| Owner | Filings | Most Recent |
|---|---|---|
| J G CONSTRUCTION SRVCS | 7 | 07/08/2026 |
| SUSAN GALI 280 LINDEN LLC | 11 | 03/22/2026 |
| DERO CONTRACTING | 1 | 03/22/2026 |
| GREEN LINE DEVELOPERS LLC | 9 | 03/22/2026 |
| SHARESTATES INVESTMENTS L | 4 | 03/22/2026 |
| 280 LINDEN | 17 | 03/22/2026 |
| 280 LINDEN LLC SUSAN GALI | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/08/2025 | $1.3M | — | SHARESTATES INVESTMENTS, LLC, SERIES BC2018-001836 → 280 LINDEN BLVD LLC | $188/sf building |
| 05/11/2015 | $862K | — | BIG BROOKLYN REHAB, INC → 280 LINDEN LLC | — not available |
| 06/06/2014 | $346K | — | Private party → BIG BROOKLYN REHAB INC. | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| KCE CONSULTING ENGINEERING PLLC | 4 | 10/24/2025 |
| KMA DESIGNS LLC | 2 | 09/11/2025 |
| NIKOLAI KATZ ARCHITECT | 2 | 08/06/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| KMA DESIGNS LLC | 4 | 03/21/2026 |
| EXPRESS FILING INC | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| YAFE MEOD CORP | General Contractor | 5 | 04/09/2026 |
| J & G CONSTRUCTION SVCS | General Contractor | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CENTURY TESTING & CONSULT | 4081 | 5 | 10/24/2025 |
| MOHAMMAD AHEAD - PROFESSI | 9286 | 1 | 09/11/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Foundation | Signed-off | YAFE MEOD CORP | 03/18/2026 |
| DOB NOW | Support of Excavation | Signed-off | YAFE MEOD CORP | 03/18/2026 |
| DOB NOW | Structural | Signed-off | YAFE MEOD CORP | 03/18/2026 |
| DOB NOW | Foundation | Signed-off | YAFE MEOD CORP | 03/17/2026 |
| DOB NOW | Supported Scaffold | Signed-off | J & G CONSTRUCTION SVCS | 09/11/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | J & G CONSTRUCTION SVCS | 09/08/2025 |
| DOB NOW | Construction Fence | Permit Issued | YAFE MEOD CORP | 04/28/2025 |
| BIS | — | ISSUED | YAFE MEOD CORP | 01/06/2026 |
| BIS | PL | ISSUED | PIPE SOLUTIONS ADVIS INC | 06/16/2025 |
| BIS | — | ISSUED | YAFE MEOD CORP | 06/09/2025 |
| BIS | — | ISSUED | YAFE MEOD CORP | 05/20/2025 |
| BIS | — | ISSUED | YAFE MEOD CORP | 05/14/2025 |
| BIS | EQ | ISSUED | YAFE MEOD CORP | 05/13/2025 |
| BIS | EQ | ISSUED | YAFE MEOD CORP | 05/05/2025 |
| BIS | — | ISSUED | ARBIE CONSTRUCTION LLC | 06/12/2018 |
| BIS | EQ | ISSUED | ARBIE CONSTRUCTION LLC | 06/12/2018 |
| BIS | PL | ISSUED | ALL HOUR SEWER SERVICE CO. | 04/24/2018 |
| BIS | — | ISSUED | ARBIE CONSTRUCTION LLC | 02/02/2018 |
| BIS | PL | ISSUED | ZONE PLUMBING & HEATING C | 08/18/2017 |
| BIS | EQ | ISSUED | ARBIE CONSTRUCTION LLC | 08/18/2017 |
| BIS | — | ISSUED | ARBIE CONSTRUCTION LLC | 08/18/2017 |
| BIS | EQ | ISSUED | GREENLINE DEVELOPERS LLC | 05/05/2016 |
| BIS | — | ISSUED | GREENLINE DEVELOPERS LLC | 05/04/2016 |
| BIS | PL | ISSUED | KATAN P & H INC | 05/04/2016 |
| BIS | OT | ISSUED | GREENLINE DEVELOPERS LLC | 04/19/2016 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/24/2025 | Signed-off | YAFE MEOD CORP | Heating and Air Conditioning Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/18/2026 | Complete | POWER DIRECT ELECTRIC INC | General Wiring |
| 09/08/2025 | Complete | RICHARD NEU | — |
| 05/27/2025 | Complete | POWER DIRECT ELECTRIC INC | — |
| 04/12/2018 | Permit Issued | POWER DIRECT ELECTRIC INC | General Wiring, Lighting |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/24/2025 | Signed-off | YAFE MEOD CORP | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/24/2025 | Signed-off | YAFE MEOD CORP | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/03/2025 | Structural Steel - High Strength Bolting | FRANZ SEBORGA | special |
| 11/03/2025 | Structural Steel - Welding | FRANZ SEBORGA | special |
| 10/16/2025 | Post-installed Anchors | FRANZ SEBORGA | special |
| 10/16/2025 | Structural Cold-Formed Steel | FRANZ SEBORGA | special |
| 10/16/2025 | Structural Steel - Details | FRANZ SEBORGA | special |
| 10/16/2025 | Concrete - Cast-In-Place | FRANZ SEBORGA | special |
| 10/16/2025 | Masonry | FRANZ SEBORGA | special |
| 10/16/2025 | Post-installed Anchors | FRANZ SEBORGA | special |
| 10/16/2025 | Structural Stability – Alterations of existing buildings | FRANZ SEBORGA | special |
| 10/16/2025 | Subgrade Inspections | FRANZ SEBORGA | special |
| 10/16/2025 | Underpinning | FRANZ SEBORGA | special |
| 09/30/2025 | Final | FRANZ SEBORGA | progress |
| 09/30/2025 | Final | FRANZ SEBORGA | progress |
| 09/30/2025 | Footing and Foundation | FRANZ SEBORGA | progress |
| 09/08/2025 | Post-installed Anchors | MOHAMMAD AHEAD | special |