| Owner | Filings | Most Recent |
|---|---|---|
| J G CONSTRUCTION SRVCS | 9 | 09/07/2026 |
| ALEXIS CONSTRUCTION | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/18/2024 | $4.3M | — | THE HANS G. KOK TRUST → Private party | $1,039/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ASHRAF CORP | 1 | 03/13/2026 |
| BITOPI CONSULTANTS LLC | 1 | 02/05/2026 |
| RJD ENGINEERING LLC | 4 | 11/06/2025 |
| BAXT INGUI ARCHITECTS | 3 | 10/15/2025 |
| GRASSO-MENZIUSO ARCHITECTS | 2 | 11/12/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| GAMILL ENGINEERING, PC | 14 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ALEXIS CONSTRUCTION INC | General Contractor | 7 | 04/09/2026 |
| J & G CONSTRUCTION SVCS | General Contractor | 4 | 09/07/2026 |
| SPICE ELECTRIC COMPANY | Electrical | 2 | 03/22/2026 |
| TT MECHANICAL CORP | Plumbing | 2 | 07/08/2026 |
| A&H EXPRESS PLBG&HTG CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MACIA INSPECTION & TESTIN | 402 | 7 | 11/06/2025 |
| GRASSO-MENZIUSO ARCHITECT | 1279 | 2 | 11/12/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | J & G CONSTRUCTION SVCS | 09/02/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | J & G CONSTRUCTION SVCS | 06/05/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | J & G CONSTRUCTION SVCS | 04/28/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | J & G CONSTRUCTION SVCS | 02/06/2026 |
| DOB NOW | Mechanical Systems | Signed-off | ALEXIS CONSTRUCTION | 08/29/2025 |
| DOB NOW | Structural | Signed-off | ALEXIS CONSTRUCTION | 08/19/2025 |
| DOB NOW | General Construction | Signed-off | ALEXIS CONSTRUCTION | 08/19/2025 |
| DOB NOW | Structural | Signed-off | ALEXIS CONSTRUCTION | 12/24/2024 |
| DOB NOW | Mechanical Systems | Signed-off | ALEXIS CONSTRUCTION | 11/13/2024 |
| DOB NOW | Plumbing | Permit Issued | A&H EXPRESS PLBG&HTG CORP | 10/15/2024 |
| DOB NOW | General Construction | Signed-off | ALEXIS CONSTRUCTION | 09/18/2024 |
| DOB NOW | Plumbing | Signed-off | RENTOM GROUP CORP | 10/25/2021 |
| DOB NOW | Plumbing | Signed-off | RENTOM GROUP CORP | 09/27/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 11/06/2025 | Signed-off | ALEXIS CONSTRUCTION INC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric MXZ-SM48NAMHZ2 48,000 BTU · Heat Pump Outdoor ×4 PEFY-P12NMAU-E4 12,000 BTU · Vrf Indoor ×2 PEFY-P18NMAU-E4 18,000 BTU · Vrf Indoor ×2 PEFY-P24NMU-E4 24,000 BTU · Vrf Indoor ×2 PVFY-P18NAMU-E1 18,000 BTU · Vrf Indoor ×2 PVFY-P24NAMU-E1 24,000 BTU · Vrf Indoor ×2 Ventilation Panasonic FV-0511VK3 110 CFM · Exhaust Fan ×10 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/06/2025 | Permit Issued | A&H EXPRESS PLBG&HTG CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/04/2026 | Permit Issued | RICHARD NEU | — |
| 03/19/2025 | Permit Issued | SPICE ELECTRIC COMPANY | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/13/2026 | Permit Issued | J & G CONSTRUCTION SVCS | Scaffold |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/03/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 02/20/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 02/20/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 02/20/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/20/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/20/2021 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 12/06/2021 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 11/03/2021 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/05/2025 | HVAC-R and service water heating equipment | CHUNG CHING JEN | energy_progress |
| 11/05/2025 | Fire-Resistant Penetrations and Joints | CHUNG CHING JEN | special |
| 11/05/2025 | Energy Code Compliance Inspections | CHUNG CHING JEN | progress |
| 11/05/2025 | HVAC-R and service water piping design and insulation | CHUNG CHING JEN | energy_progress |
| 11/05/2025 | HVAC-R and service water heating system controls | CHUNG CHING JEN | energy_progress |
| 11/05/2025 | Maintenance information | CHUNG CHING JEN | energy_progress |
| 01/28/2025 | Energy Code Compliance Inspections | CHUNG CHING JEN | progress |
| 01/28/2025 | Final | CHUNG CHING JEN | progress |
| 01/28/2025 | HVAC-R and service water heating system controls | CHUNG CHING JEN | energy_progress |
| 01/28/2025 | HVAC-R and service water heating equipment | CHUNG CHING JEN | energy_progress |
| 01/28/2025 | HVAC-R and service water piping design and insulation | CHUNG CHING JEN | energy_progress |
| 01/28/2025 | Maintenance information | CHUNG CHING JEN | energy_progress |
| 01/28/2025 | Shutoff dampers | CHUNG CHING JEN | energy_progress |
| 01/28/2025 | Fire-Resistant Penetrations and Joints | CHUNG CHING JEN | special |
| 01/28/2025 | Mechanical Systems | CHUNG CHING JEN | special |
| 11/01/2024 | Fire-Resistant Penetrations and Joints | CHUNG CHING JEN | special |
| 11/01/2024 | Energy Code Compliance Inspections | CHUNG CHING JEN | progress |
| 11/01/2024 | Final | CHUNG CHING JEN | progress |
| 11/01/2024 | Fire-Resistance Rated Construction | CHUNG CHING JEN | progress |
| 11/23/2021 | Fire-Resistant Penetrations and Joints | Christopher Menziuso | special |
| 11/12/2021 | Fire-Resistant Penetrations and Joints | Christopher Menziuso | special |