| Owner | Filings | Most Recent |
|---|---|---|
| CITISCAPE CONSULTING LTD | 9 | 09/07/2026 |
| NADA | 39 | 07/08/2026 |
| RCM GROUP | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/26/2021 | $575K | — | KEEP GROWING LLC → NADA INC | $846/sf building |
| 11/08/2016 | $305K | — | Private party → KEEP GROWING LLC | $449/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CITISCAPE CONSULTING LTD | 15 | 08/24/2026 |
| NY BUILDING ASSOCIATES INC | 1 | 02/18/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| CITISCAPE CONSULTING LTD | 24 | 03/21/2026 |
| S R SOLAR DESIGN | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| RCM GROUP INC | General Contractor | 15 | 07/08/2026 |
| MEGA PLBG CORP | Plumbing | 4 | 07/08/2026 |
| RUSS FLAUM | Electrical | 3 | 03/21/2026 |
| TJAR GROUP CORP | General Contractor | 3 | 09/07/2026 |
| MEGA PLBG CORP | Fire Protection | 1 | 07/08/2026 |
| ANTONIO TZOUMAS | Electrical | 1 | 03/21/2026 |
| SOLAR STRING INC | General Contractor | 1 | 06/28/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AA BUILDING & INSPECTION | 1519 | 11 | 07/01/2026 |
| NKM ENGINEERING PLLC | 6244 | 1 | 02/18/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | TJAR GROUP CORP | 09/01/2026 |
| DOB NOW | Curb Cut | Signed-off | TJAR GROUP CORP | 06/15/2026 |
| DOB NOW | General Construction | Permit Issued | TJAR GROUP CORP | 05/04/2026 |
| DOB NOW | Solar | Permit Issued | SOLAR STRING INC | 03/10/2026 |
| DOB NOW | Sprinklers | Signed-off | REAL PLUMBING CORP | 12/16/2025 |
| DOB NOW | Plumbing | Signed-off | MEGA PLBG CORP | 12/15/2025 |
| DOB NOW | Construction Fence | Permit Issued | RCM GROUP INC | 11/24/2025 |
| DOB NOW | Structural | Permit Issued | RCM GROUP INC | 11/24/2025 |
| DOB NOW | General Construction | Permit Issued | RCM GROUP INC | 11/24/2025 |
| DOB NOW | General Construction | Permit Issued | RCM GROUP INC | 09/10/2025 |
| DOB NOW | Structural | Permit Issued | RCM GROUP INC | 08/12/2025 |
| DOB NOW | Construction Fence | Permit Issued | RCM GROUP INC | 08/12/2025 |
| DOB NOW | Foundation | Permit Issued | RCM GROUP INC | 08/01/2025 |
| DOB NOW | Construction Fence | Signed-off | RCM GROUP INC | 04/22/2025 |
| DOB NOW | Full Demolition | Signed-off | RCM GROUP INC | 04/09/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2026 | Signed-off | REAL PLUMBING CORP | 43 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2026 | Signed-off | MEGA PLBG CORP | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/29/2026 | Complete | KINGS ELECTRIC CO., INC. | General Wiring |
| 02/09/2026 | Complete | AMBER ELECTL CONTNG INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2026 | Permit Issued | TJAR GROUP CORP | Steel, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2026 | Permit Issued | TJAR GROUP CORP | Fence |
| 03/19/2025 | Signed-off | RCM GROUP INC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/01/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/27/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/17/2026 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 06/26/2026 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 03/31/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 03/25/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/12/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 12/24/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/01/2026 | Heating Systems | — | special |
| 07/01/2026 | Ventilation and air distribution system | — | energy_progress |
| 07/01/2026 | Permanent certificate | — | energy_progress |
| 07/01/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 07/01/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 07/01/2026 | Maintenance information | — | energy_progress |
| 07/01/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 07/01/2026 | Duct leakage testing, insulation and design | — | energy_progress |
| 05/26/2026 | Lowest Floor Elevation | — | progress |
| 05/19/2026 | Permanent certificate | Younes Abouyaala | energy_progress |
| 05/19/2026 | Air barrier - visual inspection | Younes Abouyaala | energy_progress |
| 05/19/2026 | Interior lighting power | Younes Abouyaala | energy_progress |
| 05/19/2026 | Maintenance information | Younes Abouyaala | energy_progress |
| 05/19/2026 | Fire-Resistance Rated Construction | Younes Abouyaala | progress |
| 05/19/2026 | Energy Code Compliance Inspections | Younes Abouyaala | progress |
| 05/19/2026 | Subgrade Inspections | Younes Abouyaala | special |
| 05/19/2026 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 05/19/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Younes Abouyaala | special |
| 05/19/2026 | Fenestration air leakage | Younes Abouyaala | energy_progress |
| 05/19/2026 | Fenestration and door U-factor and product ratings | Younes Abouyaala | energy_progress |
| 05/19/2026 | Electric vehicle service equipment requirements | Younes Abouyaala | energy_progress |
| 05/19/2026 | Fenestration areas | Younes Abouyaala | energy_progress |
| 05/19/2026 | Insulation placement and R values | Younes Abouyaala | energy_progress |
| 05/19/2026 | Metering | Younes Abouyaala | energy_progress |
| 05/19/2026 | Protection of exposed foundation insulation | Younes Abouyaala | energy_progress |