1954Year Built
22Stories
D1Building Class
R6Zoning
483,384 sfGross Floor Area
475Units
LL97 Covered5 Open Violations ▸FISP: UNSAFEFDNY Report ↗
Elevator apt, semi-fireproof without stores · Owner of record: NYC HOUSING AUTHORITY · 238,734 sf lot · 2.02 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbing
Roof9p · 2 filings · 20 docs
Bulkhead6p · 1 filing · 18 docs
Floor 11p · 1 filing · 7 docs
Cellar1p · 1 filing · 7 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYCHA3007/19/2026
NEW YORK CITY HOUSING AUTHORITY2407/08/2026
NYC HOUSING AUTHORITY1203/22/2026
NYCHA 99503/22/2026
NYCHA 5 FLOOR 99203/22/2026
NYC HOUSING AUTHORITY 9103/22/2026
NYC HOUSING AUTH103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CONVERSANO ASSOCIATES, INC.1203/21/2026
AK CONSULTING SERVICES603/21/2026
JOEL PHAGOO P.E. PLLC103/21/2026
AE DESIGN SOLUTION203/21/2026
JOEL PHAGOO P E103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MNK ENTERPRISES LLCGeneral Contractor1307/19/2026
ZORIA HOUSING, LLCGeneral Contractor507/08/2026
CRAIG GILSTONElectrical103/21/2026
RICHARDS P AND H CO, INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SOCOTEC ENGINEERING4983406/10/2025
LEO Y LEE ASSOCIATES2481110/08/2024
JOEL PHAGOO ,PE, PLLC2416102/29/2024
RLM ENGINEERING PLLC6913109/28/2023
Building Lifecycle
All (89)Filed (15)Permit Issued (15)Signed Off (5)Facade (FISP) (17)Violation (30)Inspection (1)Objection (6)
07/17/2026
Permit issued — Sidewalk Shed
B01171337-I1-SH
06/04/2026
Permit issued — Sidewalk Shed
B01171337-I1-SH
03/04/2026
Permit issued — Construction Fence
B01171343-I1-FN
03/02/2026
Permit issued — Sidewalk Shed
B01171337-I1-SH
12/02/2025
Signed off — Alteration
ROOFING REPLACEMENT AND ROOFTOP STRUCTURE RESTORATION
B08038906-I1
11/26/2025
Signed off — Alteration
EXISTING ROOF PERIMETER GUARDRAIL TO BE REMOVED AND REPLACED WITH NEW GUARDRAIL.NEW CONCRETE STEPS ADDED AT STAIR BULKHEAD ENTRY DOORS.LOOSE LINTEL REPLACEMENT AT BULKHEAD LOUVER OPENING.
B08038966-I1
09/02/2025
Signed off — Alteration
INSTALLATION OF SUSPENDED SCAFFOLD & MATERIAL HOIST FOR ROOF REPLACEMENT & ROOFTOP STRUCTURE RENOVATION. SUSPENDED SCAFFOLD & MATERIAL HOIST SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BC. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01011730-I1
09/02/2025
Permit issued — Suspended Scaffold
B01011730-I1-SC
08/28/2025
Permit issued — General Construction
B08038906-I1-GC
07/17/2025
Cycle 10 facade report submitted
07/17/2025
Cycle 10 facade report signed — UNSAFE
07/16/2025
Cycle 10 facade inspection completed
06/10/2025
Filed — Alteration
EXISTING ROOF PERIMETER GUARDRAIL TO BE REMOVED AND REPLACED WITH NEW GUARDRAIL.NEW CONCRETE STEPS ADDED AT STAIR BULKHEAD ENTRY DOORS.LOOSE LINTEL REPLACEMENT AT BULKHEAD LOUVER OPENING.
B08038966-P2
06/03/2025
Filed — Alteration
ROOFING REPLACEMENT AND ROOFTOP STRUCTURE RESTORATION
B08038906-P2
03/06/2025
Filed — Alteration
INSTALLATION OF NEW SIDEWALK SHED AT 335 SUTTER AVENUE, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
B01171337-P1
01/28/2025
Permit issued — Construction Fence
B01171343-I1-FN
01/28/2025
Permit issued — Sidewalk Shed
B01171337-I1-SH
01/27/2025
Filed — Alteration
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 335 SUTTER AVENUE, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
B01171343-I1
01/27/2025
Filed — Alteration
INSTALLATION OF NEW SIDEWALK SHED AT 335 SUTTER AVENUE, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
B01171337-I1
01/15/2025
Signed off — Alteration
B01016882-I1
01/15/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01016880-I1
10/10/2024
Permit issued — Suspended Scaffold
B01122456-I1-SC
10/08/2024
Filed — Alteration
Installation of suspended scaffold for facade work or inspection.
B01122456-I1
05/15/2024
Permit issued — General Construction
B08038906-I1-GC
05/08/2024
Permit issued — Structural
B08038966-I1-ST
04/19/2024
Filed — Alteration
EXISTING ROOF PERIMETER GUARDRAIL TO BE REMOVED AND REPLACED WITH NEW GUARDRAIL.NEW CONCRETE STEPS ADDED AT STAIR BULKHEAD ENTRY DOORS.LOOSE LINTEL REPLACEMENT AT BULKHEAD LOUVER OPENING.
B08038966-P1
04/12/2024
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01016880-P1
03/13/2024
Permit issued — Suspended Scaffold
B01011730-I1-SC
03/08/2024
Filed — Alteration
B01016882-I1
03/08/2024
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01016880-I1
03/08/2024
Permit issued — Construction Fence
B01016882-I1-FN
03/08/2024
Permit issued — Sidewalk Shed
B01016880-I1-SH
03/07/2024
Objection resolved — Addressed
03/06/2024
Objection raised — Scope
02/29/2024
Filed — Alteration
INSTALLATION OF SUSPENDED SCAFFOLD & MATERIAL HOIST FOR ROOF REPLACEMENT & ROOFTOP STRUCTURE RENOVATION. SUSPENDED SCAFFOLD & MATERIAL HOIST SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BC. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01011730-I1
02/28/2024
Filed — Alteration
ROOFING REPLACEMENT AND ROOFTOP STRUCTURE RESTORATION
B08038906-P1
12/11/2023
Inspection — Pass-Final PL - More than 10 Requested Floors
Pass
View inspection ↗
10/10/2023
Permit issued — Plumbing
B00929035-I1-PL
09/28/2023
Filed — Alteration
Replacing gas riser for cooking (E) from cellar to the 22nd floor with new as per plans filed herewith.
B00929035-I1
12/21/2022
Objection resolved — Addressed
12/20/2022
Objection resolved — Addressed
12/05/2022
Objection raised — Scope
12/02/2022
Violation issued (ECB, closed)
Local Law
12/02/2022
Objection raised — Scope
11/28/2022
Filed — Alteration
ROOFING REPLACEMENT AND ROOFTOP STRUCTURE RESTORATION
B08038906-I1
11/28/2022
Filed — Alteration
EXISTING ROOF PERIMETER GUARDRAIL TO BE REMOVED AND REPLACED WITH NEW GUARDRAIL.NEW CONCRETE STEPS ADDED AT STAIR BULKHEAD ENTRY DOORS.LOOSE LINTEL REPLACEMENT AT BULKHEAD LOUVER OPENING.
B08038966-I1
02/22/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/31/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/26/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/29/2017
Cycle 8 facade report submitted
08/01/2017
Cycle 8 facade report signed — SWARMP
07/26/2017
Cycle 8 facade inspection completed
01/03/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/16/2015
Cycle 6 facade report submitted
09/16/2015
Cycle 7 facade report submitted
04/14/2015
Violation issued (ECB, closed)
Elevators
07/28/2014
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
07/11/2014
Cycle 7 facade report submitted
06/05/2014
Cycle 7 facade report signed — UNSAFE
04/16/2014
Cycle 7 facade inspection completed
Latest 60 of 89 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedMNK ENTERPRISES LLC07/17/2026
DOB NOWSidewalk ShedPermit IssuedMNK ENTERPRISES LLC06/04/2026
DOB NOWConstruction FencePermit IssuedMNK ENTERPRISES LLC03/04/2026
DOB NOWSidewalk ShedPermit IssuedMNK ENTERPRISES LLC03/02/2026
DOB NOWSuspended ScaffoldSigned-offZORIA HOUSING LLC09/02/2025
DOB NOWGeneral ConstructionSigned-offZORIA HOUSING, LLC08/28/2025
DOB NOWConstruction FencePermit IssuedMNK ENTERPRISES LLC01/28/2025
DOB NOWSidewalk ShedPermit IssuedMNK ENTERPRISES LLC01/28/2025
DOB NOWSuspended ScaffoldPermit IssuedSKYLINE RESTORATION INC10/10/2024
DOB NOWGeneral ConstructionSigned-offZORIA HOUSING, LLC05/15/2024
DOB NOWStructuralSigned-offZORIA HOUSING, LLC05/08/2024
DOB NOWSuspended ScaffoldSigned-offZORIA HOUSING LLC03/13/2024
DOB NOWConstruction FenceSigned-offZORIA HOUSING, LLC03/08/2024
DOB NOWSidewalk ShedSigned-offMNK ENTERPRISES LLC03/08/2024
DOB NOWPlumbingSigned-offRICHARDS P AND H CO, INC10/10/2023
BISOTISSUEDAAA WINDOWS & DOORS CORP07/18/2015
BISOTISSUEDAAA WINDOWS & DOORS CORP04/01/2015
BISEQISSUEDAAA WINDOWS & DOORS CORP03/24/2015
BISEQISSUEDMETROPOLITAN ENTERPRISES03/06/2015
BISEQISSUEDAAA WINDOWS & DOORS CORP02/23/2015
BISEQISSUEDAAA WINDOWS & DOORS CORP02/23/2015
BISEQISSUEDMETROPOLITAN ENTERPRISES02/26/2014
BISEQISSUEDMETROPOLITAN ENTERPRISES05/08/2013
BISEQISSUEDBILTMORE GENERAL CONTRACTORS08/13/2012
BISOTISSUEDBILTMORE GENERAL CONTRACTORS08/13/2012
BISEQISSUEDMETROPOLITAN ENTERPRISES05/07/2012
BISOTISSUEDBILTMORE GENERAL CONTRACTORS05/04/2012
BISEQISSUEDBILTMORE GENERAL CONTRACTORS03/29/2012
BISPLISSUEDRICHARDS P AND H CO., INC08/01/2011
BISEQISSUEDMETROPOLITAN ENTERPR INC05/20/2011
BISEQISSUEDMETROPOLITAN ENTERPR INC08/13/2010
BISEQISSUEDPIONEER GENERAL CONSTRUCT03/01/2007
BISPLISSUEDV. C. VITANZA SONS INC09/26/2005
BISEQISSUEDLILLY CONSTRUCTION CO10/14/2003
BISPLISSUEDRICHARD'S PLBG & HTG CO INC12/31/2002
BISSPISSUEDRICHARDS PLBG & HTG CO INC06/03/2002
BISPLISSUEDROY B PLUMBING & HEATING08/03/2000
BISPLISSUEDREYVIN PLBG & HTG CORP03/29/2000
1 project · most recent 09/28/2023
Gas
FiledStatusContractorScope
09/28/2023Signed-offRICHARDS P AND H CO, INCGas
8 projects · most recent 12/26/2024
General Wiring
FiledStatusContractorScope
12/26/2024Permit IssuedLIT MODE ELECL CONTG INC—
03/04/2024CompleteAUJLA ELECTRIC CORP—
05/08/2023CompleteCSI SEC & ELECTRIC INC—
04/25/2023CompleteTRI-STATE ELECL & MECHL IGeneral Wiring
10/04/2022CompleteCSI SEC & ELECTRIC INC—
04/25/2022Permit IssuedN.Y.C. HOUSING AUTHORITYGeneral Wiring
12/21/2021CompleteCSI SEC & ELECTRIC INC—
03/23/2021CompleteJEMCO ELECT. CONTRS INC—
2 projects · most recent 03/06/2025
Sidewalk Shed Fence
FiledStatusContractorScope
03/06/2025Permit IssuedMNK ENTERPRISES LLCSidewalk Shed
01/27/2025Permit IssuedMNK ENTERPRISES LLCFence
1 project · most recent 10/08/2024
Suspended Scaffold (SC)
FiledStatusContractorScope
10/08/2024Permit Issued—Suspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
12/11/2023Pass-Final PL - More than 10 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 37
DateRequirementInspectorRole
06/24/2025Structural Stability – Alterations of existing buildingsALEXIS SCHLESSINGERMANspecial
06/24/2025Post-installed AnchorsALEXIS SCHLESSINGERMANspecial
06/24/2025MasonryALEXIS SCHLESSINGERMANspecial
06/24/2025FinalALEXIS SCHLESSINGERMANprogress
06/24/2025Tenant Protection Plan ComplianceALEXIS SCHLESSINGERMANspecial
06/12/2025MasonryALEXIS SCHLESSINGERMANspecial
06/12/2025Energy Code Compliance InspectionsALEXIS SCHLESSINGERMANprogress
06/12/2025FinalALEXIS SCHLESSINGERMANprogress
06/12/2025Insulation placement and R valuesALEXIS SCHLESSINGERMANenergy_progress
06/12/2025Fenestration and door U-factor and product ratingsALEXIS SCHLESSINGERMANenergy_progress
06/12/2025Post-installed AnchorsALEXIS SCHLESSINGERMANspecial
06/12/2025Tenant Protection Plan ComplianceALEXIS SCHLESSINGERMANspecial
05/20/2025Tenant Protection Plan Compliance—special
05/20/2025Tenant Protection Plan Compliance—special
05/13/2025MasonryALEXIS SCHLESSINGERMANspecial
05/13/2025Post-installed AnchorsALEXIS SCHLESSINGERMANspecial
05/13/2025Structural Stability – Alterations of existing buildingsALEXIS SCHLESSINGERMANspecial
05/13/2025FinalALEXIS SCHLESSINGERMANprogress
05/13/2025MasonryALEXIS SCHLESSINGERMANspecial
05/13/2025Post-installed AnchorsALEXIS SCHLESSINGERMANspecial
05/13/2025Energy Code Compliance InspectionsALEXIS SCHLESSINGERMANprogress
05/13/2025FinalALEXIS SCHLESSINGERMANprogress
05/13/2025Insulation placement and R valuesALEXIS SCHLESSINGERMANenergy_progress
05/13/2025Fenestration and door U-factor and product ratingsALEXIS SCHLESSINGERMANenergy_progress
10/04/2024Alternative Materials - OTCR Buildings Bulletin NumberLeo Leespecial
Latest 25 of 37.
▾Documents — 196 on file (BIS + DOB NOW)
▸Plans & Drawings15
▸DOB NOWPlans/Sketch15
08/28/2026B08038906-P2Request digital key ↗
08/28/2026B08038966-P2Request digital key ↗
08/28/2026B08038966-P1Request digital key ↗
Showing 3 of 15 on file for this type
▸Applications & Permits25
▸BISWORK PERMIT APPLICATION15
03/24/2015340231136Open ↗
03/09/2015320197924Open ↗
02/23/2015340231136Open ↗
Showing 3 of 15 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION10
03/05/2015340232778Open ↗
02/23/2015340231136Open ↗
02/21/2015340231154Open ↗
Showing 3 of 10 on file for this type
▸Seals & Professional Certifications66
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION16
06/09/2017340232778Open ↗
06/09/2017340232778Open ↗
03/01/2016340231136Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature13
08/28/2026B08038906-P2Open ↗
08/28/2026B08038906-P1Open ↗
08/28/2026B08038906-I1Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature10
09/02/2026B08038906-I1Open ↗
09/02/2026B08038906-I1Open ↗
09/01/2026B08038906-P2Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/02/2026B08038906-I1Open ↗
09/02/2026B08038906-I1Open ↗
09/01/2026B08038906-P2Open ↗
Showing 3 of 7 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
03/29/2012320358590Open ↗
02/27/2012320432288Open ↗
04/01/2011320285749Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM4
03/29/2012320358590Open ↗
02/27/2012320432288Open ↗
04/01/2011320285749Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
03/05/2015340232778Open ↗
02/23/2015340231136Open ↗
02/21/2015340231154Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY4
03/05/2015340232778Open ↗
02/23/2015340231136Open ↗
02/21/2015340231154Open ↗
Showing 3 of 4 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION4
03/05/2015340232778Open ↗
02/23/2015340231136Open ↗
02/21/2015340231154Open ↗
Showing 3 of 4 on file for this type
▸Trade Schedules & Equipment6
▸BISSELF-CERT PLUMBING NOTICE5
10/11/2012320285749Open ↗
07/26/2012320285749Open ↗
06/21/2012320285749Open ↗
Showing 3 of 5 on file for this type
▸BISSCHEDULE B - PLUMBING1
04/01/2011320285749Open ↗
▸Environmental & Asbestos12
▸BISDEP ASBESTOS PROJECT COMPLETION FORM5
06/09/2017340232778Open ↗
05/22/2015320432288Open ↗
05/22/2015320432288Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)2
03/05/2015340232778Open ↗
08/05/2011320285749Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
08/28/2026B08038966-I1Open ↗
08/15/2026B08038906-I1Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
08/13/2010320197924Open ↗
▸BISASBESTOS INSPECTION REPORT1
04/01/2011320285749Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026B00929035-I1Open ↗
▸Energy Compliance6
▸BISTECHNICAL REPORT: ENERGY2
02/27/2012320432288Open ↗
04/01/2011320285749Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
12/03/2012320285749Open ↗
▸BISTR8: Energy Code Progress Inspections1
10/29/2011320285749Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
05/26/2015320432288Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
02/23/2015340231136Open ↗
▸Inspections & Test Reports4
▸BISTECHNICAL REPORT: RESPONSIBILITY3
02/23/2015340231136Open ↗
02/21/2015340231154Open ↗
02/21/2015340231145Open ↗
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
02/21/2015340231145Open ↗
▸Approvals, Objections & Sign-offs42
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter15
08/28/2026B08038906-P2Open ↗
08/28/2026B08038966-P2Open ↗
08/28/2026B08038966-P1Open ↗
Showing 3 of 15 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION10
03/01/2016340231136Open ↗
03/01/2016340231145Open ↗
03/01/2016340231154Open ↗
Showing 3 of 10 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST8
06/09/2017340232778Open ↗
03/01/2016340231136Open ↗
03/01/2016340231145Open ↗
Showing 3 of 8 on file for this type
▸BISADMINISTRATIVE OBJECTIONS4
03/29/2012320358590Open ↗
02/27/2012320432288Open ↗
04/01/2011320285749Open ↗
Showing 3 of 4 on file for this type
▸BISFINAL2
02/23/2015340231136Open ↗
02/21/2015340231154Open ↗
▸DOB NOWDEP Variance (V5) letter2
08/28/2026B08038966-I1Open ↗
08/15/2026B08038906-I1Open ↗
▸BISCCD1-Construction Code Determination1
03/27/2012320432288Open ↗
▸Cost, Insurance & Ownership6
▸BISCOST AFFIDAVIT6
06/09/2017340232778Open ↗
05/26/2015320432288Open ↗
03/05/2015340232778Open ↗
Showing 3 of 6 on file for this type
▸Filing & Intake Forms8
▸BISEFILING JOB APPLICATION COVER SHEET5
03/05/2015340232778Open ↗
02/23/2015340231136Open ↗
02/21/2015340231154Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING COVER SHEET3
02/27/2012320432288Open ↗
04/01/2011320285749Open ↗
08/13/2010320197924Open ↗
▸Other Documents6
▸DOB NOWManufacturer's Specifications2
08/13/2026B01011730-I1Open ↗
08/13/2026B01122456-I1Open ↗
▸DOB NOWCalculations2
08/13/2026B01011730-I1Open ↗
08/13/2026B01122456-I1Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
06/09/2017340232778Open ↗
▸BISFEE EXEMPTION DOCUMENTATION1
03/05/2015340232778Open ↗