| Owner | Filings | Most Recent |
|---|---|---|
| SLOANS UNIVERSITY AVE CO | 1 | 03/22/2026 |
| 280 HENRY STREET | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| IAQ SYSTEMS INC | 4 | 11/06/2024 |
| MLA ARCHITECTURE | 1 | 10/23/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| EMPIRE CITY CONSULTANTS, INC. | 8 | 03/21/2026 |
| ROBERT PAPAZIAN ARCHITECT PC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ZIBA CONSTRUCTION INC | General Contractor | 7 | 07/08/2026 |
| CEDAR ELEC'L CONT'RS INC. | Electrical | 1 | 03/22/2026 |
| DEPENDABLE MECHANICAL COR | Fire Protection | 1 | 07/08/2026 |
| A&H EXPRESS PLBG&HTG CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CONCRETE SOLUTIONS LAB CO | 5344 | 3 | 11/06/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | A&H EXPRESS PLBG&HTG CORP | 04/09/2025 |
| DOB NOW | General Construction | Signed-off | ZIBA CONSTRUCTION INC | 04/03/2025 |
| DOB NOW | Mechanical Systems | Signed-off | ZIBA CONSTRUCTION INC | 04/03/2025 |
| DOB NOW | Mechanical Systems | Signed-off | ZIBA CONSTRUCTION INC | 04/03/2025 |
| DOB NOW | Sprinklers | Signed-off | DEPENDABLE MECHANICAL COR | 03/17/2025 |
| DOB NOW | Mechanical Systems | Signed-off | ZIBA CONSTRUCTION INC | 02/18/2025 |
| DOB NOW | General Construction | Signed-off | ZIBA CONSTRUCTION INC | 02/18/2025 |
| BIS | OT | ISSUED | HIGH QUALITY CONSTRUCTION | 04/16/2013 |
| BIS | OT | ISSUED | QWEST CONTRACTING CORP | 05/31/2011 |
| BIS | MH | ISSUED | QWEST CONTRACTING CORP | 05/31/2011 |
| BIS | SP | ISSUED | MILLER PLUMBING & HTG INC | 02/23/2011 |
| BIS | PL | ISSUED | UNIVERSAL PLUMBING INC | 01/20/2011 |
| BIS | MH | ISSUED | QWEST CONTRACTING CORP | 01/07/2011 |
| BIS | OT | ISSUED | QWEST CONTRACTING CORP | 01/07/2011 |
| BIS | MH | ISSUED | AMTECH AIR CONDITIONING & | 08/15/2007 |
| BIS | FP | ISSUED | NEW YORK BUSINESS SYSTEM INC | 06/25/2007 |
| BIS | PL | ISSUED | AA M SAGE P;H INC | 10/31/2006 |
| BIS | SP | ISSUED | VINCESKI MAY PLUMB HEAT LLC | 02/16/2005 |
| BIS | SP | ISSUED | VINCESKI-MAY PLB. HTG. LLC | 01/25/2005 |
| BIS | PL | ISSUED | VINCESKI-MAY PLB. HTG. LLC | 01/12/2005 |
| BIS | OT | ISSUED | D E ASSOC. INC. | 12/10/2004 |
| BIS | MH | ISSUED | D AND E ASSOCIATES INC | 10/29/2004 |
| BIS | OT | ISSUED | D AND E ASSOCIATES INC | 10/29/2004 |
| BIS | MH | ISSUED | D&E ASSOCIATES INC | 10/18/2004 |
| BIS | PL | ISSUED | VINCESKY MAY PLUMB HEAT LLC | 10/18/2004 |
| BIS | OT | ISSUED | D&E ASSOCIATES INC | 08/11/2004 |
| BIS | OT | ISSUED | D AND E ASSOCIATES INC | 07/30/2004 |
| BIS | MH | ISSUED | D AND E ASSOCIATES INC | 07/30/2004 |
| BIS | SP | ISSUED | ALESSANDRO PLUMBING, INC | 10/10/2003 |
| BIS | — | ISSUED | GEORGE WONG | 09/17/2003 |
| BIS | PL | RE-ISSUED | ALESSANDRO PLUMBING, INC | 09/19/2002 |
| BIS | OT | ISSUED | HELLMAN CONSTRUCTION CO | 08/05/2002 |
| BIS | OT | ISSUED | D&E ASSOCIATES INC. | 11/20/2001 |
| BIS | OT | ISSUED | D&E ASSOCIATES INC. | 11/20/2001 |
| BIS | SP | RE-ISSUED | VINCESKY MAY PLUMB HEAT LLC | 03/27/2000 |
| BIS | PL | RE-ISSUED | VINESKI MAY PLUMB HEAT | 03/15/2000 |
| BIS | OT | RE-ISSUED | D & E ASSOC. INC. | 05/27/1999 |
| BIS | EQ | ISSUED | CONTTINENTAL/AVANTI DBA CONTINE | 05/27/1999 |
| BIS | OT | ISSUED | CONTTINENTAL/AVANTI DBA CONTINE | 05/27/1999 |
| BIS | MH | RE-ISSUED | D & E ASSOC. INC. | 05/10/1999 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/09/2022 | — | — | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/18/2025 | Complete | VALLEY ELECTRIC OF NY INC | General Wiring |
| 04/26/2018 | Complete | CEDAR ELEC'L CONT'RS INC. | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/18/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/04/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/02/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/07/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/07/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/06/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/03/2025 | Post-installed Anchors | MINA HANNA | special |
| 10/23/2024 | HVAC-R and service water heating equipment | MINA HANNA | energy_progress |
| 09/26/2024 | Fire-Resistant Penetrations and Joints | MINA HANNA | special |
| 09/26/2024 | Fire-Resistance Rated Construction | MINA HANNA | progress |
| 09/24/2024 | Final | MINA HANNA | progress |
| 09/24/2024 | Sprinkler Systems | MINA HANNA | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Betances Health Center | Medical / Healthcare | — | Project M00663965 |