| Firm | Filings | Most Recent |
|---|---|---|
| Momentum Solar | 3 | 09/01/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MXV Sia | 9281 | 3 | 09/01/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Permit Issued | Momentum Solar | 05/20/2026 |
| DOB NOW | Solar | Signed-off | Momentum Solar | 01/10/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/11/2026 | Complete | Island Electric | — |
| 01/08/2025 | Complete | Island Electric | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/01/2026 | Permit Issued | Momentum Solar | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/01/2026 | Air barrier - visual inspection | Mina Makar | energy_progress |
| 09/01/2026 | Adhesive-Based Solar Pedestal Bonding Systems | Mina Makar | special |
| 09/01/2026 | Fire-Resistant Penetrations and Joints | Mina Makar | special |
| 09/01/2026 | Structural Stability – Alterations of existing buildings | Mina Makar | special |
| 09/01/2026 | Energy Code Compliance Inspections | Mina Makar | progress |
| 09/01/2026 | Final | Mina Makar | progress |
| 01/08/2025 | Structural Stability – Alterations of existing buildings | Mina Makar | special |
| 01/08/2025 | Energy Code Compliance Inspections | Mina Makar | progress |
| 01/08/2025 | Final | Mina Makar | progress |
| 01/08/2025 | Air barrier - visual inspection | Mina Makar | energy_progress |
| 01/08/2025 | Fire-Resistant Penetrations and Joints | Mina Makar | special |