← Back
Three families
286 NICHOLS AVENUE
BROOKLYN · Cypress Hills · BIN 3092979
💬 Discuss this project
1910Year Built
2Stories
C0Building Class
R5Zoning
2,080 sfGross Floor Area
3Units
1 Open Violation ▸FDNY Report ↗
Three families · 1,750 sf lot · 1.19 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 8 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC110/08/2024
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272110/08/2024
Building Lifecycle
All (11)Filed (1)Permit Issued (1)Signed Off (1)Violation (3)Special Inspection (5)
04/07/2025
Signed off — Alteration
INSTALLATION OF SOLAR PANELS ON ROOF. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B01120682-I1
10/31/2024
Permit issued — Solar
B01120682-I1-SL
10/08/2024
Filed — Alteration
INSTALLATION OF SOLAR PANELS ON ROOF. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B01120682-I1
10/02/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
10/02/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
10/02/2024
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
10/02/2024
Special inspection requirement — Final
TOM PETERSEN
10/02/2024
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
09/24/2008
Violation issued (HPD, open)
B
04/09/1994
Violation issued (ECB, closed)
Construction
04/09/1994
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offTOM PETERSEN ARCHITECT, LLC10/31/2024
1 project · most recent 10/08/2024
FiledStatusContractorScope
10/08/2024CompleteVENTURE HOME SOLAR LLC—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
10/02/2024Fire-Resistant Penetrations and JointsWalid Abdullaspecial
10/02/2024Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
10/02/2024Energy Code Compliance InspectionsTOM PETERSENprogress
10/02/2024FinalTOM PETERSENprogress
10/02/2024Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/23/2026B01120682-I1Request digital key ↗
▸Seals & Professional Certifications5
▸DOB NOWProgress Inspector Seal & Signature2
08/27/2026B01120682-I1Open ↗
08/27/2026B01120682-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/27/2026B01120682-I1Open ↗
08/27/2026B01120682-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026B01120682-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026B01120682-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026B01120682-I1Open ↗