RoofUnder Construction139p · 2 filings · 20 docs
ArchitectureDMElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction
Structural work to be conducted to install cfs walls, cfs joists, masonry walls, and 3/4 dragonboard.
On file for this job
64 documents · 4 drawing sheets
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 102 drawing sheets
Bulkhead16p · 1 filing · 3 docs
ArchitectureMechanicalPlumbingStructural
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 16 drawing sheets
PenthouseUnder Construction57p · 2 filings · 20 docs
ArchitectureFire ProtectionPlumbingStructural
Issued Permit Scope
General Construction · Structural
Structural work to be conducted to install cfs walls, cfs joists, masonry walls, and 3/4 dragonboard.
On file for this job
64 documents · 3 drawing sheets
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 3 drawing sheets
Floor 811p · 1 filing · 3 docs
Fire Protection
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 80
Floor 79
Floor 78
Floor 77
Floor 76
Floor 75
Floor 74
Floor 73
Floor 72
Floor 71
Floor 70
Floor 69
Floor 681p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 671p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 661p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 651p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 641p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 631p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 621p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 611p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 601p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 591p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 581p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 571p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 561p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 551p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 541p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 531p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 521p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 511p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 501p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 491p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 483p · 1 filing · 3 docs
Fire ProtectionPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 3 drawing sheets
Floor 471p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 461p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 451p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 441p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 431p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 421p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 411p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 401p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 393p · 1 filing · 3 docs
DMPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 3 drawing sheets
Floor 381p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 373p · 1 filing · 3 docs
MechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 3 drawing sheets
Floor 364p · 1 filing · 3 docs
MechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 4 drawing sheets
Floor 351p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 341p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 331p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 321p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 311p · 1 filing · 3 docs
Plumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 1 drawing sheet
Floor 302p · 1 filing · 3 docs
MechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 2 drawing sheets
Floor 293p · 1 filing · 3 docs
Fire ProtectionMechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 3 drawing sheets
Floor 283p · 1 filing · 3 docs
ArchitectureMechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 3 drawing sheets
Floor 273p · 1 filing · 3 docs
ArchitectureMechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 3 drawing sheets
Floor 264p · 1 filing · 3 docs
ArchitectureMechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 4 drawing sheets
Floor 254p · 1 filing · 3 docs
ArchitectureMechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 4 drawing sheets
Floor 244p · 1 filing · 3 docs
ArchitectureMechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 4 drawing sheets
Floor 235p · 1 filing · 3 docs
ArchitectureMechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 5 drawing sheets
Floor 223p · 1 filing · 3 docs
ArchitectureMechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 3 drawing sheets
Floor 213p · 1 filing · 3 docs
ArchitecturePlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 3 drawing sheets
Floor 203p · 1 filing · 3 docs
ArchitecturePlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 3 drawing sheets
Floor 194p · 1 filing · 3 docs
ArchitecturePlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 4 drawing sheets
Floor 185p · 1 filing · 3 docs
ArchitectureGeneralPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 5 drawing sheets
Floor 177p · 1 filing · 3 docs
ArchitectureGeneralMechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 7 drawing sheets
Floor 164p · 1 filing · 3 docs
ArchitectureMechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 4 drawing sheets
Floor 155p · 1 filing · 3 docs
ArchitectureMechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 5 drawing sheets
Floor 144p · 1 filing · 3 docs
ArchitectureFire ProtectionMechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 4 drawing sheets
Floor 134p · 1 filing · 3 docs
ArchitectureMechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 4 drawing sheets
Floor 125p · 1 filing · 3 docs
ArchitectureMechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 5 drawing sheets
Floor 114p · 1 filing · 3 docs
ArchitectureMechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 4 drawing sheets
Floor 106p · 1 filing · 3 docs
ArchitectureFire ProtectionMechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 6 drawing sheets
Floor 96p · 1 filing · 3 docs
ArchitectureEquipmentMechanicalPlumbing
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 6 drawing sheets
Floor 811p · 1 filing · 3 docs
ArchitectureEquipmentFire ProtectionMechanicalPlumbingStructural
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 11 drawing sheets
Floor 712p · 1 filing · 3 docs
ArchitectureEquipmentFire ProtectionMechanicalPlumbingStructural
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 12 drawing sheets
Floor 618p · 1 filing · 3 docs
ArchitectureEquipmentFire ProtectionMechanicalPlumbingStructural
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 18 drawing sheets
Floor 520p · 1 filing · 3 docs
ArchitectureDMEquipmentFire ProtectionMechanicalPlumbingStructural
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 20 drawing sheets
Floor 4Under Construction57p · 2 filings · 20 docs
ArchitectureDMEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction
Structural work to be conducted to install cfs walls, cfs joists, masonry walls, and 3/4 dragonboard.
On file for this job
64 documents · 1 drawing sheet
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 22 drawing sheets
Floor 3Under Construction90p · 2 filings · 20 docs
ArchitectureDMEquipmentFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Structural
Structural work to be conducted to install cfs walls, cfs joists, masonry walls, and 3/4 dragonboard.
On file for this job
64 documents · 3 drawing sheets
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 36 drawing sheets
Floor 2Under Construction113p · 2 filings · 20 docs
ArchitectureCivilDMElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Structural
Structural work to be conducted to install cfs walls, cfs joists, masonry walls, and 3/4 dragonboard.
On file for this job
64 documents · 1 drawing sheet
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 62 drawing sheets
Floor 1Under Construction123p · 2 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Structural
Structural work to be conducted to install cfs walls, cfs joists, masonry walls, and 3/4 dragonboard.
On file for this job
64 documents · 2 drawing sheets
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 71 drawing sheets
Mezzanine12p · 1 filing · 3 docs
ArchitectureGeneralPlumbingStructural
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 12 drawing sheets
CellarUnder Construction156p · 2 filings · 20 docs
ArchitectureDMElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Foundation · General Construction · Support of Excavation
Structural work to be conducted to install cfs walls, cfs joists, masonry walls, and 3/4 dragonboard.
On file for this job
64 documents · 4 drawing sheets
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 101 drawing sheets
Sub-Cellar4p · 1 filing · 3 docs
ArchitectureGeneralPlumbingStructural
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 4 drawing sheets
BasementUnder Construction46p · 2 filings · 20 docs
ArchitectureDMGeneralMechanicalPlumbingStructural
Issued Permit Scope
Structural
Structural work to be conducted to install cfs walls, cfs joists, masonry walls, and 3/4 dragonboard.
On file for this job
64 documents · 2 drawing sheets
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS FOR REMEDIAL REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2014 BUILDING CODE.
On file for this job
3 documents · 24 drawing sheets