| Owner | Filings | Most Recent |
|---|---|---|
| VICTOR GROUP NYC | 32 | 07/08/2026 |
| VHS 239 | 14 | 07/08/2026 |
| FLORIM SOLUTION INC. | 1 | 03/22/2026 |
| FIBERTRONICS | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ROSINI ENGINEERING, PC | 4 | 11/23/2023 |
| MG ENGINEERING D.P.C. | 10 | 10/12/2023 |
| FROM ARCHITECTURE DPC | 2 | 08/09/2023 |
| GENSLER | 2 | 07/06/2022 |
| JOSE L. PENA,P.E. | 3 | 02/09/2022 |
| FRENCH & PARRELLO ASSOCIATES | 3 | 10/06/2021 |
| UNIVERSAL BUILDERS SUPPLY, LLC | 2 | 06/15/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| LOUIS STRIAR | 6 | 03/21/2026 |
| DOMANI CONSULTING | 29 | 03/21/2026 |
| EUROCELT EXPEDITING, INC | 4 | 03/21/2026 |
| SKYLINE ACCESS | 1 | 03/21/2026 |
| PAR PLUMBING GROUP | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| 20/20 GENERAL CONTRACTING | General Contractor | 6 | 03/21/2026 |
| THOMAS FAY | Fire Protection | 5 | 03/21/2026 |
| SPK/LEWIS CONSTRUCTION LL | General Contractor | 4 | 03/21/2026 |
| LENDLEASE(US)CONSTRUCTION | General Contractor | 4 | 03/21/2026 |
| GOING SIGN SVCNG | Scaffold | 3 | 07/08/2026 |
| UNIVERSAL BUILD SUPP LLC | General Contractor | 2 | 07/08/2026 |
| METRO FIRE PROTECTION INC | Fire Protection | 2 | 07/08/2026 |
| VILLAGE P & H NY INC | Fire Protection | 1 | 07/08/2026 |
| ROBERT CHIMENTI | Electrical | 1 | 03/22/2026 |
| R-2 ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| JTE ELECTRICAL SERVICES | Electrical | 1 | 03/22/2026 |
| DPH PLUMBING & HTG CORP | Plumbing | 1 | 07/08/2026 |
| PARKVIEW P&H INC | Plumbing | 1 | 07/08/2026 |
| VILLAGE P & H NY INC | Plumbing | 1 | 07/08/2026 |
| ANTHONY FIGUCCIO | Electrical | 1 | 03/21/2026 |
| FULL CAPACITY FIRE CORP | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| DOMANI INSPECTION SERVICE | 843 | 17 | 11/23/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Suspended Scaffold | Permit Issued | SKYLINE RESTORATION INC | 02/20/2026 |
| DOB NOW | Sprinklers | Signed-off | METRO FIRE PROTECTION INC | 09/27/2023 |
| DOB NOW | Mechanical Systems | Signed-off | LENDLEASE(US)CONSTRUCTION | 09/21/2023 |
| DOB NOW | Sprinklers | Signed-off | METRO FIRE PROTECTION INC | 08/30/2023 |
| DOB NOW | Mechanical Systems | Signed-off | LENDLEASE(US)CONSTRUCTION | 08/03/2023 |
| DOB NOW | Plumbing | Signed-off | PARKVIEW P&H INC | 06/15/2023 |
| DOB NOW | Sprinklers | Signed-off | VILLAGE P & H NY INC | 06/05/2023 |
| DOB NOW | Plumbing | Signed-off | VILLAGE P & H NY INC | 06/05/2023 |
| DOB NOW | Mechanical Systems | Signed-off | 20/20 GENERAL CONTRACTING | 06/02/2023 |
| DOB NOW | General Construction | Signed-off | 20/20 GENERAL CONTRACTING | 05/02/2023 |
| DOB NOW | Sign | Signed-off | POLSINELLI, HENRY | 02/12/2022 |
| DOB NOW | Sign | Signed-off | POLSINELLI, HENRY | 02/12/2022 |
| DOB NOW | Sign | Signed-off | POLSINELLI, HENRY | 02/12/2022 |
| DOB NOW | Mechanical Systems | Signed-off | SPK/LEWIS CONSTRUCTION LL | 10/20/2021 |
| DOB NOW | Sprinklers | Signed-off | FULL CAPACITY FIRE CORP | 10/20/2021 |
| DOB NOW | Plumbing | Signed-off | DPH PLUMBING & HTG CORP | 10/19/2021 |
| DOB NOW | General Construction | Signed-off | SPK/LEWIS CONSTRUCTION LL | 10/06/2021 |
| DOB NOW | Supported Scaffold | Signed-off | UNIVERSAL BUILD SUPP LLC | 10/02/2018 |
| DOB NOW | Supported Scaffold | Signed-off | UNIVERSAL BUILD SUPP LLC | 06/18/2018 |
| BIS | — | ISSUED | LENDLEASE(US)CONSTRUCTION | 01/20/2023 |
| BIS | — | ISSUED | LENDLEASE(US)CONSTRUCTION | 09/30/2021 |
| BIS | — | ISSUED | LENDLEASE(US)CONSTRUCTION | 03/01/2021 |
| BIS | OT | ISSUED | TACONIC BUILDERS INC | 01/23/2020 |
| BIS | OT | ISSUED | TACONIC BUILDERS INC | 01/23/2020 |
| BIS | PL | ISSUED | PARKVIEW P&H INC | 01/22/2020 |
| BIS | OT | ISSUED | TACONIC BUILDERS INC | 05/30/2019 |
| BIS | PL | ISSUED | ARCON PLBG SOLUTIONS | 05/30/2019 |
| BIS | OT | ISSUED | TACONIC BUILDERS INC | 05/29/2019 |
| BIS | EQ | ISSUED | LENDLEASE(US)CONSTRUCTION | 05/01/2019 |
| BIS | PL | ISSUED | PARKVIEW P&H INC | 01/09/2019 |
| BIS | EQ | ISSUED | UNIVERSAL BUILD SUPP LLC | 12/04/2018 |
| BIS | EQ | ISSUED | UNIVERSAL BUILD SUPP LLC | 11/27/2018 |
| BIS | OT | ISSUED | LENDLEASE(US)CONSTRUCTION | 10/15/2018 |
| BIS | BL | ISSUED | PARKVIEW P&H INC | 10/04/2018 |
| BIS | SP | ISSUED | METRO FIRE PROTECTION INC | 09/28/2018 |
| BIS | — | ISSUED | LENDLEASE(US)CONSTRUCTION | 09/27/2018 |
| BIS | — | ISSUED | LENDLEASE(US)CONSTRUCTION | 08/17/2018 |
| BIS | EQ | ISSUED | W & W GLASS LLC | 07/10/2018 |
| BIS | SD | ISSUED | METRO FIRE PROTECTION INC | 06/18/2018 |
| BIS | SD | ISSUED | METRO FIRE PROTECTION INC | 06/18/2018 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/16/2026 | Permit Issued | XELA ELECTRICAL CORP | General Wiring |
| 05/24/2024 | Complete | S. J. ELECTRIC INC. | General Wiring |
| 02/22/2024 | Permit Issued | ROBERT CHIMENTI | 7 meters, 1 new_meters |
| 01/30/2024 | Complete | JTE ELECTRICAL SERVICES | 1 meters, 1 new_meters |
| 10/31/2022 | Complete | NYCOM ELECTRICAL CORP | — |
| 05/05/2022 | Complete | S. J. ELECTRIC INC. | General Wiring |
| 10/07/2021 | Complete | LIVE WIRE ELECTRIC 1 LLC | General Wiring |
| 04/16/2021 | Complete | APOLLO ELECTRIC NYG, INC | — |
| 08/07/2019 | Complete | R-2 ELECTRIC INC | General Wiring |
| 04/25/2018 | Complete | S. J. ELECTRIC INC. | General Wiring, Lighting |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| — | — | — | Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/26/2026 | Permit Issued | SKYLINE ACCESS LLC | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/07/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/07/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/19/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/18/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/11/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/05/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/05/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/04/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/03/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/28/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/28/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/28/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/15/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/02/2023 | No Access-Final PL - Up to 3 Requested Floors | No Access | View ↗ |
| 07/25/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/11/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 03/11/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/07/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/01/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/08/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/01/2023 | Sprinkler Systems | JOHN MCMONAGLE | special |
| 10/12/2023 | Final | JOHN MCMONAGLE | progress |
| 10/12/2023 | Mechanical Systems | JOHN MCMONAGLE | special |
| 10/11/2023 | Final | JOHN MCMONAGLE | progress |
| 10/11/2023 | Mechanical Systems | JOHN MCMONAGLE | special |
| 10/11/2023 | Mechanical Systems | JOHN MCMONAGLE | special |
| 10/11/2023 | Final | JOHN MCMONAGLE | progress |
| 08/18/2023 | Interior lighting power | JOHN MCMONAGLE | energy_progress |
| 08/18/2023 | Lighting controls | JOHN MCMONAGLE | energy_progress |
| 08/18/2023 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 08/18/2023 | Final | JOHN MCMONAGLE | progress |
| 08/18/2023 | Energy Code Compliance Inspections | JOHN MCMONAGLE | progress |
| 08/18/2023 | Sprayed fire-resistant materials | JOHN MCMONAGLE | special |
| 08/01/2023 | Sprayed fire-resistant materials | JOHN MCMONAGLE | special |
| 08/01/2023 | Energy Code Compliance Inspections | JOHN MCMONAGLE | progress |
| 08/01/2023 | Final | JOHN MCMONAGLE | progress |
| 08/01/2023 | Interior lighting power | JOHN MCMONAGLE | energy_progress |
| 08/01/2023 | Lighting controls | JOHN MCMONAGLE | energy_progress |
| 08/01/2023 | Sprinkler Systems | JOHN MCMONAGLE | special |
| 08/01/2023 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 02/22/2023 | Mechanical Systems | JOHN MCMONAGLE | special |
| 02/22/2023 | Final | JOHN MCMONAGLE | progress |
| 02/22/2023 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 02/22/2023 | Post-installed Anchors | JOHN MCMONAGLE | special |
| 07/06/2022 | Energy Code Compliance Inspections | JOHN MCMONAGLE | progress |