1925Year Built
2Stories
A9Building Class
R3AZoning
2,034 sfGross Floor Area
1Units
Miscellaneous one family · 2,375 sf lot · 0.86 FAR built · Flood zone X
Locations of Work
Electrical
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofRoof mounted solar electricity generating system installatio1p · 1 filing · 11 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/29/2024$563K—Private party → Private party$277/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Trinity Solar203/12/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Aca Associates203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Trinity Solarspecialty_contractor104/09/2026
Macreddin Plumbing & HeatingPlumbing204/28/2016
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Ikra Consulting7032203/12/2026
Building Lifecycle
03/24/2026
Signed off — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
X01270962-I1
03/12/2026
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
X01270962-P1
03/12/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
MD MOSTAFA
03/12/2026
Special inspection requirement — Final
Ayracon Almaraz
03/12/2026
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
8 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offTrinity Solar08/21/2025
BISPLISSUEDMacreddin Plumbing & Heating04/28/2016
BISPLISSUEDMacreddin Plumbing & Heating09/04/2014
1 project · most recent 08/07/2025
FiledStatusContractorScope
08/07/2025CompleteRedline Electric—
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
03/12/2026Fire-Resistant Penetrations and JointsMD MOSTAFAspecial
03/12/2026FinalAyracon Almarazprogress
03/12/2026Energy Code Compliance InspectionsAyracon Almarazprogress
03/12/2026Air barrier - visual inspectionAyracon Almarazenergy_progress