← Back
Predominantly retail with other uses
29-09 23 AVENUE
QUEENS · BIN 4017590
💬 Discuss this project
2006Year Built
3Stories
K4Building Class
R5BZoning
10,898 sfGross Floor Area
3Units
Rent Stabilized1 Open Violation ▸
Predominantly retail with other uses · Owner of record: THESSALONIKI REALTY L · 5,187 sf lot · 2.1 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbingCivil
Floor 33p · 2 filings · 20 docs
Floor 22p · 1 filing · 20 docs
Floor 1
Cellar1p · 1 filing · 17 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
THESSALONIKI REALTY203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
A. GIANNOPOULOS ARCHITECTS PLLC.1005/16/2022
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DELPHI CONSTRUCTION CORPGeneral Contractor603/21/2026
T.N.T. PLBG & HTG, INCPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
A. GIANNOPOULOS ARCHITECT21961405/16/2022
Building Lifecycle
All (57)Filed (10)Permit Issued (4)Signed Off (4)Violation (1)Inspection (8)Special Inspection (30)
05/26/2022
Signed off — Alteration
Installation of New Balcony on 2nd. floor. No change to use, egress or occupancy.
Q00566251-I1
05/26/2022
Signed off — Alteration
Installation of New Balcony on 2nd. floor. No change to use, egress or occupancy.
Q00566251-S1
05/25/2022
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
05/24/2022
Signed off — Alteration
Installation (1) washing machine and (1) gas dryer with (1) sprinkler head on top. Relocate (2) two gas metes on osp. Replace (2) two tub with stall showers.
Q00596119-I1
05/24/2022
Signed off — Alteration
Installation of (2) gas combination boilers. No change to use, egress or occupancy
Q00596013-I1
05/23/2022
Special inspection requirement — Structural Steel - Welding
ANASTASIOS GIANNOPOULOS
05/23/2022
Special inspection requirement — Footing and Foundation
ANASTASIOS GIANNOPOULOS
05/23/2022
Special inspection requirement — Final
ANASTASIOS GIANNOPOULOS
05/23/2022
Special inspection requirement — Structural Cold-Formed Steel
ANASTASIOS GIANNOPOULOS
05/23/2022
Special inspection requirement — Structural Steel - Details
ANASTASIOS GIANNOPOULOS
05/23/2022
Special inspection requirement — Structural Steel - High Strength Bolting
ANASTASIOS GIANNOPOULOS
05/23/2022
Special inspection requirement — Concrete - Cast-In-Place
ANASTASIOS GIANNOPOULOS
05/23/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
ANASTASIOS GIANNOPOULOS
05/18/2022
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
05/16/2022
Filed — Alteration
Installation of New Balcony on 2nd. floor. No change to use, egress or occupancy.
Q00566251-P3
05/16/2022
Filed — Alteration
Installation (1) washing machine and (1) gas dryer with (1) sprinkler head on top. Relocate (2) two gas metes on osp. Replace (2) two tub with stall showers.
Q00596119-P2
05/16/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
ANASTASIOS GIANNOPOULOS
05/13/2022
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/13/2022
Special inspection requirement — Footing and Foundation
ANASTASIOS GIANNOPOULOS
05/13/2022
Special inspection requirement — Structural Steel - Details
ANASTASIOS GIANNOPOULOS
05/13/2022
Special inspection requirement — Structural Steel - High Strength Bolting
ANASTASIOS GIANNOPOULOS
05/13/2022
Special inspection requirement — Structural Steel - Welding
ANASTASIOS GIANNOPOULOS
05/13/2022
Special inspection requirement — Final
ANASTASIOS GIANNOPOULOS
05/13/2022
Special inspection requirement — Concrete - Cast-In-Place
ANASTASIOS GIANNOPOULOS
05/13/2022
Special inspection requirement — Structural Cold-Formed Steel
ANASTASIOS GIANNOPOULOS
05/13/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
ANASTASIOS GIANNOPOULOS
04/25/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
ANASTASIOS GIANNOPOULOS
04/25/2022
Special inspection requirement — Heating Systems
ANASTASIOS GIANNOPOULOS
04/25/2022
Special inspection requirement — Maintenance information
ANASTASIOS GIANNOPOULOS
04/25/2022
Special inspection requirement — HVAC-R and service water heating equipment
ANASTASIOS GIANNOPOULOS
04/25/2022
Special inspection requirement — HVAC-R and service water heating system controls
ANASTASIOS GIANNOPOULOS
04/19/2022
Filed — Alteration
Installation of (2) gas combination boilers. No change to use, egress or occupancy
Q00596013-P1
04/19/2022
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
04/19/2022
Special inspection requirement — Heating Systems
ANASTASIOS GIANNOPOULOS
04/19/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
ANASTASIOS GIANNOPOULOS
04/19/2022
Special inspection requirement — HVAC-R and service water heating equipment
ANASTASIOS GIANNOPOULOS
04/19/2022
Special inspection requirement — Maintenance information
ANASTASIOS GIANNOPOULOS
04/19/2022
Special inspection requirement — HVAC-R and service water heating system controls
ANASTASIOS GIANNOPOULOS
04/05/2022
Permit issued — Boiler Equipment
Q00596013-I1-BE
03/29/2022
Special inspection requirement — Fire-Resistance Rated Construction
ANASTASIOS GIANNOPOULOS
03/29/2022
Special inspection requirement — Mechanical Systems
ANASTASIOS GIANNOPOULOS
03/29/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
ANASTASIOS GIANNOPOULOS
03/25/2022
Filed — Alteration
Installation of New Balcony on 2nd. floor. No change to use, egress or occupancy.
Q00566251-P2
03/02/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/17/2022
Filed — Alteration
Installation (1) washing machine and (1) gas dryer with (1) sprinkler head on top. Relocate (2) two gas metes on osp. Replace (2) two tub with stall showers.
Q00596119-P1
01/03/2022
Filed — Alteration
Installation of (2) gas combination boilers. No change to use, egress or occupancy
Q00596013-I1
12/03/2021
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
12/03/2021
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
12/03/2021
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
11/08/2021
Permit issued — Plumbing
Q00596119-I1-PL
10/27/2021
Filed — Alteration
Installation (1) washing machine and (1) gas dryer with (1) sprinkler head on top. Relocate (2) two gas metes on osp. Replace (2) two tub with stall showers.
Q00596119-I1
10/15/2021
Permit issued — Structural
Q00566251-S1-GC-CX
09/30/2021
Filed — Alteration
Installation of New Balcony on 2nd. floor. No change to use, egress or occupancy.
Q00566251-P1
09/24/2021
Permit issued — General Construction
Q00566251-I1-GC-CX
09/16/2021
Filed — Alteration
Installation of New Balcony on 2nd. floor. No change to use, egress or occupancy.
Q00566251-S1
08/02/2021
Filed — Alteration
Installation of New Balcony on 2nd. floor. No change to use, egress or occupancy.
Q00566251-I1
07/25/2003
Violation issued (HPD, open)
B
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWBoiler EquipmentSigned-offT.N.T. PLBG & HTG, INC04/05/2022
DOB NOWPlumbingSigned-offT.N.T. PLBG & HTG, INC11/08/2021
DOB NOWStructuralSigned-offDELPHI CONSTRUCTION CORP10/15/2021
DOB NOWGeneral ConstructionSigned-offDELPHI CONSTRUCTION CORP09/24/2021
1 project · most recent 09/30/2021
General Wiring
FiledStatusContractorScope
09/30/2021CompleteBRANDL ELECTRIC INC.General Wiring
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
05/25/2022Pass-Final General Construction Non-Directive 14PassView ↗
05/18/2022Fail-Final General Construction Non-Directive 14FailView ↗
05/13/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/19/2022Pass-Final Boiler Equipment InspectionPassView ↗
03/02/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/03/2021Certified Gas-Gas-Piping-RoughingCertifiedView ↗
12/03/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/03/2021Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 54
DateRequirementInspectorRole
05/23/2022Structural Steel - WeldingANASTASIOS GIANNOPOULOSspecial
05/23/2022Footing and FoundationANASTASIOS GIANNOPOULOSprogress
05/23/2022FinalANASTASIOS GIANNOPOULOSprogress
05/23/2022Structural Cold-Formed SteelANASTASIOS GIANNOPOULOSspecial
05/23/2022Structural Steel - DetailsANASTASIOS GIANNOPOULOSspecial
05/23/2022Structural Steel - High Strength BoltingANASTASIOS GIANNOPOULOSspecial
05/23/2022Concrete - Cast-In-PlaceANASTASIOS GIANNOPOULOSspecial
05/23/2022Structural Stability – Alterations of existing buildingsANASTASIOS GIANNOPOULOSspecial
05/16/2022Fire-Resistant Penetrations and JointsANASTASIOS GIANNOPOULOSspecial
05/13/2022Footing and FoundationANASTASIOS GIANNOPOULOSprogress
05/13/2022Structural Steel - DetailsANASTASIOS GIANNOPOULOSspecial
05/13/2022Structural Steel - High Strength BoltingANASTASIOS GIANNOPOULOSspecial
05/13/2022Structural Steel - WeldingANASTASIOS GIANNOPOULOSspecial
05/13/2022FinalANASTASIOS GIANNOPOULOSprogress
05/13/2022Concrete - Cast-In-PlaceANASTASIOS GIANNOPOULOSspecial
05/13/2022Structural Cold-Formed SteelANASTASIOS GIANNOPOULOSspecial
05/13/2022Structural Stability – Alterations of existing buildingsANASTASIOS GIANNOPOULOSspecial
04/25/2022Fire-Resistant Penetrations and JointsANASTASIOS GIANNOPOULOSspecial
04/25/2022Heating SystemsANASTASIOS GIANNOPOULOSspecial
04/25/2022Maintenance informationANASTASIOS GIANNOPOULOSenergy_progress
04/25/2022HVAC-R and service water heating equipmentANASTASIOS GIANNOPOULOSenergy_progress
04/25/2022HVAC-R and service water heating system controlsANASTASIOS GIANNOPOULOSenergy_progress
04/19/2022Heating SystemsANASTASIOS GIANNOPOULOSspecial
04/19/2022Fire-Resistant Penetrations and JointsANASTASIOS GIANNOPOULOSspecial
04/19/2022HVAC-R and service water heating equipmentANASTASIOS GIANNOPOULOSenergy_progress
Latest 25 of 54.
▾Documents — 96 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch10
08/26/2026Q00596013-I1Request digital key ↗
08/26/2026Q00596013-P1Request digital key ↗
08/26/2026Q00566251-P3Request digital key ↗
Showing 3 of 10 on file for this type
▸Applications & Permits4
▸BISPLAN / WORK APPROVAL APPLICATION3
03/07/2016410101615Open ↗
06/12/2009410101615Open ↗
05/09/2008410101615Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
10/11/2013410101615Open ↗
▸Seals & Professional Certifications64
▸DOB NOWSpecial Inspector Seal & Signature30
09/23/2026Q00596013-I1Open ↗
09/23/2026Q00596013-I1Open ↗
09/01/2026Q00596013-P1Open ↗
Showing 3 of 30 on file for this type
▸DOB NOWProgress Inspector Seal & Signature24
09/23/2026Q00596013-I1Open ↗
09/23/2026Q00596013-I1Open ↗
09/23/2026Q00596013-I1Open ↗
Showing 3 of 24 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature10
08/26/2026Q00596013-I1Open ↗
08/26/2026Q00566251-P3Open ↗
08/26/2026Q00566251-P2Open ↗
Showing 3 of 10 on file for this type
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/26/2026Q00596013-I1Open ↗
08/26/2026Q00566251-I1Open ↗
08/26/2026Q00566251-P2Open ↗
Showing 3 of 7 on file for this type
▸Energy Compliance2
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026Q00596013-I1Open ↗
08/13/2026Q00566251-I1Open ↗
▸Approvals, Objections & Sign-offs5
▸BISSCHEDULE A - OCCUPANCY / USE3
03/07/2016410101615Open ↗
06/12/2009410101615Open ↗
04/23/2008410101615Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
04/20/2016410101615Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
04/21/2008410101615Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT1
10/11/2013410101615Open ↗
▸BISDEPT OF FINANCE VERIFICATION1
03/04/2016410101615Open ↗
▸Filing & Intake Forms1
▸BISADDITIONAL INFORMATION1
10/11/2013410101615Open ↗
▸Other Documents1
▸DOB NOWPARTIAL DEMO: 10-DAY Notice1
08/13/2026Q00566251-S1Open ↗