RoofUnder Construction39p · 5 filings · 20 docs
ArchitectureDMEquipmentFire ProtectionGeneralMechanicalPlumbingStructuralZ
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 8 drawing sheets
INSTALLATION OF TEMPORARY ROOF PROTECTION AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Latest 3 of 5 filings on this floor.
Floor 30Under Construction68p · 2 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 8 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 1 drawing sheet
Floor 29Under Construction67p · 2 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 8 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 28Under Construction65p · 2 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 6 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 27Under Construction33p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 7 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 26Under Construction33p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 7 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 25Under Construction32p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 6 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 24Under Construction32p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 6 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 23Under Construction33p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 7 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 22Under Construction32p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 6 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 21Under Construction32p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 6 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 20Under Construction32p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 6 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 19Under Construction32p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 6 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 18Under Construction32p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 6 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 17Under Construction33p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 7 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 16Under Construction32p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 6 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 15Under Construction31p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 5 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 14Under Construction31p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 5 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 13Under Construction31p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 5 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 12Under Construction31p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 5 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 11Under Construction68p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 9 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 10Under Construction67p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 8 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 9Under Construction32p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionPlumbingStructural
Issued Permit Scope
Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 6 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 8Under Construction187p · 2 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructuralZ
Issued Permit Scope
General Construction · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 10 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 1 drawing sheet
Floor 7Under Construction184p · 2 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructuralZ
Issued Permit Scope
General Construction · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 8 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 6Under Construction183p · 2 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructuralZ
Issued Permit Scope
General Construction · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 7 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 5Under Construction184p · 2 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructuralZ
Issued Permit Scope
General Construction · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 8 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 4Under Construction184p · 2 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructuralZ
Issued Permit Scope
General Construction · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 8 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 3Under Construction186p · 2 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructuralZ
Issued Permit Scope
General Construction · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 10 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 2Under Construction162p · 3 filings · 20 docs
ArchitectureDMElectricalFire ProtectionMechanicalPlumbingStructuralZ
Issued Permit Scope
General Construction · Protection and Mechanical Methods
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 11 drawing sheets
INSTALLATION OF TEMPORARY PIPE & SYSTEM SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 1Under Construction188p · 2 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 11 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 2 drawing sheets
CellarUnder Construction189p · 1 filing · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 13 drawing sheets
Sub-CellarUnder Construction186p · 1 filing · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Sprinklers · Standpipe
UNDERGROUND PLUMBING FILED IN CONJUNCTION WITH NB # B01097093-I1.
On file for this project
130 documents · 10 drawing sheets