| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 11/15/2024 | Signed-off | BUILDERS GROUP USA INC | Heating and Air Conditioning Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/15/2024 | Signed-off | PRIME PIPING & HEATING IN | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/15/2024 | Signed-off | A M B MECHANICAL INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/04/2024 | Complete | FRIED ELECTRIC CO. | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| OWNER OF 2788 CLAFLIN AVE | 2 | 03/22/2026 |
| 2788 CLAFLIN LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/20/2023 | $1.2M | — | — → — | $442/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| PRAMODRAY SHAH, P.E. | 3 | 11/15/2024 |
| NOEL WONG, RA | 3 | 07/25/2024 |
| VASILIOS ARTEMIOU PE | 1 | 12/14/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| XPDITE GROUP LLC (104) | 7 | 03/21/2026 |
| XPDITE GROUP LLC 105 | 6 | 03/21/2026 |
| XPDITE GROUP LLC 104 | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BUILDERS GROUP USA INC | General Contractor | 2 | 07/08/2026 |
| FRIED ELECTRIC CO. | Electrical | 1 | 03/22/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 1 | 07/08/2026 |
| PRIME PIPING & HEATING IN | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 7 | 11/15/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | BUILDERS GROUP USA | 01/18/2024 |
| DOB NOW | General Construction | Permit Issued | BUILDERS GROUP USA | 12/29/2023 |
| DOB NOW | Sprinklers | Signed-off | A M B MECHANICAL INC | 12/26/2023 |
| DOB NOW | Plumbing | Signed-off | PRIME PIPING & HEATING IN | 12/26/2023 |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/09/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/01/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/25/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/07/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| 03/05/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/05/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 02/08/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/02/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/03/2024 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 12/03/2024 | Interior lighting power | FAHAD FATEH | energy_progress |
| 12/03/2024 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 12/03/2024 | Fenestration areas | FAHAD FATEH | energy_progress |
| 12/03/2024 | Permanent certificate | FAHAD FATEH | energy_progress |
| 12/03/2024 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 12/03/2024 | Metering | FAHAD FATEH | energy_progress |
| 12/03/2024 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 12/03/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 12/03/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 12/03/2024 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 12/03/2024 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 12/03/2024 | Maintenance information | FAHAD FATEH | energy_progress |
| 10/30/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 10/30/2024 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 10/30/2024 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 10/30/2024 | Maintenance information | FAHAD FATEH | energy_progress |
| 10/30/2024 | Fenestration areas | FAHAD FATEH | energy_progress |
| 10/30/2024 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 10/30/2024 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 10/30/2024 | Interior lighting power | FAHAD FATEH | energy_progress |
| 10/30/2024 | Metering | FAHAD FATEH | energy_progress |
| 10/30/2024 | Permanent certificate | FAHAD FATEH | energy_progress |
| 10/30/2024 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 10/30/2024 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |