← Back
Railroad, private ownership
28-27 30 STREET
QUEENS · BIN 4007688
💬 Discuss this project
0Year Built
—Stories
U6Building Class
C4-4AZoning
0 sfGross Floor Area
0Units
1 Open Violation ▸
Railroad, private ownership · Owner of record: VERIZON NEW YORK INC · 21,213 sf lot · 0 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalFire ProtectionGeneralOther
Permit Issued — active, not yet Signed-off
Roof8p · 3 filings · 17 docs
Floor 35p · 3 filings · 18 docs
Floor 26p · 3 filings · 18 docs
Floor 19p · 4 filings · 20 docs
CellarUnder Construction7p · 3 filings · 14 docs
Basement5p · 3 filings · 19 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
VERIZON3507/08/2026
ON-TRAC CONSTRUCTION ASSOCIATES707/08/2026
NY TELEPHONE CO103/22/2026
MANAGER OF CONSTRUCTION SERVICES403/21/2026
BELL ATLANTIC RM 802203/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JAM CONSULTANTS, INC.603/21/2026
PREEMPTIVE SOLUTIONS & CONSULTING L203/21/2026
ANGELA RIVERA203/21/2026
UNITED SAFETY CONSULTANTS403/21/2026
ARSENAL BUILDING CONSULTANTS LLC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SPRING SCAFFOLDING LLCGeneral Contractor1307/08/2026
TISHMAN INTERIORS CORPGeneral Contractor1107/08/2026
MASTER TECH PLUMBING LLCPlumbing307/08/2026
NEW YORK PLBG-HTG-COOL CFire Protection106/28/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
RLM ENGINEERING PLLC6913104/27/2026
CROSSCHECK INSPECTION SER544511/03/2022
STRACAR SPECIAL INSPECTIO229207/20/2020
Building Lifecycle
All (118)Filed (16)Permit Issued (24)Signed Off (10)Violation (32)Inspection (2)Objection (4)Special Inspection (30)
08/14/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/14/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
06/03/2026
Permit issued — Standpipe
Q01378840-I1-EW-SD
05/20/2026
Signed off — Alteration
Filing for mechanical modifications in a commercial space. No change of use, egress or occupancy.
Q00781694-I1
04/27/2026
Filed — Alteration
Replacing existing standpipe fire pump with new in the cellar as per plans filed herewith.
Q01378840-I1
04/07/2026
Signed off — Alteration
Q00882157-I1
03/26/2026
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
03/20/2026
Signed off — Alteration
Installation of sidewalk shed as indicated on the attcahed drawings. There are no changes in use, egreess or occupancy.
Q00829831-I1
03/17/2026
Signed off — Alteration
INSTALLATION OF TEMPORARY SYSTEM SCAFFOLD AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE SYSTEM SCAFFOLD STARTS FROM THE GROUND FLOOR OF THE FRONT BUILDING ON 30TH STREET.
Q01217562-S1
03/17/2026
Signed off — Alteration
INSTALLATION OF TEMPORARY SYSTEM SCAFFOLD AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE SYSTEM SCAFFOLD STARTS FROM THE GROUND FLOOR OF THE FRONT BUILDING ON 30TH STREET.
Q01217562-I1
03/10/2026
Permit issued — Protection and Mechanical Methods
Q00882157-I1-PMM
01/22/2026
Signed off — Alteration
Filing removal and replace of existing generators located within the cellar and roof and cellar switchgear with one new 750KW diesel generator and switchgear on the second floor and new battery room on the first floor and includes new partitions.
Q00778718-I1
11/14/2025
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/14/2025
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/24/2025
Signed off — Alteration
Structural modifications in a commercial building as per plans filed. No change in use, egress or occupancy.
Q00781552-I1
07/07/2025
Filed — Alteration
INSTALLATION OF TEMPORARY SYSTEM SCAFFOLD AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE SYSTEM SCAFFOLD STARTS FROM THE GROUND FLOOR OF THE FRONT BUILDING ON 30TH STREET.
Q01217562-S1
07/07/2025
Permit issued — Protection and Mechanical Methods
Q01217562-S1-PMM
05/01/2025
Permit issued — Supported Scaffold
Q01217562-I1-SF
04/29/2025
Filed — Alteration
INSTALLATION OF TEMPORARY SYSTEM SCAFFOLD AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE SYSTEM SCAFFOLD STARTS FROM THE GROUND FLOOR OF THE FRONT BUILDING ON 30TH STREET.
Q01217562-I1
04/17/2025
Permit issued — Mechanical Systems
Q00781694-I1-MS
04/17/2025
Permit issued — Structural
Q00781552-I1-ST
04/17/2025
Permit issued — General Construction
Q00778718-I1-GC
02/27/2025
Permit issued — Sidewalk Shed
Q00829831-I1-SH
02/26/2025
Permit issued — Protection and Mechanical Methods
Q00882157-I1-PMM
09/23/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/23/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/01/2024
Permit issued — Structural
Q00781552-I1-ST
05/01/2024
Permit issued — Mechanical Systems
Q00781694-I1-MS
05/01/2024
Permit issued — General Construction
Q00778718-I1-GC
02/15/2024
Permit issued — Sidewalk Shed
Q00829831-I1-SH
09/19/2023
Filed — Alteration
Installation of sidewalk shed as indicated on the attcahed drawings. There are no changes in use, egreess or occupancy.
Q00829831-P1
06/30/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/30/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/31/2023
Filed — Alteration
Q00882157-I1
05/31/2023
Permit issued — Protection and Mechanical Methods
Q00882157-I1-PMM
04/25/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/25/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/28/2023
Permit issued — Structural
Q00781552-I1-ST
02/15/2023
Filed — Alteration
Installation of sidewalk shed as indicated on the attcahed drawings. There are no changes in use, egreess or occupancy.
Q00829831-I1
02/15/2023
Permit issued — Mechanical Systems
Q00781694-I1-MS
02/15/2023
Permit issued — General Construction
Q00778718-I1-GC
02/15/2023
Permit issued — Sidewalk Shed
Q00829831-I1-SH
11/03/2022
Filed — Alteration
Filing for mechanical modifications in a commercial space. No change of use, egress or occupancy.
Q00781694-I1
11/03/2022
Filed — Alteration
Structural modifications in a commercial building as per plans filed. No change in use, egress or occupancy.
Q00781552-I1
11/02/2022
Filed — Alteration
Filing removal and replace of existing generators located within the cellar and roof and cellar switchgear with one new 750KW diesel generator and switchgear on the second floor and new battery room on the first floor and includes new partitions.
Q00778718-I1
10/05/2022
Special inspection requirement — Shutoff dampers
EUGENE BIFULCO
10/05/2022
Special inspection requirement — HVAC-R and service water heating system controls
EUGENE BIFULCO
10/05/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
EUGENE BIFULCO
10/05/2022
Special inspection requirement — HVAC-R and service water heating equipment
EUGENE BIFULCO
10/05/2022
Special inspection requirement — Maintenance information
EUGENE BIFULCO
09/27/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
EUGENE BIFULCO
09/27/2022
Special inspection requirement — Energy Code Compliance Inspections
EUGENE BIFULCO
07/28/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
EUGENE BIFULCO
07/28/2022
Special inspection requirement — Structural Steel - Details
EUGENE BIFULCO
07/28/2022
Special inspection requirement — Structural Steel - High Strength Bolting
EUGENE BIFULCO
07/28/2022
Special inspection requirement — Structural Steel - Welding
EUGENE BIFULCO
Latest 60 of 118 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStandpipePermit IssuedNEW YORK PLBG-HTG-COOL C06/03/2026
DOB NOWProtection and Mechanical MethodsSigned-offSPRING SCAFFOLDING LLC03/10/2026
DOB NOWProtection and Mechanical MethodsSigned-offSPRING SCAFFOLDING LLC07/07/2025
DOB NOWSupported ScaffoldSigned-offSPRING SCAFFOLDING LLC05/01/2025
DOB NOWMechanical SystemsSigned-offTISHMAN INTERIORS CORP04/17/2025
DOB NOWStructuralSigned-offTISHMAN INTERIORS CORP04/17/2025
DOB NOWGeneral ConstructionSigned-offTISHMAN INTERIORS CORP04/17/2025
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC02/27/2025
DOB NOWProtection and Mechanical MethodsSigned-offSPRING SCAFFOLDING LLC02/26/2025
DOB NOWStructuralSigned-offTISHMAN INTERIORS CORP05/01/2024
DOB NOWMechanical SystemsSigned-offTISHMAN INTERIORS CORP05/01/2024
DOB NOWGeneral ConstructionSigned-offTISHMAN INTERIORS CORP05/01/2024
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC02/15/2024
DOB NOWProtection and Mechanical MethodsSigned-offSPRING SCAFFOLDING LLC05/31/2023
DOB NOWStructuralSigned-offTISHMAN INTERIORS CORP03/28/2023
DOB NOWMechanical SystemsSigned-offTISHMAN INTERIORS CORP02/15/2023
DOB NOWGeneral ConstructionSigned-offTISHMAN INTERIORS CORP02/15/2023
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC02/15/2023
DOB NOWStructuralSigned-offTISHMAN INTERIORS CORP05/10/2021
DOB NOWSupported ScaffoldSigned-offSPRING SCAFFOLDING LLC03/22/2021
DOB NOWMechanical SystemsSigned-offTISHMAN INTERIORS CORP02/03/2021
DOB NOWPlumbingSigned-offMASTER TECH PLUMBING LLC12/22/2020
DOB NOWBoiler EquipmentSigned-offMASTER TECH PLUMBING LLC01/06/2020
DOB NOWPlumbingSigned-offMASTER TECH PLUMBING LLC11/21/2019
BISEQISSUEDTRI BOROUGH SCAFFOLDING06/22/2017
BISEQISSUEDTRI BOROUGH SCAFFOLDING06/20/2017
BISPLISSUEDTRADELINE PLUMBING INC12/31/2012
BISOTISSUEDSUGRUE CONTRACTING CORP09/28/2012
BISOTISSUEDSUGRUE CONTRACTING CORP09/28/2012
BISOTISSUEDSUGRUE CONTRACTING CORP04/16/2012
BISMHISSUEDSUGRUE CONTRACTING CORP04/16/2012
BISMHISSUEDTISHMAN CONSTRUCTION CORP01/02/2007
BISOTISSUEDVERIZON11/28/2006
BISMHISSUEDTISHMAN CONSTRUCTION CORP02/24/2006
BISMHISSUEDTISHMAN CONSTRUCTION CORP06/03/2003
BISOTISSUEDTISHMAN CONSTRUCTION CORP05/29/2003
BISMHISSUEDTISHMAN CONSTRUCTION CORP09/18/2002
BISMHISSUEDSUGRUE CONTRACTING CORP05/15/2002
BISPLISSUEDBROOK PLUMBING & HTG CORP03/14/2002
BISOTISSUEDTISHMAN CONSTRUCTION CORP02/21/2002
+ 13 more permits on file
1 project · most recent 11/03/2022
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
11/03/2022Signed-offTISHMAN INTERIORS CORPAir Conditioning Systems
Cooling
Climateworx PFU051 6,600 CFM · Wshp ×1
PS6FU03 1,500 CFM · Wshp ×1
PS6FU05 2,700 CFM · Wshp ×1
Goodman GUNTNER 46,658 CFM ×1
1 project · most recent 07/20/2020
Gas
FiledStatusContractorScope
07/20/2020Signed-offMASTER TECH PLUMBING LLCGas
4 projects · most recent 04/29/2025
General Wiring
FiledStatusContractorScope
04/29/2025CompletePINTO & TEGER ELEC. CORP.General Wiring
04/28/2025CompletePINTO AND TEGER ELECTRICGeneral Wiring
01/25/2023Permit IssuedTOP SHELF ELECTRIC CORP—
07/12/2021CompleteJAMES F. VOLPE ELEC'LGeneral Wiring
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
08/14/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/14/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 35
DateRequirementInspectorRole
10/05/2022Shutoff dampersEUGENE BIFULCOenergy_progress
10/05/2022HVAC-R and service water heating system controlsEUGENE BIFULCOenergy_progress
10/05/2022HVAC-R and service water piping design and insulationEUGENE BIFULCOenergy_progress
10/05/2022HVAC-R and service water heating equipmentEUGENE BIFULCOenergy_progress
10/05/2022Maintenance informationEUGENE BIFULCOenergy_progress
09/27/2022Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
09/27/2022Energy Code Compliance InspectionsEUGENE BIFULCOprogress
07/28/2022Structural Stability – Alterations of existing buildingsEUGENE BIFULCOspecial
07/28/2022Structural Steel - DetailsEUGENE BIFULCOspecial
07/28/2022Structural Steel - High Strength BoltingEUGENE BIFULCOspecial
07/28/2022Structural Steel - WeldingEUGENE BIFULCOspecial
07/28/2022PreliminaryEUGENE BIFULCOprogress
07/28/2022Concrete - Cast-In-PlaceEUGENE BIFULCOspecial
07/26/2022FinalEUGENE BIFULCOprogress
07/26/2022Mechanical SystemsEUGENE BIFULCOspecial
07/26/2022FinalEUGENE BIFULCOprogress
07/20/2022FinalEUGENE BIFULCOprogress
07/20/2022Fire-Resistance Rated ConstructionEUGENE BIFULCOprogress
07/20/2022Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
07/20/2022MasonryEUGENE BIFULCOspecial
11/23/2020HVAC insulation and sealing EUGENE BIFULCOenergy_progress
11/23/2020Energy Code Compliance InspectionsEUGENE BIFULCOprogress
11/23/2020Maintenance informationEUGENE BIFULCOenergy_progress
11/23/2020Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
11/23/2020HVAC and service water heating system controls EUGENE BIFULCOenergy_progress
Latest 25 of 35.
▾Documents — 169 on file (BIS + DOB NOW)
▸Plans & Drawings17
▸DOB NOWPlans/Sketch10
08/27/2026Q00478230-I1Request digital key ↗
08/25/2026Q00778718-I1Request digital key ↗
08/25/2026Q00781552-I1Request digital key ↗
Showing 3 of 10 on file for this type
▸DOB NOWPlans/Sketch - Plumbing2
08/28/2026Q00261684-I1Request digital key ↗
08/15/2026Q00261684-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Boiler Equipment2
08/28/2026Q00220663-I1Request digital key ↗
08/28/2026Q00220663-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural1
08/15/2026Q00468560-I1Request digital key ↗
▸DOB NOWPlans/Sketch - General Construction1
08/15/2026Q00468560-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
08/27/2026Q00425780-I1Request digital key ↗
▸Applications & Permits18
▸BISPLAN / WORK APPROVAL APPLICATION9
07/29/2019421734341Open ↗
06/21/2017440413269Open ↗
06/19/2017440413535Open ↗
Showing 3 of 9 on file for this type
▸BISWORK PERMIT APPLICATION9
08/28/2019421734341Open ↗
08/28/2019421734341Open ↗
06/21/2017440413269Open ↗
Showing 3 of 9 on file for this type
▸Seals & Professional Certifications63
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION17
08/28/2019421734341Open ↗
07/29/2019421734341Open ↗
06/20/2018440413269Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature16
08/28/2026Q00220663-P1Open ↗
08/28/2026Q00220663-I1Open ↗
08/28/2026Q00261684-I1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWProgress Inspector Seal & Signature15
09/28/2026Q00425780-I1Open ↗
09/28/2026Q00425780-I1Open ↗
09/28/2026Q00425780-I1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/28/2026Q00425780-I1Open ↗
09/28/2026Q00425780-I1Open ↗
09/23/2026Q00220663-I1Open ↗
Showing 3 of 7 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
05/19/2020421734341Open ↗
06/21/2017440413269Open ↗
06/19/2017440413535Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
06/21/2017440413269Open ↗
06/19/2017440413535Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
06/21/2017440413269Open ↗
06/19/2017440413535Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
07/29/2019421734341Open ↗
▸Trade Schedules & Equipment8
▸BISEQUIPMENT USE PERMITS2
06/24/2022421734341Open ↗
05/05/2022421734341Open ↗
▸BISSELF-CERT PLUMBING NOTICE2
06/10/2013420543228Open ↗
02/22/2013420543228Open ↗
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS1
04/18/2022421734341Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT1
05/05/2022421734341Open ↗
▸BISSCHEDULE B - PLUMBING1
03/13/2012420543228Open ↗
▸BISHVAC & SERVICE WATER HEATING EQUIPMENT1
04/18/2022421734341Open ↗
▸Environmental & Asbestos13
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form5
08/28/2026Q00220663-I1Open ↗
08/28/2026Q00261684-I1Open ↗
08/25/2026Q00781694-I1Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)4
07/29/2019421734341Open ↗
06/19/2017440413535Open ↗
06/12/2012420578654Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/27/2026Q00425780-I1Open ↗
08/17/2026Q01378840-I1Open ↗
08/13/2026Q00468560-I1Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
03/13/2012420543228Open ↗
▸Energy Compliance16
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
08/28/2019421734341Open ↗
08/28/2019421734341Open ↗
09/29/2014420543228Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWPreliminary Commissioning Report Certification3
08/25/2026Q00781694-I1Open ↗
08/13/2026Q00781694-I1Open ↗
08/13/2026Q00425780-I1Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
03/06/2013420543228Open ↗
▸BIS* DUCT LEAKAGE TESTING1
04/18/2022421734341Open ↗
▸BISTR8: Energy Code Progress Inspections1
04/16/2012420543228Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
06/21/2017440413269Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
04/18/2022421734341Open ↗
▸BIS* HVAC INSULATION AND SEALING1
04/18/2022421734341Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
04/18/2022421734341Open ↗
▸BISTECHNICAL REPORT: ENERGY1
04/17/2012420543228Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026Q00425780-I1Open ↗
▸Inspections & Test Reports8
▸BISTECHNICAL REPORT: RESPONSIBILITY2
06/21/2017440413269Open ↗
06/19/2017440413535Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
04/18/2022421734341Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
10/03/2012420578654Open ↗
▸BISSTRUCTURAL STEEL - HIGH STRENGTH BOLTING1
04/18/2022421734341Open ↗
▸BISMECHANICAL SYSTEMS1
04/18/2022421734341Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
10/03/2012420578654Open ↗
▸BISCONCRETE - CAST-IN-PLACE1
04/18/2022421734341Open ↗
▸Approvals, Objections & Sign-offs9
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
05/11/2022421734341Open ↗
05/06/2022421734341Open ↗
06/20/2018440413269Open ↗
Showing 3 of 5 on file for this type
▸BISADMINISTRATIVE OBJECTIONS2
06/12/2012420578654Open ↗
03/13/2012420543228Open ↗
▸BISFINAL1
04/18/2022421734341Open ↗
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter1
08/24/2026Q00882157-I1Open ↗
▸Cost, Insurance & Ownership6
▸BISCOST AFFIDAVIT5
07/29/2019421734341Open ↗
03/14/2013420543228Open ↗
06/12/2012420578654Open ↗
Showing 3 of 5 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
05/05/2022421734341Open ↗
▸Filing & Intake Forms10
▸BISEFILING COVER SHEET6
07/29/2019421734341Open ↗
06/12/2012420578654Open ↗
06/12/2012420578654Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET2
06/21/2017440413269Open ↗
06/19/2017440413535Open ↗
▸BISADDITIONAL INFORMATION2
09/17/2012420578654Open ↗
09/17/2012420578654Open ↗
▸Other Documents1
▸BISMAINTENANCE INFORMATION1
04/18/2022421734341Open ↗