1960Year Built
1Stories
P5Building Class
R6Zoning
16,130 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Community center · Owner of record: LUNA PARK HOUSING CORP · 81,888 sf lot · 0.2 FAR built · Flood zone AE
Locations of Work
ArchitectureStructuralElectricalMechanicalGeneral
Site & exterior6p · 4 filings · 18 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
LUNA PARK HOUSING1603/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ELEVATED ENGINEERING, PLLC107/09/2021
PAUL PERDEK, PROF. ENG. PLLC205/20/2021
URBAN INTEGRATIONS305/18/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
A1 EXPEDITING SERVICE403/21/2026
UNITED SAFETY CONSULTANTS303/21/2026
CONSTRUCTION PERMIT SERVICES103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ANDAMIO SCAFFOLDING LLCGeneral Contractor207/08/2026
EVEREST SCAFFOLDING INCGeneral Contractor207/08/2026
AM&G WATERPROOFING LLCGeneral Contractor107/08/2026
TELCOM ENGINEERING GP INCGeneral Contractor107/08/2026
Building Lifecycle
All (32)Filed (6)Permit Issued (6)Signed Off (3)Violation (15)Inspection (1)Special Inspection (1)
02/01/2023
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
04/28/2022
Signed off — Alteration
Pipe Scaffolding installed per plans, no change in use, egress or occupancy
B00482658-I1
02/22/2022
Signed off — Alteration
INSTALLATION OF 500# CAPACITY ELECTRIC MATERIAL ONLY HOISTS DURING BLDG ALTERATION, FILED SEPARATELY. HOISTS SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
B00502810-I1
09/21/2021
Permit issued — Sidewalk Shed
B00523300-I1-SH
09/15/2021
Permit issued — Supported Scaffold
B00482658-I1-SF
07/21/2021
Signed off — Alteration
B00539075-I1
07/20/2021
Permit issued — General Construction
B00539075-I1-GC
07/09/2021
Filed — Alteration
B00539075-I1
05/20/2021
Filed — Alteration
INSTALLATION OF 500# CAPACITY ELECTRIC MATERIAL ONLY HOISTS DURING BLDG ALTERATION, FILED SEPARATELY. HOISTS SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
B00502810-P1
05/20/2021
Special inspection requirement — Final
DANNY TRUJILLO
05/18/2021
Filed — Alteration
Pipe Scaffolding installed per plans, no change in use, egress or occupancy
B00482658-P2
05/18/2021
Permit issued — Sidewalk Shed
B00523300-I1-SH
05/04/2021
Permit issued — Protection and Mechanical Methods
B00502810-I1-PM
05/03/2021
Filed — Alteration
INSTALLATION OF 500# CAPACITY ELECTRIC MATERIAL ONLY HOISTS DURING BLDG ALTERATION, FILED SEPARATELY. HOISTS SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
B00502810-I1
03/29/2021
Filed — Alteration
Pipe Scaffolding installed per plans, no change in use, egress or occupancy
B00482658-P1
03/09/2021
Permit issued — Supported Scaffold
B00482658-I1-SF
03/08/2021
Filed — Alteration
Pipe Scaffolding installed per plans, no change in use, egress or occupancy
B00482658-I1
06/28/2018
Violation issued (ECB, closed)
Construction
09/20/2017
Violation issued (ECB, closed)
Construction
02/24/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/18/2001
Violation issued (ECB, closed)
Boilers
05/04/1998
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/04/1998
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/04/1998
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/04/1998
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/04/1998
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/04/1998
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/10/1997
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/21/1995
Violation issued (ECB, closed)
Public Assembly
06/21/1991
Violation issued (ECB, closed)
Public Assembly
06/05/1990
Violation issued (ECB, closed)
Public Assembly
06/05/1990
Violation issued (ECB, closed)
Public Assembly
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedANDAMIO SCAFFOLDING LLC09/21/2021
DOB NOWSupported ScaffoldSigned-offANDAMIO SCAFFOLDING LLC09/15/2021
DOB NOWGeneral ConstructionSigned-offLINED UP CONSTRUCTION07/20/2021
DOB NOWSidewalk ShedPermit IssuedEVEREST SCAFFOLDING INC05/18/2021
DOB NOWProtection and Mechanical MethodsSigned-offAM&G WATERPROOFING LLC05/04/2021
DOB NOWSupported ScaffoldSigned-offEVEREST SCAFFOLDING INC03/09/2021
BISOTISSUEDAM&G WATERPROOFING LLC04/15/2021
BISOTISSUEDAM&G WATERPROOFING LLC03/11/2021
BISPLISSUEDCC CONTROLLED PLBG CO INC10/21/2016
BISFBISSUEDC C CONTROLLED COMBUSTION11/15/2013
BISPLISSUEDCC CONTROLLED PLBG CO INC11/15/2013
BISEQISSUEDSPRING SCAFFOLDING LLC01/10/2013
BISEQISSUEDSPRING SCAFFOLDING LLC11/08/2012
BISBLISSUEDC C CONTROLLED COMBUSTION10/01/2012
BISPLISSUEDCC CONTROLLED PLBG CO INC10/01/2012
BISOTISSUEDTRINITY TECHNOLOGIES LLC03/09/2010
BISFSISSUEDN.Y.OIL HTG ASSOC08/18/2005
BISOTISSUEDNEW YORK PLUMBING-HEATING08/11/2005
BISMHISSUEDLEONE CONSTRUCTION, INC05/20/2005
BISOTISSUEDBERLINER COMMUNICATIONS11/24/2004
BISPLISSUEDATLANTIS PLBG&HTG CORP09/07/2001
BISPLISSUEDMETROPOLITAN HEAT & POWER CO05/21/1999
BISMHISSUEDLAFATA-CORALLO PLBG & HTG INC10/28/1997
BISOTISSUEDL.S.R.CONSTRUCTION08/22/1997
BISFBISSUEDNEAL M. RUDIKOFF11/08/1995
Nothing on file for this building.
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
02/01/2023Fail-Final General Construction Non-Directive 14FailView ↗
▾Special Inspection Requirements (DOB NOW) — 1
DateRequirementInspectorRole
05/20/2021FinalDANNY TRUJILLOprogress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
SprintOffice—
Project B00539075 Alteration · LOC Issued · 07/09/2021
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 90 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
09/01/2026B00482658-P1Request digital key ↗
09/01/2026B00482658-I1Request digital key ↗
09/01/2026B00482658-P2Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits18
▸BISWORK PERMIT APPLICATION10
03/11/2021321680043Open ↗
10/21/2016320586040Open ↗
01/11/2013340024253Open ↗
Showing 3 of 10 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION5
11/03/2017321680043Open ↗
02/09/2016320586040Open ↗
11/08/2012340024253Open ↗
Showing 3 of 5 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
02/05/2016320586040Open ↗
▸BISPLACE OF ASSEMBLY1
06/24/2009320038188Open ↗
▸BISSCAFFOLD APPLICATION & PERMIT1
03/11/2021321680043Open ↗
▸Seals & Professional Certifications19
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION7
01/13/2020321680043Open ↗
11/03/2017321680043Open ↗
01/06/2017320586040Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
09/01/2026B00482658-I1Open ↗
09/01/2026B00482658-P1Open ↗
09/01/2026B00482658-P2Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
11/08/2012340024253Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
10/12/2012320586040Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
11/08/2012340024253Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
10/02/2012320586040Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
11/08/2012340024253Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
09/27/2026B00482658-I1Open ↗
▸Trade Schedules & Equipment6
▸BISSELF-CERT PLUMBING NOTICE2
07/25/2014320586040Open ↗
07/25/2014320586040Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
02/08/2016320586040Open ↗
▸BISPLUMBING - SUPPORTING DOCUMENTATION1
07/02/2016320586040Open ↗
▸BISSCHEDULE B - PLUMBING1
10/02/2012320586040Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
10/02/2012320586040Open ↗
▸Environmental & Asbestos7
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
03/11/2021321680043Open ↗
03/11/2021321680043Open ↗
10/02/2012320586040Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
02/11/2010320115576Open ↗
02/11/2010320115576Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
06/24/2009320038188Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
09/01/2026B00539075-I1Open ↗
▸Energy Compliance4
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
05/10/2022321680043Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
11/03/2017321680043Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
05/10/2022321680043Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
11/08/2012340024253Open ↗
▸Inspections & Test Reports7
▸BISTECHNICAL REPORT: RESPONSIBILITY6
05/10/2022321680043Open ↗
05/10/2022321680043Open ↗
04/25/2022321680043Open ↗
Showing 3 of 6 on file for this type
▸BISNOTIF.-PROPOSED STEAM/HOT WATER INSPECTION1
07/29/2014320586040Open ↗
▸Approvals, Objections & Sign-offs12
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST4
05/12/2022321680043Open ↗
01/06/2017320586040Open ↗
04/08/2015340024253Open ↗
Showing 3 of 4 on file for this type
▸BISADMINISTRATIVE OBJECTIONS3
10/12/2012320586040Open ↗
02/11/2010320115576Open ↗
06/24/2009320038188Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION2
04/08/2015340024253Open ↗
07/25/2014320586040Open ↗
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter2
09/01/2026B00502810-I1Open ↗
09/01/2026B00502810-P1Open ↗
▸BISFINAL1
03/11/2021321680043Open ↗
▸Cost, Insurance & Ownership7
▸BISCOST AFFIDAVIT6
05/10/2022321680043Open ↗
11/03/2017321680043Open ↗
01/06/2017320586040Open ↗
Showing 3 of 6 on file for this type
▸BISWELDERS AFFIDAVIT1
07/25/2014320586040Open ↗
▸Filing & Intake Forms3
▸BISEFILING COVER SHEET2
11/03/2017321680043Open ↗
10/02/2012320586040Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
11/08/2012340024253Open ↗
▸Other Documents1
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
01/06/2017320586040Open ↗