1930Year Built
2Stories
B1Building Class
R4-1Zoning
1,600 sfGross Floor Area
2Units
0 Open Violations
Two family brick · Owner of record: BRONX CAPITAL A LLC · 2,533 sf lot · 0.63 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalPlumbing
Roof1 filing · 3 docs
Floor 23p · 1 filing · 20 docs
Floor 13p · 1 filing · 20 docs
Basement1p · 1 filing · 20 docs
Sub-Basement3p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BRONX CAPITAL A2207/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/26/2024$465K—Private party → BRONX CAPITAL A LLC$291/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR103/25/2026
PARIKH ARCHITECTURAL P.C.610/27/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DOUG'S PLUMBING & HEATINGGeneral Contractor807/08/2026
DOUG'S PLBG & HTG SERV COPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281103/25/2026
PARIKH ARCHITECTURAL P.C.1470610/27/2025
Building Lifecycle
All (73)Filed (7)Permit Issued (9)Signed Off (3)Violation (4)Inspection (7)Objection (16)Special Inspection (27)
04/01/2026
Permit issued — Solar
X01377623-I1-SL
03/25/2026
Filed — Alteration
Installation of solar panels, rooftop, grid tied, railed, 14 modules, 5.74 KW
X01377623-I1
02/11/2026
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
02/04/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
01/13/2026
Signed off — Alteration
Provide two gas boiler and two H.W. heaters and one floor drain in the basement. Relocate gas stoves on first and second floor. No change use, occupancy or egress.
X01133678-S2
01/13/2026
Signed off — Alteration
Provide two gas boiler and two H.W. heaters and one floor drain in the basement. Relocate gas stoves on first and second floor. No change use, occupancy or egress.
X01133678-S1
01/08/2026
Permit issued — Structural
X01133678-S2-ST
01/07/2026
Signed off — Alteration
Provide two gas boiler and two H.W. heaters and one floor drain in the basement. Relocate gas stoves on first and second floor. No change use, occupancy or egress.
X01133678-I1
12/02/2025
Permit issued — Structural
X01133678-I1-ST
11/19/2025
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
10/31/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
BINA PARIKH
10/31/2025
Special inspection requirement — HVAC-R and service water heating system controls
BINA PARIKH
10/31/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
BINA PARIKH
10/31/2025
Special inspection requirement — HVAC-R and service water heating equipment
BINA PARIKH
10/31/2025
Special inspection requirement — Permanent certificate
BINA PARIKH
10/31/2025
Special inspection requirement — Energy Code Compliance Inspections
BINA PARIKH
10/27/2025
Filed — Alteration
Provide two gas boiler and two H.W. heaters and one floor drain in the basement. Relocate gas stoves on first and second floor. No change use, occupancy or egress.
X01133678-P4
09/22/2025
Special inspection requirement — HVAC-R and service water heating system controls
BINA PARIKH
09/22/2025
Special inspection requirement — Permanent certificate
BINA PARIKH
09/22/2025
Special inspection requirement — HVAC-R and service water heating equipment
BINA PARIKH
09/22/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
BINA PARIKH
09/22/2025
Special inspection requirement — Energy Code Compliance Inspections
BINA PARIKH
09/22/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
BINA PARIKH
09/12/2025
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
08/13/2025
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
07/08/2025
Special inspection requirement — Mechanical Systems
BINA PARIKH
07/08/2025
Special inspection requirement — Final
BINA PARIKH
07/08/2025
Special inspection requirement — Structural Steel - Details
BINA PARIKH
07/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
BINA PARIKH
07/01/2025
Filed — Alteration
Provide two gas boiler and two H.W. heaters and one floor drain in the basement. Relocate gas stoves on first and second floor. No change use, occupancy or egress.
X01133678-P3
05/06/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
04/30/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/18/2025
Permit issued — Plumbing
X01133678-S3-PL
02/18/2025
Permit issued — Structural
X01133678-S2-GC
02/18/2025
Permit issued — Structural
X01133678-S2-MS
02/18/2025
Permit issued — Plumbing
X01133678-S1-PL
02/11/2025
Objection resolved — Addressed
02/11/2025
Objection resolved — Addressed
02/11/2025
Objection resolved — Addressed
02/11/2025
Objection resolved — Addressed
02/11/2025
Objection resolved — Addressed
02/11/2025
Objection resolved — Addressed
02/10/2025
Objection raised — Mechanical
02/10/2025
Objection raised — Fire_Protection
02/10/2025
Objection raised — Zoning
02/10/2025
Objection raised — Structural
02/10/2025
Objection raised — Cost
02/04/2025
Objection raised — Energy
01/31/2025
Filed — Alteration
Provide two gas boiler and two H.W. heaters and one floor drain in the basement. Relocate gas stoves on first and second floor. No change use, occupancy or egress.
X01133678-S2
01/31/2025
Filed — Alteration
Provide two gas boiler and two H.W. heaters and one floor drain in the basement. Relocate gas stoves on first and second floor. No change use, occupancy or egress.
X01133678-S3
01/29/2025
Permit issued — Mechanical Systems
X01133678-I1-MS
01/21/2025
Permit issued — Mechanical Systems
X01133678-I1-GC
12/17/2024
Objection resolved — Addressed
12/17/2024
Objection resolved — Addressed
12/10/2024
Objection raised — Fire_Protection
12/10/2024
Objection raised — Plumbing
12/07/2024
Filed — Alteration
Provide two gas boiler and two H.W. heaters and one floor drain in the basement. Relocate gas stoves on first and second floor. No change use, occupancy or egress.
X01133678-S1
11/25/2024
Special inspection requirement — Energy Code Compliance Inspections
BINA PARIKH
11/25/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
BINA PARIKH
11/20/2024
Filed — Alteration
Provide two gas boiler and two H.W. heaters and one floor drain in the basement. Relocate gas stoves on first and second floor. No change use, occupancy or egress.
X01133678-I1
Latest 60 of 73 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedMOMENTUM SOLAR04/01/2026
DOB NOWStructuralSigned-offDOUG'S PLUMBING & HEATING01/08/2026
DOB NOWStructuralSigned-offDOUG'S PLUMBING & HEATING12/02/2025
DOB NOWPlumbingPermit IssuedDOUG'S PLBG & HTG SERV CO02/18/2025
DOB NOWStructuralSigned-offDOUG'S PLUMBING & HEATING02/18/2025
DOB NOWStructuralSigned-offDOUG'S PLUMBING & HEATING02/18/2025
DOB NOWPlumbingSigned-offDOUG'S PLBG & HTG SERV CO02/18/2025
DOB NOWMechanical SystemsSigned-offDOUG'S PLUMBING & HEATING01/29/2025
DOB NOWMechanical SystemsSigned-offDOUG'S PLUMBING & HEATING01/21/2025
1 project · most recent 10/27/2025
Gas Water/Sanitary
FiledStatusContractorScope
10/27/2025Permit IssuedDOUG'S PLBG & HTG SERV COGas, Water/Sanitary
4 projects · most recent 03/25/2026
General Wiring
FiledStatusContractorScope
03/25/2026Permit IssuedISLAND ELECTRIC CORP—
08/28/2025CompleteTECHNICAL ELECTRIC CORPGeneral Wiring
07/12/2019CompleteALEF ELEC'L CONTR'G INCGeneral Wiring
04/05/2019CompleteALEF ELEC'L CONTR'G INCGeneral Wiring
1 project · most recent 10/27/2025
Steel Concrete
FiledStatusContractorScope
10/27/2025Signed-offDOUG'S PLUMBING & HEATINGSteel, Concrete
1 project · most recent 03/25/2026
FiledStatusContractorScope
03/25/2026Permit IssuedMOMENTUM SOLAR14 panels, 5.74 kw, 246 roof_area_sqft
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
02/11/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
02/04/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
11/19/2025Pass-Final PL - Up to 9 Requested FloorsPassView ↗
09/12/2025Pass-Final PL - Up to 9 Requested FloorsPassView ↗
08/13/2025Pass-Final General Construction Non-Directive 14PassView ↗
05/06/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/30/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 27
DateRequirementInspectorRole
10/31/2025Fire-Resistant Penetrations and JointsBINA PARIKHspecial
10/31/2025HVAC-R and service water heating system controlsBINA PARIKHenergy_progress
10/31/2025HVAC-R and service water piping design and insulationBINA PARIKHenergy_progress
10/31/2025HVAC-R and service water heating equipmentBINA PARIKHenergy_progress
10/31/2025Permanent certificateBINA PARIKHenergy_progress
10/31/2025Energy Code Compliance InspectionsBINA PARIKHprogress
09/22/2025HVAC-R and service water heating system controlsBINA PARIKHenergy_progress
09/22/2025Permanent certificateBINA PARIKHenergy_progress
09/22/2025HVAC-R and service water heating equipmentBINA PARIKHenergy_progress
09/22/2025Fire-Resistant Penetrations and JointsBINA PARIKHspecial
09/22/2025Energy Code Compliance InspectionsBINA PARIKHprogress
09/22/2025HVAC-R and service water piping design and insulationBINA PARIKHenergy_progress
07/08/2025Mechanical SystemsBINA PARIKHspecial
07/08/2025FinalBINA PARIKHprogress
07/08/2025Structural Steel - DetailsBINA PARIKHspecial
07/08/2025Fire-Resistant Penetrations and JointsBINA PARIKHspecial
11/25/2024Energy Code Compliance InspectionsBINA PARIKHprogress
11/25/2024Fire-Resistant Penetrations and JointsBINA PARIKHspecial
11/19/2024Fire-Resistant Penetrations and JointsBINA PARIKHspecial
11/19/2024Structural Stability – Alterations of existing buildingsBINA PARIKHspecial
11/03/2024HVAC-R and service water piping design and insulationBINA PARIKHenergy_progress
11/03/2024HVAC-R and service water heating equipmentBINA PARIKHenergy_progress
11/03/2024HVAC-R and service water heating system controlsBINA PARIKHenergy_progress
11/03/2024Permanent certificateBINA PARIKHenergy_progress
10/28/2024FinalBINA PARIKHprogress
Latest 25 of 27.
▾Documents — 48 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/20/2026X01133678-P3Request digital key ↗
08/20/2026X01133678-S3Request digital key ↗
08/20/2026X01133678-S2Request digital key ↗
Showing 3 of 7 on file for this type
▸Seals & Professional Certifications34
▸DOB NOWProgress Inspector Seal & Signature17
09/01/2026X01133678-S3Open ↗
09/01/2026X01133678-S3Open ↗
09/01/2026X01133678-S3Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature10
09/01/2026X01133678-S3Open ↗
08/28/2026X01133678-S1Open ↗
08/26/2026X01133678-P4Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/20/2026X01133678-S3Open ↗
08/20/2026X01133678-S2Open ↗
08/20/2026X01133678-S1Open ↗
Showing 3 of 7 on file for this type
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/20/2026X01133678-S3Open ↗
08/20/2026X01133678-S2Open ↗
08/20/2026X01133678-S1Open ↗
Showing 3 of 7 on file for this type