structural Steel - High Strength BoltingALEKSANDR LEVINspecial
09/22/2023Structural Steel - WeldingALEKSANDR LEVINspecial
08/14/2023Fire-Resistant Penetrations and Joints—special
08/14/2023Masonry—special
08/14/2023Fenestration and door U-factor and product ratings—energy_progress
08/14/2023Fenestration areas—energy_progress
08/14/2023Lighting in dwelling units—energy_progress
08/14/2023Interior lighting power—energy_progress
08/14/2023Fenestration air leakage—energy_progress
08/14/2023Insulation placement and R values—energy_progress
08/14/2023Lighting controls—energy_progress
08/14/2023Exterior lighting power—energy_progress
08/14/2023Fire-Resistance Rated Construction—progress
08/14/2023Final—progress
08/30/2022FinalALEKSANDR LEVINprogress
▾Documents — 27 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/28/2026B00774339-I1Request digital key ↗
08/28/2026B00774339-P1Request digital key ↗
08/26/2026B07998405-P2Request digital key ↗
Showing 3 of 8 on file for this type
▸Seals & Professional Certifications14
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/28/2026B00774339-I1Open ↗
08/26/2026B07998412-P1Open ↗
08/26/2026B07998412-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
08/23/2026B07995942-I1Open ↗
08/22/2026B07998405-P1Open ↗
08/22/2026B07998405-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
08/23/2026B07995942-I1Open ↗
08/23/2026B07995942-I1Open ↗
08/22/2026B07998405-P1Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form4
08/26/2026B07998412-I1Open ↗
08/13/2026B07995942-I1Open ↗
08/13/2026B00774339-I1Open ↗
Showing 3 of 4 on file for this type
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026B00774339-I1Open ↗