← Back
Elevator cooperative
28 5 AVENUE
MANHATTAN · BIN 1009481
💬 Discuss this project
1923Year Built
15Stories
D4Building Class
R10Zoning
168,806 sfGross Floor Area
153Units
LL97 CoveredRent Stabilized21 Open Violations 20 unresolved · 1 paperwork only ▸FISP: SWARMP
Elevator cooperative · Owner of record: 30 FIFTH AVE OWNERS INC · 14,174 sf lot · 11.91 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalMechanicalPlumbingOther
Permit Issued — active, not yet Signed-off
Roof2p · 2 filings · 20 docs
Penthouse3p · 2 filings · 8 docs
Floor 173p · 1 filing · 20 docs
Floor 162p · 2 filings · 20 docs
Floor 152p · 2 filings · 20 docs
Floor 145p · 1 filing · 12 docs
Floor 13
Floor 12
Floor 11Under Construction6p · 2 filings · 20 docs
Floor 101p · 1 filing · 14 docs
Floor 9
Floor 8
Floor 71p · 2 filings · 20 docs
Floor 6
Floor 5
Floor 4
Floor 34p · 2 filings · 20 docs
Floor 2
Floor 1
Cellar1p · 1 filing · 16 docs
1 job · most recent 06/30/2021
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
06/30/2021Permit IssuedTHINK CONSTRUCTION LLCAir Conditioning Systems
Cooling
Task T25HXX 800 CFM · Ahu ×1
T31HXX 1,000 CFM · Ahu ×1
TGC021TWEC-25K-3620 25,300 BTU · Condensing Unit ×1
TGC021TWEC-29K-3620-RH 29,700 BTU · Condensing Unit ×1
4 jobs · most recent 06/03/2026
Gas Water/Sanitary
FiledStatusContractorScope
06/03/2026Permit IssuedA PLUS PLUMBING CORPGas, Water/Sanitary
05/21/2025Signed-offMETROTECH MECHANICAL CORPGas, Water/Sanitary
08/18/2021——Gas, Water/Sanitary
06/30/2021Signed-offDONATO PLUMBING, INCGas, Water/Sanitary
17 jobs · most recent 09/14/2026
General Wiring Lighting
FiledStatusContractorScope
09/14/2026CompleteENTERPRISE ELEC'L SYSTEMS—
07/28/2026Permit IssuedBIG CITY ELECL SOLUTIONSGeneral Wiring
06/19/2026Permit IssuedHIGH QUALITY ELEC.OF NYC—
05/21/2026Permit IssuedE & M ELECTRICAL NY CORPGeneral Wiring
11/03/2025CompleteEMELEC ELECTRIC CORPGeneral Wiring
09/05/2025CompleteMARTINEZ ELECTRICAL CONTGeneral Wiring
04/08/2025CompleteJTE ELECTRICAL SERVICESGeneral Wiring
04/15/2022CompleteLENS ELECTRIC, INCGeneral Wiring
02/25/2022CompleteINFINITY ELECTRIC, INCGeneral Wiring
12/16/2021CompleteCITI-WIDE ELECTRIC INCGeneral Wiring
08/18/2021Permit IssuedJOMEN ELECT. CONT'G CORPGeneral Wiring
11/16/2020Permit IssuedELPO ELECTRICAL CONTG INCGeneral Wiring
10/04/2019CompleteSUPER CHARGED ELEC. INC.—
10/04/2019CompleteSUPER CHARGED ELEC. INC.—
07/18/2018Permit IssuedACCURATE ELEC'L CORP.General Wiring
1 job · most recent 07/01/2026
Scaffold Sidewalk Shed
FiledStatusContractorScope
07/01/2026Permit IssuedA & H INSTALLATION INCScaffold, Sidewalk Shed
1 job · most recent 07/27/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
07/27/2026Permit IssuedHARROW CONSTRUCTION &Suspended Scaffold (SC)
Building Lifecycle
All (300)Filed (51)Permit Issued (37)Signed Off (20)Facade (FISP) (6)Violation (40)Inspection (38)Objection (78)Special Inspection (30)
08/10/2026
Objection resolved — Addressed
08/03/2026
Objection raised — Other
07/29/2026
Permit issued — General Construction
M01405715-I1-GC
07/27/2026
Filed — Alteration
SUSPENDED SCAFFOLD OUTRIGGER SYSTEM FOR EXTERIOR FACADE REPAIR WORK AT 30 5 AVENUE, MANHATTAN, NY 10011
M01406725-P1
07/27/2026
Permit issued — Plumbing
M01405715-S1-PL
07/02/2026
Permit issued — Sidewalk Shed
M01419510-I1-SH
07/02/2026
Permit issued — Sidewalk Shed
M01419510-I1-SF
07/01/2026
Filed — Alteration
INSTALLATION OF 300 PSF SIDEWALK SHED AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01419510-I1
07/01/2026
Filed — Alteration
COMBINATION OF (2) APARTMENTS ON TENTH FLOOR. REMOVAL OF EXISTING KITCHEN. MINOR ROOM LAYOUT MODIFICATIONS AND FINISH/LIGHTING UPGRADES. NO CHANGE OF USE, OCCUPACY, OR EGRESS.
M01412161-I1
06/26/2026
Special inspection requirement — Energy Code Compliance Inspections
David Katz
06/26/2026
Special inspection requirement — Lighting in dwelling units
David Katz
06/12/2026
Special inspection requirement — Final
David Katz
06/05/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
David Katz
06/04/2026
Permit issued — Suspended Scaffold
M01406725-I1-SC
06/03/2026
Filed — Alteration
Plumbing work related to interior renovation on Apt 11GHJ as per plans filed herewith.
M01405715-I1
06/03/2026
Filed — Alteration
Plumbing work related to interior renovation on Apt 11GHJ as per plans filed herewith.
M01405715-S1
05/27/2026
Filed — Alteration
Facade repairs as per plans filed herewith. No change to use, egress, or occupancy.
M01298581-I1
05/27/2026
Special inspection requirement — Fire-Resistance Rated Construction
Michael Schmitt
05/27/2026
Special inspection requirement — Lighting controls
Michael Schmitt
05/27/2026
Special inspection requirement — Lighting in dwelling units
Michael Schmitt
05/27/2026
Special inspection requirement — Post-installed Anchors
Joseph El-kallassy
05/22/2026
Filed — Alteration
SUSPENDED SCAFFOLD OUTRIGGER SYSTEM FOR EXTERIOR FACADE REPAIR WORK AT 30 5 AVENUE, MANHATTAN, NY 10011
M01406725-I1
05/21/2026
Special inspection requirement — Final
Michael Schmitt
04/13/2026
Signed off — Alteration
INTERIOR RENOVATION OF UNIT 5JK. NEW PARTITIONS, FIXTURES, AND FINISHES PER PLANS
M01199228-I1
03/17/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
02/10/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/12/2026
Permit issued — General Construction
M01199228-I1-GC
12/05/2025
Signed off — Alteration
PROPOSE PLUMBING WORK IN CONJUNCTION WITH ARCH. DESIGN. NO CHANGE IN USE, EGRESS, AND OCCUPANCY.
M01098870-I1
12/02/2025
Signed off — Alteration
PROPOSE PLUMBING WORK IN CONJUNCTION WITH ARCH. DESIGN. NO CHANGE IN USE, EGRESS, AND OCCUPANCY.
M01098870-S1
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/16/2025
Permit issued — General Construction
M01199228-I1-GC
10/07/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/01/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
09/29/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/19/2025
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
09/05/2025
Permit issued — General Construction
M01199228-I1-GC
08/15/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/08/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/07/2025
Violation issued (ECB, closed)
Boilers
08/07/2025
Violation issued (ECB, closed)
Boilers
06/25/2025
Signed off — Alteration
COMBINATION OF APARTMENTS 10H AND 10J ON 10TH FL AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY. COMBINATION COMPLY WITH TPPN 03/97.
M00965155-I1
06/20/2025
Permit issued — Plumbing
M01199228-S1-PL
06/06/2025
Signed off — Alteration
REMOVAL, MODIFICATION AND INSTALLTION OF PLUMBING AND GAS FIXTURES.
M01108265-I1
06/04/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
06/04/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/02/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Howard Spivak
05/23/2025
Permit issued — General Construction
M01199228-I1-GC
05/21/2025
Filed — Alteration
INTERIOR RENOVATION OF UNIT 5JK. NEW PARTITIONS, FIXTURES, AND FINISHES PER PLANS
M01199228-S1
05/19/2025
Signed off — Alteration
M01108241-I1
05/19/2025
Filed — Alteration
REMOVAL, MODIFICATION AND INSTALLTION OF PLUMBING AND GAS FIXTURES.
M01108265-P1
05/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Howard Spivak
05/06/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/01/2025
Filed — Alteration
INTERIOR RENOVATION OF UNIT 5JK. NEW PARTITIONS, FIXTURES, AND FINISHES PER PLANS
M01199228-I1
05/01/2025
Special inspection requirement — Interior lighting power
Matthew Rauch
05/01/2025
Special inspection requirement — Lighting in dwelling units
Matthew Rauch
05/01/2025
Special inspection requirement — Lighting controls
Matthew Rauch
05/01/2025
Special inspection requirement — Post-installed Anchors
Matthew Rauch
05/01/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Matthew Rauch
05/01/2025
Special inspection requirement — Final
Matthew Rauch
Latest 60 of 300 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
TERRIS REALTY3807/08/2026
HARROW CONSTRUCTION MANAGEMENT SE106/23/2026
30 FIFTH AVENUE OWNERS9803/22/2026
30 5TH AVENUE OWNERS803/22/2026
EQUITY MANAGEMENT GROUP103/22/2026
CONTRACTOR: BRUNI CONS203/22/2026
CS CLEAR STONE CONSTRUCTION103/22/2026
GREEN103/21/2026
ROCK GROUP NY203/21/2026
30 FIFTH AVENUE1603/21/2026
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DJM NYC, LLCGeneral Contractor707/08/2026
ORCHARD CONSTRUCTION GROUPGeneral Contractor607/08/2026
BALOG CONSTRUCTION LLCGeneral Contractor403/21/2026
THINK CONSTRUCTION LLCGeneral Contractor403/21/2026
SWE DEVELOPMENT CORPGeneral Contractor303/21/2026
A&G DESIGN CORPORATIONGeneral Contractor303/21/2026
MCCREADY & RICE PLUMB.,INGeneral Contractor307/08/2026
A & H INSTALLATION INCGeneral Contractor207/04/2026
CHARLES MCGRATH CONST INCGeneral Contractor203/21/2026
JEROME KRITZElectrical203/21/2026
SUPER CHARGED ELEC. INC.Electrical203/22/2026
KLE CONSTRUCTION INCGeneral Contractor107/08/2026
MCK CONTRACTING INCGeneral Contractor107/08/2026
TRIESTE CONSTRUCTION CORPGeneral Contractor107/30/2026
A PLUS PLUMBING CORPPlumbing107/28/2026
ARCON PLBG SOLUTIONSPlumbing107/08/2026
BRANCH PLUMBING LLCPlumbing107/08/2026
EVERYDAY MECHANICAL CORPPlumbing107/08/2026
HUDSON PLMBING & MCH, LLCPlumbing107/08/2026
MC CREADY & RICE PLBG INC.Plumbing107/08/2026
METROTECH MECHANICAL CORPPlumbing107/08/2026
M & M PIPING AND HEATINGPlumbing107/08/2026
NICE PLUMBING CORPPlumbing107/08/2026
P.S.I. MECHANICALPlumbing107/08/2026
RAPTOR MECHANICAL,INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
KATZ ARCHITECTURE1371207/01/2026
KALLASSY ENGINEERING PLLC5711106/03/2026
COWLEY ENGINEERING186205/27/2026
RAUCH ARCHITECTURE D.P.C.7888205/21/2025
SPIVAK ARCHITECTS PC6957205/19/2025
METRIC CONSULTING AND INS1803109/25/2024
SE INSPECTIONS7486109/25/2024
RICHARD H. BALSER ENGINEE3028208/19/2024
SU ARCHITECT PC6857307/26/2024
MESZAROS ENGINEERING PLLC963804/08/2024
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedTRIESTE CONSTRUCTION CORP07/29/2026
DOB NOWPlumbingPermit IssuedA PLUS PLUMBING CORP07/27/2026
DOB NOWSidewalk ShedPermit IssuedA & H INSTALLATION INC07/02/2026
DOB NOWSidewalk ShedPermit IssuedA & H INSTALLATION INC07/02/2026
DOB NOWSuspended ScaffoldPermit IssuedHARROW CONSTRUCTION &06/04/2026
DOB NOWGeneral ConstructionSigned-offORCHARD CONSTRUCTION GROU01/12/2026
DOB NOWGeneral ConstructionSigned-offORCHARD CONSTRUCTION GROU10/16/2025
DOB NOWGeneral ConstructionSigned-offORCHARD CONSTRUCTION GROU09/05/2025
DOB NOWPlumbingSigned-offMETROTECH MECHANICAL CORP06/20/2025
DOB NOWGeneral ConstructionSigned-offORCHARD CONSTRUCTION GROU05/23/2025
DOB NOWPlumbingSigned-offHUDSON PLMBING & MCH, LLC02/12/2025
DOB NOWGeneral ConstructionSigned-offSWE DEVELOPMENT CORP11/26/2024
DOB NOWGeneral ConstructionSigned-offDSC CONSTRUCTION YME LLC11/04/2024
DOB NOWPlumbingSigned-offSAMUEL & SONS P & H INC10/30/2024
DOB NOWGeneral ConstructionSigned-offMCCREADY & RICE PLUMB.,IN07/18/2024
DOB NOWPlumbingSigned-offM & M PIPING AND HEATING06/21/2024
DOB NOWGeneral ConstructionSigned-offKLE CONSTRUCTION INC06/07/2024
DOB NOWGeneral ConstructionSigned-offCHARLES MCGRATH CONST INC01/11/2024
DOB NOWGeneral ConstructionPermit IssuedCENTRAL CONSTRUCTION MANAGEMENT10/30/2023
DOB NOWPlumbingSigned-offMC CREADY & RICE PLBG INC07/18/2023
DOB NOWGeneral ConstructionSigned-offMCCREADY & RICE PLUMB.,IN07/18/2023
DOB NOWPlumbingSigned-offRAPTOR MECHANICAL, INC02/16/2023
DOB NOWGeneral ConstructionSigned-offMCK CONTRACTING INC02/09/2023
DOB NOWPlumbingSigned-offNICE PLUMBING CORP12/20/2022
DOB NOWGeneral ConstructionSigned-offBALOG CONSTRUCTION12/20/2022
DOB NOWMechanical SystemsSigned-offBALOG CONSTRUCTION12/20/2022
DOB NOWPlumbingSigned-offP.S.I. MECHANICAL04/20/2022
DOB NOWMechanical SystemsSigned-offA&G DESIGN CORPORATION04/12/2022
DOB NOWPlumbingSigned-offEVERYDAY MECHANICAL CORP12/16/2021
DOB NOWGeneral ConstructionSigned-offHESCO CONSTRUCTION CORP12/08/2021
DOB NOWMechanical SystemsPermit IssuedTHINK CONSTRUCTION LLC10/25/2021
DOB NOWMechanical SystemsPermit IssuedTHINK CONSTRUCTION LLC06/15/2021
DOB NOWPlumbingSigned-offARCON PLBG SOLUTIONS04/20/2021
DOB NOWPlumbingSigned-offBRANCH PLUMBING LLC11/12/2020
DOB NOWSupported ScaffoldSigned-offDJM NYC, LLC08/19/2020
DOB NOWSupported ScaffoldSigned-offDJM NYC, LLC02/20/2020
DOB NOWSupported ScaffoldSigned-offDJM NYC, LLC12/16/2019
BISOTISSUEDTHINK CONSTRUCTION LLC10/25/2021
BISPLISSUEDCHAMP PLUMBING & HTG CORP08/02/2021
BISOTISSUEDTHINK CONSTRUCTION LLC02/22/2021
+ 47 more permits on file
▾Field Inspections (DOB CAP) — 38
DateTypeResultReport
03/17/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/10/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/07/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/01/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/29/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/19/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
08/15/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/08/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/04/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/04/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/06/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/28/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/23/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
01/23/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/23/2024Pass-Final General Construction Non-Directive 14PassView ↗
07/22/2024Fail-Final General Construction Non-Directive 14FailView ↗
07/12/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
07/09/2024Fail-Final General Construction Non-Directive 14FailView ↗
07/01/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/28/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/25/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
05/09/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
03/29/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
03/01/2024Fail-Final PL - Up to 9 Requested FloorsFailView ↗
01/09/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
Latest 25 of 38.
▾Special Inspection Requirements (DOB NOW) — 110
DateRequirementInspectorRole
06/26/2026Lighting in dwelling unitsDavid Katzenergy_progress
06/26/2026Energy Code Compliance InspectionsDavid Katzprogress
06/12/2026FinalDavid Katzprogress
06/05/2026Fire-Resistant Penetrations and JointsDavid Katzspecial
05/27/2026Post-installed AnchorsJoseph El-kallassyspecial
05/27/2026Lighting in dwelling unitsMichael Schmittenergy_progress
05/27/2026Lighting controlsMichael Schmittenergy_progress
05/27/2026Fire-Resistance Rated ConstructionMichael Schmittprogress
05/21/2026FinalMichael Schmittprogress
06/02/2025Fire-Resistant Penetrations and JointsHoward Spivakspecial
05/08/2025Fire-Resistant Penetrations and JointsHoward Spivakspecial
05/01/2025Fire-Resistant Penetrations and JointsMatthew Rauchspecial
05/01/2025Interior lighting powerMatthew Rauchenergy_progress
05/01/2025Lighting controlsMatthew Rauchenergy_progress
05/01/2025Lighting in dwelling unitsMatthew Rauchenergy_progress
05/01/2025Post-installed AnchorsMatthew Rauchspecial
05/01/2025FinalMatthew Rauchprogress
05/01/2025Tenant Protection Plan ComplianceMatthew Rauchspecial
08/29/2024Post-installed AnchorsBalser Richardspecial
08/29/2024FinalDAVID CHAGNONprogress
08/29/2024Fire-Resistant Penetrations and JointsBalser Richardspecial
08/21/2024Fire-Resistant Penetrations and JointsSpencer Goroffspecial
08/21/2024Interior lighting powerSpencer Goroffenergy_progress
08/21/2024Structural Stability – Alterations of existing buildingsSpencer Goroffspecial
08/21/2024Energy Code Compliance InspectionsSpencer Goroffprogress
Latest 25 of 110.
▾Documents — 1,007 on file (BIS + DOB NOW)
▸Plans & Drawings51
▸DOB NOWPlans/Sketch47
09/03/2026M00517337-I1Request digital key ↗
09/03/2026M00466692-S1Request digital key ↗
09/03/2026M00603600-P1Request digital key ↗
Showing 3 of 47 on file for this type
▸DOB NOWPlans/Sketch - Plumbing3
09/03/2026M00422861-I1Request digital key ↗
09/03/2026M00422861-P1Request digital key ↗
09/03/2026M00466692-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold1
09/05/2026M00282382-I1Request digital key ↗
▸Applications & Permits225
▸BISWORK PERMIT APPLICATION93
04/04/2022122953624Open ↗
03/30/2022122953624Open ↗
02/22/2021140994994Open ↗
Showing 3 of 93 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION79
05/15/2024120810747Open ↗
03/11/2024100374845Open ↗
03/11/2024103335847Open ↗
Showing 3 of 79 on file for this type
▸DOB NOWLPC Approval/Permit47
09/03/2026M00422861-P1Open ↗
09/03/2026M00422861-I1Open ↗
09/03/2026M00603600-P1Open ↗
Showing 3 of 47 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION2
02/22/2021140994994Open ↗
02/22/2021140994994Open ↗
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications230
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION72
12/12/2019140864107Open ↗
12/12/2019140864107Open ↗
11/04/2019122945028Open ↗
Showing 3 of 72 on file for this type
▸DOB NOWProgress Inspector Seal & Signature54
09/29/2026M00875073-I1Open ↗
09/01/2026M00875073-P4Open ↗
09/01/2026M00422861-I1Open ↗
Showing 3 of 54 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature49
09/03/2026M00422861-P1Open ↗
09/03/2026M00422861-I1Open ↗
09/03/2026M00466692-I1Open ↗
Showing 3 of 49 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature32
09/29/2026M00875073-I1Open ↗
09/01/2026M00875073-P4Open ↗
09/01/2026M00668469-P5Open ↗
Showing 3 of 32 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
10/02/2019140864107Open ↗
Showing 1 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
09/15/2020140941701Open ↗
10/02/2019140864107Open ↗
Showing 2 of 3 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
10/02/2019140864107Open ↗
Showing 1 of 2 on file for this type
▸BISProfessional and Owner Certification (POC3)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISAPPLICANT OWNER SIGNATURE2
02/10/2021140994994Open ↗
09/15/2020140941701Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Trade Schedules & Equipment59
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE22
09/10/2019122945028Open ↗
03/02/2018123357928Open ↗
Showing 2 of 22 on file for this type
▸BISSCHEDULE B - PLUMBING19
04/28/2022122953624Open ↗
09/10/2021123168473Open ↗
Showing 2 of 19 on file for this type
▸BISSELF-CERT PLUMBING NOTICE13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Safety & Tenant Protection30
▸BISTenant Protection Plan and Notes16
03/20/2018123357928Open ↗
09/15/2020140941701Open ↗
10/02/2019140864107Open ↗
Showing 3 of 16 on file for this type
▸BISSRO MD ANTI-HARASSMENT CHECKLIST10
09/15/2020140941701Open ↗
10/02/2019140864107Open ↗
Showing 2 of 10 on file for this type
▸DOB NOWTenant Protection Plan3
09/03/2026M00422861-I1Open ↗
09/03/2026M00422861-P1Open ↗
Showing 2 of 3 on file for this type
▸BISTPP1: TENANT PROTECTION PLAN1
06/23/2021140994994Open ↗
▸Environmental & Asbestos74
▸DOB NOWDEP ACP-5: Asbestos Assessment Report44
09/03/2026M00422861-P1Open ↗
09/03/2026M00422861-I1Open ↗
09/03/2026M00466692-I1Open ↗
Showing 3 of 44 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)19
02/10/2021140994994Open ↗
09/15/2020140941701Open ↗
10/02/2019140864107Open ↗
Showing 3 of 19 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance41
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS21
10/21/2019122945028Open ↗
Showing 1 of 21 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS12
05/21/2024120810747Open ↗
11/04/2019122945028Open ↗
10/21/2019122945028Open ↗
Showing 3 of 12 on file for this type
▸BISNYCECC EXEMPTION2
02/10/2021140994994Open ↗
10/02/2019140864107Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
05/21/2024120810747Open ↗
09/15/2020140941701Open ↗
▸DOB NOWEN2: As Built Energy Analysis.2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTR8: Energy Code Progress Inspections1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports16
▸BISTECHNICAL REPORT: RESPONSIBILITY15
05/21/2024120810747Open ↗
03/11/2024103335847Open ↗
03/11/2024100374845Open ↗
Showing 3 of 15 on file for this type
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
05/11/2022140698234Open ↗
▸Approvals, Objections & Sign-offs106
▸BISLANDMARKS APPROVAL32
02/10/2021140994994Open ↗
09/30/2020140941701Open ↗
12/12/2019140864107Open ↗
Showing 3 of 32 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST29
05/23/2024120810747Open ↗
03/11/2024103335847Open ↗
03/11/2024100374845Open ↗
Showing 3 of 29 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION17
03/30/2022122953624Open ↗
11/04/2019122945028Open ↗
10/21/2019122945028Open ↗
Showing 3 of 17 on file for this type
▸BISADMINISTRATIVE OBJECTIONS10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISSUPERSEDING LETTER6
04/04/2022122953624Open ↗
03/30/2022122953624Open ↗
07/24/2020122953624Open ↗
Showing 3 of 6 on file for this type
▸BISSHED LETTER5
09/09/2020140698234Open ↗
09/09/2020140698234Open ↗
08/22/2019140698234Open ↗
Showing 3 of 5 on file for this type
▸BISLANDMARKS SIGNOFF4
05/23/2024120810747Open ↗
06/21/2022122953624Open ↗
05/18/2022140698234Open ↗
Showing 3 of 4 on file for this type
▸BISFINAL2
06/16/2022122953624Open ↗
06/03/2022140698234Open ↗
▸BISCCD1-Construction Code Determination1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership68
▸BISCOST AFFIDAVIT61
05/21/2024120810747Open ↗
02/10/2021140994994Open ↗
09/15/2020140941701Open ↗
Showing 3 of 61 on file for this type
▸BISHIC LICENSE OR AFFIDAVIT5
10/02/2019140864107Open ↗
Showing 1 of 5 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
06/21/2022122953624Open ↗
10/30/2021140941701Open ↗
▸Filing & Intake Forms87
▸BISADDITIONAL INFORMATION31
06/07/2022122953624Open ↗
02/15/2022122953624Open ↗
11/10/2021122953624Open ↗
Showing 3 of 31 on file for this type
▸BISEFILING COVER SHEET29
03/02/2018123357928Open ↗
Showing 1 of 29 on file for this type
▸BISBOROUGH INTAKE FORM18
04/04/2022122953624Open ↗
07/24/2020122953624Open ↗
02/28/2020123091108Open ↗
Showing 3 of 18 on file for this type
▸BISHPD-3 - SRO MD ANTI-HARASSEMENT CHECKLIST5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET4
02/10/2021140994994Open ↗
09/15/2020140941701Open ↗
10/02/2019140864107Open ↗
Showing 3 of 4 on file for this type
▸Other Documents20
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION6
08/22/2019140698234Open ↗
Showing 1 of 6 on file for this type
▸DOB NOWProof of Historic Building5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION2
03/11/2024103335847Open ↗
03/11/2024103335847Open ↗
▸DOB NOWManufacturer's Specifications2
08/17/2026M01406725-I1Open ↗
Showing 1 of 2 on file for this type
▸DOB NOWCalculations2
08/17/2026M01406725-I1Open ↗
Showing 1 of 2 on file for this type
▸BISSupporting Document: Fee Deferment1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSupporting Document: Fee Exempt1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISDepartment of Consumer Affairs (DCA) Form1
10/17/2018123343505Open ↗