| Firm | Filings | Most Recent |
|---|---|---|
| CHON ENGINEERING | 2 | 11/15/2023 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| I DO PLUMBING & HTG INC | Plumbing | 1 | 07/08/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | I DO PLUMBING & HTG INC | 06/13/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/15/2023 | Signed-off | I DO PLUMBING & HTG INC | Gas |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/17/2023 | Energy Code Compliance Inspections | Steve Chon | progress |
| 11/17/2023 | HVAC-R and service water piping design and insulation | Steve Chon | energy_progress |
| 11/17/2023 | HVAC-R and service water heating system controls | Steve Chon | energy_progress |
| 11/17/2023 | HVAC-R and service water heating equipment | Steve Chon | energy_progress |