← Back
Two stories - detached, small or mid-size
275 ARKANSAS DRIVE
BROOKLYN · BIN 3243041
💬 Discuss this project
1960Year Built
2Stories
A1Building Class
R2Zoning
2,804 sfGross Floor Area
1Units
21 Open Violations 20 unresolved · 1 paperwork only ▸FDNY Report ↗
Two stories - detached, small or mid-size · 4,200 sf lot · 0.67 FAR built · Flood zone VE
Locations of Work
Architecture
Roof1p · 1 filing · 20 docs
1 job · most recent 02/23/2026
Steel
FiledStatusContractorScope
02/23/2026——Steel
1 job · most recent 02/23/2026
Fence
FiledStatusContractorScope
02/23/2026——Fence
Building Lifecycle
All (123)Filed (6)Violation (22)Objection (65)Special Inspection (30)
04/13/2026
Objection resolved — Addressed
03/09/2026
Special inspection requirement — Air barrier — testing
Alix Michel
03/09/2026
Special inspection requirement — Interior lighting power
Alix Michel
03/09/2026
Special inspection requirement — Maintenance information
Alix Michel
03/09/2026
Special inspection requirement — Permanent certificate
Alix Michel
03/09/2026
Special inspection requirement — Fenestration areas
Alix Michel
03/09/2026
Special inspection requirement — Electric vehicle service equipment requirements
Alix Michel
03/09/2026
Special inspection requirement — Metering
Alix Michel
03/09/2026
Special inspection requirement — Fenestration air leakage
Alix Michel
03/09/2026
Special inspection requirement — Protection of exposed foundation insulation
Alix Michel
03/09/2026
Special inspection requirement — Insulation placement and R values
Alix Michel
03/09/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Alix Michel
03/09/2026
Special inspection requirement — Subgrade Inspections
Joe Lieberman
03/09/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Joe Lieberman
03/09/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Joe Lieberman
03/09/2026
Special inspection requirement — Energy Code Compliance Inspections
Joe Lieberman
03/09/2026
Special inspection requirement — Fire-Resistance Rated Construction
Joe Lieberman
03/09/2026
Special inspection requirement — Air barrier - visual inspection
Alix Michel
02/24/2026
Objection resolved — Addressed
02/23/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
SUBSEQUENT FOUNDATION APPLICATION IN CONJUNCTION WITH APPROVED GC #B01266823-I1
B01266823-P1
02/23/2026
Special inspection requirement — Fenestration areas
Alix Michel
02/23/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Joe Lieberman
02/23/2026
Special inspection requirement — Subgrade Inspections
Joe Lieberman
02/23/2026
Special inspection requirement — Energy Code Compliance Inspections
Joe Lieberman
02/23/2026
Special inspection requirement — Fire-Resistance Rated Construction
Joe Lieberman
02/23/2026
Special inspection requirement — Maintenance information
Alix Michel
02/23/2026
Special inspection requirement — Permanent certificate
Alix Michel
02/23/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Alix Michel
02/23/2026
Special inspection requirement — Metering
Alix Michel
02/23/2026
Special inspection requirement — Air barrier — testing
Alix Michel
02/23/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Joe Lieberman
02/23/2026
Special inspection requirement — Electric vehicle service equipment requirements
Alix Michel
02/23/2026
Special inspection requirement — Insulation placement and R values
Alix Michel
02/05/2026
Objection resolved — Addressed
01/16/2026
Objection resolved — Addressed
12/23/2025
Objection resolved — Addressed
12/23/2025
Objection resolved — Addressed
12/23/2025
Objection resolved — Addressed
12/23/2025
Objection resolved — Addressed
12/11/2025
Objection resolved — Addressed
12/11/2025
Objection resolved — Addressed
12/10/2025
Objection raised — Scope
12/10/2025
Objection raised — Scope
12/09/2025
Objection raised — Inspections
12/09/2025
Objection raised — Structural
12/09/2025
Objection raised — Inspections
12/09/2025
Objection raised — Structural
12/09/2025
Objection raised — Structural
12/09/2025
Objection raised — Admin
12/09/2025
Objection raised — Admin
12/09/2025
Objection raised — Other
12/01/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
SUBSEQUENT FOUNDATION APPLICATION IN CONJUNCTION WITH APPROVED GC #B01266823-I1
B01266823-S5
12/01/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
SUBSEQUENT FOUNDATION APPLICATION IN CONJUNCTION WITH APPROVED GC #B01266823-I1
B01266823-S4
11/17/2025
Objection resolved — Addressed
11/15/2025
Objection raised — Other
11/11/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
SUBSEQUENT FOUNDATION APPLICATION IN CONJUNCTION WITH APPROVED GC #B01266823-I1
B01266823-S3
10/29/2025
Objection resolved — Addressed
10/29/2025
Objection resolved — Addressed
10/29/2025
Objection resolved — Addressed
10/29/2025
Objection resolved — Addressed
Latest 60 of 123 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CITISCAPE CONSULTING LTD1003/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/25/2022$900K—Private party → Private party$321/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CITISCAPE CONSULTING LTD502/23/2026
SYED ENGINEERING, P.C.105/15/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CITISCAPE CONSULTING LTD1003/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CITISCAPE CONSULTING LTD762302/23/2026
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 45
DateRequirementInspectorRole
03/09/2026Air barrier — testing Alix Michelenergy_progress
03/09/2026Interior lighting powerAlix Michelenergy_progress
03/09/2026Maintenance informationAlix Michelenergy_progress
03/09/2026Permanent certificateAlix Michelenergy_progress
03/09/2026Fenestration areasAlix Michelenergy_progress
03/09/2026Electric vehicle service equipment requirementsAlix Michelenergy_progress
03/09/2026MeteringAlix Michelenergy_progress
03/09/2026Fenestration air leakageAlix Michelenergy_progress
03/09/2026Protection of exposed foundation insulationAlix Michelenergy_progress
03/09/2026Insulation placement and R valuesAlix Michelenergy_progress
03/09/2026Fenestration and door U-factor and product ratingsAlix Michelenergy_progress
03/09/2026Subgrade InspectionsJoe Liebermanspecial
03/09/2026Fire-Resistant Penetrations and JointsJoe Liebermanspecial
03/09/2026Structural Stability – Alterations of existing buildingsJoe Liebermanspecial
03/09/2026Energy Code Compliance InspectionsJoe Liebermanprogress
03/09/2026Fire-Resistance Rated ConstructionJoe Liebermanprogress
03/09/2026Air barrier - visual inspectionAlix Michelenergy_progress
02/23/2026Fenestration areasAlix Michelenergy_progress
02/23/2026Structural Stability – Alterations of existing buildingsJoe Liebermanspecial
02/23/2026Subgrade InspectionsJoe Liebermanspecial
02/23/2026Energy Code Compliance InspectionsJoe Liebermanprogress
02/23/2026Fire-Resistance Rated ConstructionJoe Liebermanprogress
02/23/2026Maintenance informationAlix Michelenergy_progress
02/23/2026Permanent certificateAlix Michelenergy_progress
02/23/2026Fenestration and door U-factor and product ratingsAlix Michelenergy_progress
Latest 25 of 45.
▾Documents — 45 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/21/2026B01222583-I1Request digital key ↗
08/19/2026B01266823-P1Request digital key ↗
08/19/2026B01266823-S3Request digital key ↗
Showing 3 of 6 on file for this type
▸Zoning, Tax Lot & Property Records6
▸DOB NOWHouse Number Verification: TOPO Stamp2
08/19/2026B01266823-P1Open ↗
08/14/2026B01266823-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/19/2026B01266823-P1Open ↗
08/14/2026B01266823-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram2
08/19/2026B01266823-P1Open ↗
08/14/2026B01266823-I1Open ↗
▸Seals & Professional Certifications18
▸DOB NOWProgress Inspector Seal & Signature8
08/28/2026B01266823-S2Open ↗
08/23/2026B01266823-P1Open ↗
08/23/2026B01266823-P1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/21/2026B01222583-I1Open ↗
08/19/2026B01266823-P1Open ↗
08/19/2026B01266823-S5Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/28/2026B01266823-S2Open ↗
08/23/2026B01266823-P1Open ↗
08/23/2026B01266823-S5Open ↗
Showing 3 of 4 on file for this type
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/19/2026B01266823-P1Open ↗
08/14/2026B01266823-I1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/14/2026B01266823-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/19/2026B01266823-P1Open ↗
08/14/2026B01266823-S5Open ↗
08/14/2026B01266823-I1Open ↗
▸Inspections & Test Reports3
▸DOB NOWGeotechnical Report (BC 1803.6)1
08/15/2026B01266823-S4Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/15/2026B01266823-S4Open ↗
▸DOB NOWSOIL REPORT1
08/15/2026B01266823-S4Open ↗
▸Other Documents6
▸DOB NOWProperty Ownership Certification2
08/19/2026B01266823-P1Open ↗
08/14/2026B01266823-I1Open ↗
▸DOB NOWSite Survey: Initial2
08/19/2026B01266823-P1Open ↗
08/14/2026B01266823-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/19/2026B01266823-P1Open ↗
08/14/2026B01266823-I1Open ↗