| Owner | Filings | Most Recent |
|---|---|---|
| CONSTRUCTION SVS CON NY | 4 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| JUN YAN, PE | 4 | 11/28/2023 |
| NMI ARCHITECTURE, PLLC | 9 | 11/13/2023 |
| KZ ENGINEERING, P.C | 1 | 11/01/2017 |
| Representative | Filings | Most Recent |
|---|---|---|
| NMI ARCHITECTURE PLLC | 26 | 03/21/2026 |
| ATLANTIC BUILDING SUPPLY INC. | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PUREFORM DESIGN/BUILD LLC | General Contractor | 9 | 03/21/2026 |
| CONSTRUCTION SVS CON NY | General Contractor | 6 | 03/21/2026 |
| PASQUALE QUARATINO INC | General Contractor | 4 | 03/21/2026 |
| NASHAT R IBRAHIM | Electrical | 4 | 03/21/2026 |
| PASQUALE QUARATINO INC | Plumbing | 3 | 07/08/2026 |
| PASQUALE QUARATINO INC | Fire Protection | 1 | 07/08/2026 |
| JOSE GERMAN | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JUN YAN, PE | 7170 | 4 | 11/28/2023 |
| NMI ARCHITECTURE, PLLC | 6825 | 12 | 11/28/2023 |
| JUST CONSULTING ENGINEERI | 5865 | 2 | 11/13/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | PASQUALE QUARATINO INC | 04/28/2023 |
| DOB NOW | Plumbing | Signed-off | PASQUALE QUARATINO INC | 04/28/2023 |
| DOB NOW | Construction Fence | Signed-off | PUREFORM DESIGN/BUILD LLC | 03/28/2023 |
| DOB NOW | Mechanical Systems | Signed-off | PUREFORM DESIGN/BUILD LLC | 03/21/2023 |
| DOB NOW | Foundation | Signed-off | PUREFORM DESIGN/BUILD LLC | 03/21/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | CONSTRUCTION SVS CON NY | 04/25/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | CONSTRUCTION SVS CON NY | 11/02/2017 |
| BIS | — | ISSUED | PUREFORM DESIGN/BUILD LLC | 02/06/2023 |
| BIS | PL | ISSUED | AMOK INC | 02/26/1993 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/28/2024 | Complete | AMPS & VOLTS ELECL CONTS | 4 meters |
| 11/14/2023 | Complete | AMPS & VOLTS ELECL CONTS | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/06/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/28/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/28/2023 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| 06/22/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/22/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/27/2023 | Structural Steel - Details | NASHAT IBRAHIM | special |
| 11/27/2023 | Structural Stability – Alterations of existing buildings | JUN YAN | special |
| 11/27/2023 | Concrete - Cast-In-Place | JUN YAN | special |
| 11/27/2023 | Footing and Foundation | JUN YAN | progress |
| 11/27/2023 | Final | JUN YAN | progress |
| 11/20/2023 | HVAC-R and service water heating system controls | NASHAT IBRAHIM | energy_progress |
| 11/20/2023 | Post-installed Anchors | XIAOJUN WANG | special |
| 11/20/2023 | HVAC-R and service water piping design and insulation | NASHAT IBRAHIM | energy_progress |
| 11/20/2023 | Fire-Resistant Penetrations and Joints | NASHAT IBRAHIM | special |
| 11/20/2023 | Sprinkler Systems | XIAOJUN WANG | special |
| 11/20/2023 | Energy Code Compliance Inspections | NASHAT IBRAHIM | progress |
| 11/20/2023 | HVAC-R and service water heating equipment | NASHAT IBRAHIM | energy_progress |
| 11/20/2023 | Permanent certificate | NASHAT IBRAHIM | energy_progress |
| 11/20/2023 | Maintenance information | NASHAT IBRAHIM | energy_progress |
| 11/15/2023 | Mechanical Systems | NASHAT IBRAHIM | special |
| 11/15/2023 | Heating Systems | NASHAT IBRAHIM | special |
| 11/15/2023 | Energy Code Compliance Inspections | NASHAT IBRAHIM | progress |
| 11/15/2023 | Fire-Resistance Rated Construction | NASHAT IBRAHIM | progress |
| 11/15/2023 | Final | NASHAT IBRAHIM | progress |
| 11/15/2023 | Fire-Resistant Penetrations and Joints | NASHAT IBRAHIM | special |
| 11/15/2023 | Maintenance information | NASHAT IBRAHIM | energy_progress |
| 11/15/2023 | HVAC-R and service water piping design and insulation | NASHAT IBRAHIM | energy_progress |
| 11/15/2023 | Shutoff dampers | NASHAT IBRAHIM | energy_progress |
| 11/15/2023 | HVAC-R and service water heating system controls | NASHAT IBRAHIM | energy_progress |
| 11/15/2023 | HVAC-R and service water heating equipment | NASHAT IBRAHIM | energy_progress |