← Back
Large suburban residence
28 ELMIRA STREET
STATEN ISLAND · Oakwood-Richmondtown · BIN 5058694
💬 Discuss this project
2023Year Built
2Stories
A3Building Class
R2Zoning
4,108 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Large suburban residence · 6,300 sf lot · 0.65 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralPlumbing
Floor 216p · 1 filing · 20 docs
Floor 117p · 1 filing · 20 docs
Basement17p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BLUE STAR GROUP103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JOSEPH M. MORACE, A.I.A., ARCHITECT504/04/2024
C&P DESIGN CONSULTANTS105/06/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PATRICIA L GASS1003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BLUE STAR GROUP LLCGeneral Contractor907/08/2026
J. SMITH CONSTRUCTION INC.General Contractor107/08/2026
CAPITAL CONTR P&H CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
A TECH ENGINEERING NYC, P6738204/04/2024
Building Lifecycle
All (52)Filed (6)Permit Issued (7)Signed Off (2)Violation (1)Inspection (8)Special Inspection (28)
04/04/2024
Filed — New Building
INSTALLATION OF NEW GAS AND PLUMBING FIXTURES FOR A DETACHED ONE-FAMILY RESIDENCE.
S00594240-P2
04/04/2024
Special inspection requirement — Concrete - Cast-In-Place
anthony santoro
04/04/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
anthony santoro
04/04/2024
Special inspection requirement — Mechanical Systems
anthony santoro
04/04/2024
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
anthony santoro
04/04/2024
Special inspection requirement — Structural Steel - High Strength Bolting
anthony santoro
04/04/2024
Special inspection requirement — Subgrade Inspections
anthony santoro
04/04/2024
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
anthony santoro
04/04/2024
Special inspection requirement — Energy Code Compliance Inspections
anthony santoro
04/04/2024
Special inspection requirement — Final
anthony santoro
04/04/2024
Special inspection requirement — Fire-Resistance Rated Construction
anthony santoro
04/04/2024
Special inspection requirement — Footing and Foundation
anthony santoro
04/04/2024
Special inspection requirement — Structural Wood Frame
anthony santoro
04/04/2024
Special inspection requirement — Fenestration air leakage
anthony santoro
04/04/2024
Special inspection requirement — Interior lighting power
anthony santoro
04/04/2024
Special inspection requirement — HVAC-R and service water heating equipment
anthony santoro
04/04/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
anthony santoro
04/04/2024
Special inspection requirement — Maintenance information
anthony santoro
04/04/2024
Special inspection requirement — HVAC-R and service water heating system controls
anthony santoro
04/04/2024
Special inspection requirement — Fenestration areas
anthony santoro
04/04/2024
Special inspection requirement — Protection of exposed foundation insulation
anthony santoro
04/04/2024
Special inspection requirement — Permanent certificate
anthony santoro
04/04/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
anthony santoro
04/04/2024
Special inspection requirement — Fireplaces
anthony santoro
04/04/2024
Special inspection requirement — Air barrier — testing
anthony santoro
04/04/2024
Special inspection requirement — Insulation placement and R values
anthony santoro
04/04/2024
Special inspection requirement — Ventilation and air distribution system
anthony santoro
04/04/2024
Special inspection requirement — Air barrier - visual inspection
anthony santoro
04/04/2024
Special inspection requirement — Electric vehicle service equipment requirements
anthony santoro
03/19/2024
Signed off — New Building
INSTALLATION OF NEW GAS AND PLUMBING FIXTURES FOR A DETACHED ONE-FAMILY RESIDENCE.
S00594240-S3
03/06/2024
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
02/16/2024
Permit issued — Curb Cut
S00594240-S3-CC
02/14/2024
Signed off — Alteration
S00732562-I1
02/09/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/22/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/15/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/26/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/28/2023
Filed — New Building
INSTALLATION OF NEW GAS AND PLUMBING FIXTURES FOR A DETACHED ONE-FAMILY RESIDENCE.
S00594240-S3
02/14/2023
Violation issued (ECB, closed)
Construction
02/07/2023
Filed — New Building
INSTALLATION OF NEW GAS AND PLUMBING FIXTURES FOR A DETACHED ONE-FAMILY RESIDENCE.
S00594240-P1
01/23/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/01/2022
Permit issued — General Construction
S00594240-I1-GC-CX
11/01/2022
Permit issued — Foundation
S00594240-I1-GC-CX
11/01/2022
Permit issued — Structural
S00594240-I1-GC-CX
09/30/2022
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
09/23/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
08/31/2022
Permit issued — Plumbing
S00594240-S2-PL
08/30/2022
Filed — New Building
INSTALLATION OF NEW GAS AND PLUMBING FIXTURES FOR A DETACHED ONE-FAMILY RESIDENCE.
S00594240-S2
08/17/2022
Permit issued — Structural
S00594240-I1-GC-CX
05/12/2022
Permit issued — Construction Fence
S00732562-I1-FN
05/06/2022
Filed — Alteration
S00732562-I1
01/26/2022
Filed — New Building
INSTALLATION OF NEW GAS AND PLUMBING FIXTURES FOR A DETACHED ONE-FAMILY RESIDENCE.
S00594240-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offBLUE STAR GROUP LLC02/16/2024
DOB NOWGeneral ConstructionPermit IssuedBLUE STAR GROUP LLC11/01/2022
DOB NOWFoundationPermit IssuedBLUE STAR GROUP LLC11/01/2022
DOB NOWStructuralPermit IssuedBLUE STAR GROUP LLC11/01/2022
DOB NOWPlumbingSigned-offCAPITAL CONTR P&H CORP08/31/2022
DOB NOWStructuralPermit IssuedBLUE STAR GROUP LLC08/17/2022
DOB NOWConstruction FenceSigned-offJ. SMITH CONSTRUCTION INC05/12/2022
BISOTISSUEDVENTURE HOME SOLAR LLC05/17/2023
BIS—ISSUEDJ. SMITH CONSTRUCTION INC.05/13/2022
2 projects · most recent 05/16/2023
General Wiring
FiledStatusContractorScope
05/16/2023CompleteVENTURE HOME SOLAR LLC—
12/13/2022CompleteTRUE ELECTRIC CORP.General Wiring
1 project · most recent 04/04/2024
Fence
FiledStatusContractorScope
04/04/2024Signed-offBLUE STAR GROUP LLCFence
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
03/06/2024Pass-Final Curb Cut Non-Directive 14PassView ↗
02/09/2024Pass-Final CND-Occupancy InspectionPassView ↗
08/22/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/15/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/26/2023Pass-Final CND-Occupancy InspectionPassView ↗
01/23/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/30/2022Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
09/23/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 28
DateRequirementInspectorRole
04/04/2024Concrete - Cast-In-Placeanthony santorospecial
04/04/2024Fire-Resistant Penetrations and Jointsanthony santorospecial
04/04/2024Mechanical Systemsanthony santorospecial
04/04/2024Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installationanthony santorospecial
04/04/2024Structural Steel - High Strength Boltinganthony santorospecial
04/04/2024Subgrade Inspectionsanthony santorospecial
04/04/2024Subsurface Investigations (Borings/Test Pits)anthony santorospecial
04/04/2024Energy Code Compliance Inspectionsanthony santoroprogress
04/04/2024Finalanthony santoroprogress
04/04/2024Fire-Resistance Rated Constructionanthony santoroprogress
04/04/2024Footing and Foundationanthony santoroprogress
04/04/2024Structural Wood Frameanthony santoroprogress
04/04/2024Fenestration air leakageanthony santoroenergy_progress
04/04/2024Interior lighting poweranthony santoroenergy_progress
04/04/2024HVAC-R and service water heating equipmentanthony santoroenergy_progress
04/04/2024Fenestration and door U-factor and product ratingsanthony santoroenergy_progress
04/04/2024Maintenance informationanthony santoroenergy_progress
04/04/2024HVAC-R and service water heating system controlsanthony santoroenergy_progress
04/04/2024Fenestration areasanthony santoroenergy_progress
04/04/2024Protection of exposed foundation insulationanthony santoroenergy_progress
04/04/2024Permanent certificateanthony santoroenergy_progress
04/04/2024HVAC-R and service water piping design and insulationanthony santoroenergy_progress
04/04/2024Fireplacesanthony santoroenergy_progress
04/04/2024Air barrier — testing anthony santoroenergy_progress
04/04/2024Insulation placement and R valuesanthony santoroenergy_progress
Latest 25 of 28.
▾Documents — 96 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/24/2026S00732562-I1Request digital key ↗
08/21/2026S00594240-S3Request digital key ↗
08/21/2026S00594240-P1Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits7
▸BISPLAN / WORK APPROVAL APPLICATION3
05/16/2023540250431Open ↗
03/24/2022520464649Open ↗
08/25/2021540205678Open ↗
▸BISWORK PERMIT APPLICATION2
05/17/2023540250431Open ↗
05/13/2022520464649Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation2
03/26/2024540205678Open ↗
07/25/2022540205678Open ↗
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026S00594240-P2Open ↗
08/13/2026S00594240-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/13/2026S00594240-P2Open ↗
08/13/2026S00594240-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026S00594240-I1Open ↗
▸Seals & Professional Certifications15
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/21/2026S00594240-S3Open ↗
08/21/2026S00594240-P1Open ↗
08/21/2026S00594240-S2Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
05/16/2023540250431Open ↗
08/25/2021540205678Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/26/2026S00594240-P2Open ↗
08/26/2026S00594240-P2Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/26/2026S00594240-P2Open ↗
08/26/2026S00594240-P2Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
05/16/2023540250431Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
08/25/2021540205678Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
05/16/2023540250431Open ↗
▸Trade Schedules & Equipment5
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/13/2026S00594240-I1Open ↗
08/13/2026S00594240-P2Open ↗
▸BISGAS CUT-OFF1
05/13/2022520464649Open ↗
▸BISELECTRIC CUT-OFF1
05/13/2022520464649Open ↗
▸BISSEWER CUT-OFF1
05/13/2022520464649Open ↗
▸Safety & Tenant Protection8
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE2
05/13/2022520464649Open ↗
05/13/2022520464649Open ↗
▸DOB NOWStreet Tree Checklist2
08/21/2026S00594240-I1Open ↗
08/21/2026S00594240-P2Open ↗
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
05/13/2022520464649Open ↗
▸BISSTREET TREE SUPPORTING DOCUMENT1
08/25/2021540205678Open ↗
▸BISTPP1: TENANT PROTECTION PLAN1
05/16/2023540250431Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026S00594240-I1Open ↗
▸Environmental & Asbestos3
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
05/16/2023540250431Open ↗
05/13/2022520464649Open ↗
▸BISRODENT CONTROL1
05/13/2022520464649Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
08/21/2023540250431Open ↗
05/16/2023540250431Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
05/16/2023540250431Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
08/21/2023540250431Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
08/21/2023540250431Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
05/16/2023540250431Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026S00594240-I1Open ↗
▸Inspections & Test Reports7
▸BISTECHNICAL REPORT: RESPONSIBILITY2
08/21/2023540250431Open ↗
05/16/2023540250431Open ↗
▸DOB NOWSOIL REPORT2
08/13/2026S00594240-I1Open ↗
08/13/2026S00594240-P2Open ↗
▸BISBPP-9 - Request for Builders Pavement Field Inspection1
08/25/2021540205678Open ↗
▸DOB NOWTR4 Plot Diagram1
08/13/2026S00594240-I1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026S00594240-I1Open ↗
▸Approvals, Objections & Sign-offs7
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
08/22/2023540250431Open ↗
▸BISTAP LETTER - DOM SVC : DEP-DOM1
05/13/2022520464649Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
05/13/2022520464649Open ↗
▸BISLANDMARKS APPROVAL1
05/13/2022520464649Open ↗
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
03/26/2024540205678Open ↗
▸BISFINAL ELECTRICAL SIGNOFF1
08/22/2023540250431Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
05/13/2022520464649Open ↗
▸Cost, Insurance & Ownership5
▸BISCOST AFFIDAVIT1
05/16/2023540250431Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
08/21/2023540250431Open ↗
▸BISWC-DB-100 (Replaces Form C-105-21)Affidavit for NY Entities And Any Out of State Entities with no employees1
05/13/2022520464649Open ↗
▸BISDEPT OF FINANCE VERIFICATION1
05/13/2022520464649Open ↗
▸BISPROJECT-SPECIFIC GL INSURANCE1
05/13/2022520464649Open ↗
▸Filing & Intake Forms4
▸BISEFILING JOB APPLICATION COVER SHEET2
05/16/2023540250431Open ↗
08/25/2021540205678Open ↗
▸BISEFILING COVER SHEET1
03/24/2022520464649Open ↗
▸BISADDITIONAL INFORMATION1
03/26/2024540205678Open ↗
▸Other Documents17
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION4
05/16/2023540250431Open ↗
05/13/2022520464649Open ↗
05/13/2022520464649Open ↗
Showing 3 of 4 on file for this type
▸BISBPP - SUPPORTING DOCUMENTATION2
07/21/2022540205678Open ↗
08/25/2021540205678Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026S00594240-P2Open ↗
08/13/2026S00594240-I1Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026S00594240-P2Open ↗
08/13/2026S00594240-I1Open ↗
▸DOB NOWProperty Ownership Certification2
08/21/2026S00594240-I1Open ↗
08/21/2026S00594240-P2Open ↗
▸BISCOMMUNITY BOARD NOTIFICATION1
05/13/2022520464649Open ↗
▸BISBPP: WAIVER OF GRADE FILING1
03/26/2024540205678Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
03/26/2024540205678Open ↗
▸BISBPP: TOPOGRAPHIC SURVEY1
03/26/2024540205678Open ↗
▸DOB NOWFinal Survey1
08/13/2026S00594240-I1Open ↗