← Back
Predominantly retail with other uses
2768 WEBSTER AVENUE
BRONX · BIN 2016233
💬 Discuss this project
1920Year Built
2Stories
K4Building Class
C4-5DZoning
—Gross Floor Area
8Units
0 Open Violations
Predominantly retail with other uses · Owner of record: SOUTH BRONX DEVELOPMENT I LLC · 0.18 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionCivilGeneral
Roof16p · 3 filings · 20 docs
Bulkhead1p · 1 filing · 20 docs
Floor 133p · 2 filings · 20 docs
Floor 124p · 2 filings · 20 docs
Floor 112p · 2 filings · 20 docs
Floor 102p · 2 filings · 20 docs
Floor 94p · 2 filings · 20 docs
Floor 85p · 2 filings · 20 docs
Floor 72p · 1 filing · 2 docs
Floor 62p · 1 filing · 2 docs
Floor 52p · 1 filing · 2 docs
Floor 42p · 1 filing · 2 docs
Floor 34p · 2 filings · 20 docs
Floor 27p · 2 filings · 20 docs
Floor 14p · 2 filings · 20 docs
Cellar9p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
RYTY HOME BUILDERS1209/13/2026
YYY 62ND STREET1108/05/2026
BANDRY LLC203/22/2026
OWNER OF 2768 WEBSTER AV203/22/2026
BANDY, LLC103/22/2026
PENN CENTRAL CORP103/22/2026
OWNER OF PREMISES103/22/2026
SOUTH BRONX DEVELOPMENT I LLC103/22/2026
REALITY103/21/2026
PLAZA REST SUPPLY303/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AUFGANG ARCHITECTS806/04/2026
FAIRFIELD TESTING LABORATORY101/21/2026
ADROIT ENGINEERING PLLC302/06/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MIELE SOLUTIONS1003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DM80 SOLUTIONS LLCGeneral Contractor408/05/2026
CAPE PLUMBING INCPlumbing403/22/2026
CESAR QUERYElectrical103/21/2026
NICHOLAS BLASONEElectrical103/21/2026
JOSE R TAVERASGeneral Contractor103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ADROIT ENGINEERING PLLC8885106/04/2024
Building Lifecycle
All (84)Filed (12)Permit Issued (4)Signed Off (1)Violation (22)Objection (15)Special Inspection (30)
08/04/2026
Permit issued — Construction Fence
X01157737-I1-FN
07/13/2026
Special inspection requirement — Subgrade Inspections
07/13/2026
Special inspection requirement — Lowest Floor Elevation
07/13/2026
Special inspection requirement — Concrete - Cast-In-Place
07/13/2026
Special inspection requirement — Sprayed fire-resistant materials
07/13/2026
Special inspection requirement — Concrete - Cast-In-Place
07/13/2026
Special inspection requirement — Structural Steel - Welding
07/13/2026
Special inspection requirement — Structural Steel - High Strength Bolting
07/13/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
07/13/2026
Special inspection requirement — Subsurface Conditions – Fill Placement & In-Place Density
07/13/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
07/02/2026
Objection raised — Other
07/02/2026
Objection raised — Other
06/11/2026
Objection raised — Other
06/11/2026
Objection raised — Other
06/04/2026
Filed — New Building
Construction of a New Building.
X01298990-S8
06/04/2026
Filed — New Building
Construction of a New Building.
X01298990-S7
06/01/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
06/01/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
06/01/2026
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
06/01/2026
Special inspection requirement — Fire-Resistance Rated Construction
06/01/2026
Special inspection requirement — Masonry
06/01/2026
Special inspection requirement — Mastic and Intumescent Fire-resistant Coatings
06/01/2026
Special inspection requirement — Sprayed fire-resistant materials
06/01/2026
Special inspection requirement — Energy Code Compliance Inspections
05/13/2026
Special inspection requirement — Lighting controls
05/13/2026
Special inspection requirement — Lighting in dwelling units
05/13/2026
Special inspection requirement — Protection of exposed foundation insulation
05/13/2026
Special inspection requirement — Electrical motors and elevators
05/13/2026
Special inspection requirement — Maintenance information
05/13/2026
Special inspection requirement — Exterior lighting power
05/13/2026
Special inspection requirement — Air barrier — testing
05/13/2026
Special inspection requirement — Interior lighting power
05/13/2026
Special inspection requirement — Metering
05/13/2026
Special inspection requirement — Air barrier continuity plan testing
05/13/2026
Special inspection requirement — Vestibules
05/12/2026
Filed — New Building
Construction of a New Building.
X01298990-S2
05/12/2026
Filed — New Building
Construction of a New Building.
X01298990-S3
05/12/2026
Special inspection requirement — Masonry
03/23/2026
Objection resolved — Resolved
01/29/2026
Objection raised — Admin
01/21/2026
Filed — New Building
Construction of a New Building.
X01298990-S1
01/21/2026
Objection raised — Other
01/21/2026
Objection raised — Other
01/12/2026
Objection resolved — Resolved
01/06/2026
Objection raised — Cost
01/06/2026
Objection raised — Fire_Protection
01/06/2026
Objection raised — Fire_Protection
12/30/2025
Objection raised — Other
12/19/2025
Filed — New Building
Construction of a New Building.
X01298990-S6
12/19/2025
Filed — Alteration
Temporary standpipe filed in conjunction with construction of a new building.
X01337032-I1
12/19/2025
Filed — New Building
Construction of a New Building.
X01298990-S4
12/18/2025
Signed off — Full Demolition
MECHANICAL MEANS SUBMITTED FOR USE OF MECHANICAL EQUIPMENT ON GRADE AT THE TIME OF DEMOLITION
X01005103-I1
11/21/2025
Filed — New Building
Construction of a New Building.
X01298990-I1
09/30/2025
Permit issued — Protection and Mechanical Methods
X01005103-S1-PMM
09/29/2025
Permit issued — Full Demolition
X01005103-I1-FD
08/06/2025
Permit issued — Construction Fence
X01157737-I1-FN
02/06/2025
Filed — Alteration
X01157737-I1
08/05/2024
Filed — Full Demolition
MECHANICAL MEANS SUBMITTED FOR USE OF MECHANICAL EQUIPMENT ON GRADE AT THE TIME OF DEMOLITION
X01005103-S1
08/02/2024
Objection resolved — Addressed
Latest 60 of 84 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FencePermit IssuedDM80 SOLUTIONS LLC08/04/2026
DOB NOWProtection and Mechanical MethodsSigned-offDM80 SOLUTIONS LLC09/30/2025
DOB NOWFull DemolitionSigned-offDM80 SOLUTIONS LLC09/29/2025
DOB NOWConstruction FencePermit IssuedDM80 SOLUTIONS LLC08/06/2025
BISPLISSUEDCAPE PLUMBING INC06/25/2019
BISPLISSUEDCAPE PLUMBING INC05/11/2018
BISOTISSUEDJOSE R TAVERAS04/05/2018
BISEQISSUEDROCKLEDGE SCAFFOLD CORP01/20/2004
BISFPISSUEDMASTER FIRE SYSTEMS, INC04/17/2003
BISOTISSUEDBERGER SIGN FABRICATION INC04/18/2002
BISPLISSUEDCAVALRY PLG & HTG CORP03/19/2001
BISPLISSUEDCAVALRY PLG & HTG CORP03/19/2001
BISPLISSUEDCAVALRY PLG & HTG CORP12/27/2000
BISFPISSUEDIDEAL FIRE CONTROL, INC04/14/2000
BISFPISSUEDIDEAL FIRE CONTROL INC04/04/2000
BIS—ISSUEDC/O NORTH END LIQUOR11/06/1998
BISPLISSUEDLUVER PLBG & HTG INC11/06/1998
BISOTISSUEDLUVER PLBG & HTG INC11/06/1998
BISSPISSUEDFULL CAPACITY FIRE CORP03/28/1997
BISPLISSUEDDANIEL WEINTRAUB10/10/1995
BISPLISSUEDA P PLUMBING&HEATING INC09/08/1992
BIS—ISSUEDN/A02/28/1992
BIS—ISSUEDN/A07/17/1991
1 project · most recent 12/19/2025
FiledStatusContractorScope
12/19/2025——1 outlets
1 project · most recent 12/19/2025
FiledStatusContractorScope
12/19/2025———
1 project · most recent 06/04/2026
FiledStatusContractorScope
06/04/2026——3 scope_items
▾Special Inspection Requirements (DOB NOW) — 52
DateRequirementInspectorRole
07/13/2026Subgrade Inspections—special
07/13/2026Lowest Floor Elevation—progress
07/13/2026Concrete - Cast-In-Place—special
07/13/2026Sprayed fire-resistant materials—special
07/13/2026Concrete - Cast-In-Place—special
07/13/2026Structural Steel - Welding—special
07/13/2026Structural Steel - High Strength Bolting—special
07/13/2026Subsurface Investigations (Borings/Test Pits)—special
07/13/2026Subsurface Conditions – Fill Placement & In-Place Density—special
07/13/2026Excavations - Sheeting, Shoring, and Bracing—special
06/01/2026Fire-Resistant Penetrations and Joints—special
06/01/2026Exterior Insulation and Finish Systems (EIFS)—special
06/01/2026Wall Panels, Curtain Walls, and Veneers—special
06/01/2026Fire-Resistance Rated Construction—progress
06/01/2026Masonry—special
06/01/2026Mastic and Intumescent Fire-resistant Coatings—special
06/01/2026Sprayed fire-resistant materials—special
06/01/2026Energy Code Compliance Inspections—progress
05/13/2026Lighting controls—energy_progress
05/13/2026Lighting in dwelling units—energy_progress
05/13/2026Protection of exposed foundation insulation—energy_progress
05/13/2026Electrical motors and elevators—energy_progress
05/13/2026Maintenance information—energy_progress
05/13/2026Exterior lighting power—energy_progress
05/13/2026Air barrier — testing —energy_progress
Latest 25 of 52.
▾Documents — 91 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch12
08/21/2026X01005103-S1Request digital key ↗
08/20/2026X01157737-I1Request digital key ↗
08/16/2026X01298990-I1Request digital key ↗
Showing 3 of 12 on file for this type
▸Applications & Permits7
▸BISPLAN / WORK APPROVAL APPLICATION5
06/24/2019220628328Open ↗
12/11/2017220628328Open ↗
03/11/2016220518795Open ↗
Showing 3 of 5 on file for this type
▸BISWORK PERMIT APPLICATION2
05/15/2018220628328Open ↗
04/05/2018220628328Open ↗
▸Zoning, Tax Lot & Property Records13
▸DOB NOWRestrictive Declaration/Easement 24
08/16/2026X01298990-S2Open ↗
08/16/2026X01298990-S1Open ↗
08/16/2026X01298990-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWRestrictive Declaration/Easement 14
08/16/2026X01298990-I1Open ↗
08/16/2026X01298990-S1Open ↗
08/16/2026X01298990-S3Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWZD1: DOB Zoning Diagram1
08/16/2026X01298990-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/16/2026X01298990-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/16/2026X01298990-I1Open ↗
▸DOB NOWRestrictive Declaration/Easement 31
08/16/2026X01298990-I1Open ↗
▸DOB NOWRestrictive Declaration/Easement 41
08/16/2026X01298990-I1Open ↗
▸Seals & Professional Certifications22
▸DOB NOWDPL-1: Design Professional Seal & Signature14
08/21/2026X01005103-S1Open ↗
08/21/2026X01005103-I1Open ↗
08/20/2026X01157737-I1Open ↗
Showing 3 of 14 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION4
12/11/2017220628328Open ↗
12/11/2017220628328Open ↗
03/11/2016220518795Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
09/02/2026X01005103-I1Open ↗
09/02/2026X01005103-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
12/11/2017220628328Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
12/11/2017220628328Open ↗
▸Trade Schedules & Equipment8
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE4
06/24/2019220628328Open ↗
12/11/2017220628328Open ↗
03/11/2016220518795Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWElectric Cut-Off1
08/13/2026X01005103-I1Open ↗
▸DOB NOWWater Cut-Off1
08/13/2026X01005103-I1Open ↗
▸DOB NOWGas Cut-Off1
08/13/2026X01005103-I1Open ↗
▸DOB NOWSewer Cut-Off1
08/13/2026X01005103-I1Open ↗
▸Safety & Tenant Protection1
▸BISST-1 Street Tree Checklist1
11/06/2014220362042Open ↗
▸Environmental & Asbestos6
▸BISASBESTOS-CERTIFICATION (DEP ACP5)3
11/06/2014220362042Open ↗
11/06/2014220362042Open ↗
12/11/2017220628328Open ↗
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED1
03/20/2018220628328Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/15/2026X01005103-I1Open ↗
▸DOB NOWRodent Control1
08/13/2026X01005103-I1Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
12/11/2017220628328Open ↗
12/11/2017220628328Open ↗
03/27/2014220362042Open ↗
▸Inspections & Test Reports2
▸DOB NOWTR4 Test Report and Plot Diagram1
08/16/2026X01298990-S2Open ↗
▸DOB NOWSOIL REPORT1
08/16/2026X01298990-S2Open ↗
▸Approvals, Objections & Sign-offs2
▸BISSCHEDULE A - OCCUPANCY - USE2
03/27/2014220362042Open ↗
03/27/2014220362042Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT4
08/20/2018220628328Open ↗
12/11/2017220628328Open ↗
03/11/2016220518795Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms4
▸BISEFILING COVER SHEET3
12/11/2017220628328Open ↗
03/11/2016220518795Open ↗
03/27/2014220362042Open ↗
▸BISADDITIONAL INFORMATION1
06/24/2019220628328Open ↗
▸Other Documents7
▸BIS* ENVIRONMENTAL 'E' DEP NOTICE TO PROCEED1
11/24/2014220362042Open ↗
▸DOB NOWCommunity Board Notification1
08/13/2026X01005103-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/15/2026X01005103-I1Open ↗
▸DOB NOWFull Demo: 10-Day Notice1
08/13/2026X01005103-I1Open ↗
▸DOB NOWStructure Photographs1
08/13/2026X01005103-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/16/2026X01298990-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/16/2026X01298990-I1Open ↗