← Back
Predominantly retail with other uses
29-05 21 AVENUE
QUEENS · BIN 4017807
💬 Discuss this project
1931Year Built
2Stories
K4Building Class
R5BZoning
5,040 sfGross Floor Area
4Units
Rent Stabilized1 Open Violation ▸FDNY Report ↗
Predominantly retail with other uses · 3,600 sf lot · 1.4 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
THE SUSTAINABLE SPACE312/06/2019
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TEKA ENTERPRISES INCGeneral Contractor107/08/2026
L&J PLG & HTG CO OF NY INPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
WAYPOINT CONSULTING GROUP6175312/06/2019
Building Lifecycle
All (32)Filed (3)Permit Issued (2)Signed Off (2)Violation (13)Special Inspection (12)
05/06/2026
Violation issued (HPD, closed)
A
06/11/2025
Violation issued (HPD, closed)
A
04/12/2024
Violation issued (HPD, closed)
A
11/24/2023
Violation issued (HPD, closed)
I
03/27/2023
Violation issued (HPD, closed)
A
11/15/2022
Violation issued (HPD, closed)
I
03/02/2022
Violation issued (HPD, closed)
A
04/14/2021
Violation issued (HPD, closed)
A
08/31/2020
Signed off — Alteration
- Replace one toilet on existing location. - Replace and relocate one bathroom lavatory. - Install one new drinking fountain. -Install new Toilet & new bathroom lavatory on new locations
Q00205703-I1
01/22/2020
Signed off — Alteration
Installation of new HVAC equipment: 3 mini-split condenser units and 7 wall mounted, ductless air handlers as per plans filed herewith. No change in use, egress or occupancy.
Q00205704-I1
12/06/2019
Filed — Alteration
- Replace one toilet on existing location. - Replace and relocate one bathroom lavatory. - Install one new drinking fountain. -Install new Toilet & new bathroom lavatory on new locations
Q00205703-P1
12/06/2019
Special inspection requirement — Fire-Resistant Penetrations and Joints
Alejandro Molina
12/06/2019
Special inspection requirement — Fire-Resistance Rated Construction
Alejandro Molina
11/24/2019
Special inspection requirement — Fire-Resistance Rated Construction
Alejandro Molina
11/24/2019
Special inspection requirement — Fire-Resistant Penetrations and Joints
Alejandro Molina
11/07/2019
Permit issued — Plumbing
Q00205703-I1-PL
11/01/2019
Permit issued — Mechanical Systems
Q00205704-I1-MS
08/22/2019
Filed — Alteration
- Replace one toilet on existing location. - Replace and relocate one bathroom lavatory. - Install one new drinking fountain. -Install new Toilet & new bathroom lavatory on new locations
Q00205703-I1
08/20/2019
Filed — Alteration
Installation of new HVAC equipment: 3 mini-split condenser units and 7 wall mounted, ductless air handlers as per plans filed herewith. No change in use, egress or occupancy.
Q00205704-I1
08/20/2019
Special inspection requirement — HVAC insulation and sealing
Alejandro Molina
08/06/2019
Special inspection requirement — Fire-Resistance Rated Construction
Alejandro Molina
08/06/2019
Special inspection requirement — HVAC and service water heating equipment
Alejandro Molina
08/06/2019
Special inspection requirement — HVAC and service water heating system controls
Alejandro Molina
08/06/2019
Special inspection requirement — Mechanical Systems
Alejandro Molina
08/06/2019
Special inspection requirement — Fire-Resistant Penetrations and Joints
Alejandro Molina
08/06/2019
Special inspection requirement — Final
Alejandro Molina
08/06/2019
Special inspection requirement — Energy Code Compliance Inspections
Alejandro Molina
09/03/1993
Violation issued (ECB, closed)
Construction
09/01/1993
Violation issued (ECB, closed)
Construction
09/01/1993
Violation issued (ECB, closed)
Construction
06/28/1993
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/24/1990
Violation issued (DOB, open)
VP-VIOLATION UNSERVED ECB-ACTIVE
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offL&J PLG & HTG CO OF NY IN11/07/2019
DOB NOWMechanical SystemsSigned-offTEKA ENTERPRISES INC11/01/2019
BISOTISSUEDTEKA ENTERPRISES INC11/02/2019
BISPLISSUEDTHOMAS PLG & HTG INC03/07/2003
BISMHISSUEDCLASSIC ELECTRIC, INC.11/29/2001
1 project · most recent 01/15/2020
General Wiring
FiledStatusContractorScope
01/15/2020CompleteBASS ELECTRICAL CORP.General Wiring
▾Special Inspection Requirements (DOB NOW) — 12
DateRequirementInspectorRole
12/06/2019Fire-Resistant Penetrations and JointsAlejandro Molinaspecial
12/06/2019Fire-Resistance Rated ConstructionAlejandro Molinaprogress
11/24/2019Fire-Resistance Rated ConstructionAlejandro Molinaprogress
11/24/2019Fire-Resistant Penetrations and JointsAlejandro Molinaspecial
08/20/2019HVAC insulation and sealing Alejandro Molinaenergy_progress
08/06/2019Fire-Resistance Rated ConstructionAlejandro Molinaprogress
08/06/2019HVAC and service water heating equipment Alejandro Molinaenergy_progress
08/06/2019HVAC and service water heating system controls Alejandro Molinaenergy_progress
08/06/2019Mechanical SystemsAlejandro Molinaspecial
08/06/2019Fire-Resistant Penetrations and JointsAlejandro Molinaspecial
08/06/2019FinalAlejandro Molinaprogress
08/06/2019Energy Code Compliance InspectionsAlejandro Molinaprogress
▾Documents — 46 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch - Plumbing2
08/28/2026Q00205703-P1Request digital key ↗
08/28/2026Q00205703-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
08/28/2026Q00205704-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
08/13/2019440560849Open ↗
▸BISWORK PERMIT APPLICATION1
11/02/2019440560849Open ↗
▸Seals & Professional Certifications18
▸DOB NOWProgress Inspector Seal & Signature8
09/13/2026Q00205704-I1Open ↗
09/13/2026Q00205704-I1Open ↗
09/13/2026Q00205704-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/13/2026Q00205704-I1Open ↗
09/13/2026Q00205704-I1Open ↗
08/22/2026Q00205703-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/28/2026Q00205703-I1Open ↗
08/28/2026Q00205703-P1Open ↗
08/13/2026Q00205704-I1Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
03/11/2020440560849Open ↗
02/27/2020440560849Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
08/13/2019440560849Open ↗
▸Safety & Tenant Protection4
▸DOB NOWTenant Protection Plan3
08/28/2026Q00205703-P1Open ↗
08/28/2026Q00205703-I1Open ↗
08/13/2026Q00205704-I1Open ↗
▸BISTENANT PROTECTION PLAN AND NOTES1
08/13/2019440560849Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/28/2026Q00205703-I1Open ↗
08/28/2026Q00205703-P1Open ↗
08/13/2026Q00205704-I1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
08/13/2019440560849Open ↗
▸Energy Compliance3
▸BISAS-BUILT ENERGY ANALYSIS1
02/27/2020440560849Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
08/13/2019440560849Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
02/27/2020440560849Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: RESPONSIBILITY1
08/13/2019440560849Open ↗
▸Approvals, Objections & Sign-offs2
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
03/11/2020440560849Open ↗
02/27/2020440560849Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
02/27/2020440560849Open ↗
08/22/2019440560849Open ↗
08/13/2019440560849Open ↗
▸Filing & Intake Forms5
▸BISADDITIONAL INFORMATION4
10/22/2019440560849Open ↗
09/26/2019440560849Open ↗
09/12/2019440560849Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET1
08/13/2019440560849Open ↗
▸Other Documents1
▸BISECCCNYS ANALYSIS1
08/13/2019440560849Open ↗