← Back
BuildNYC
One family attached or semi-detached
2932 HOLLAND AVENUE
BRONX · BIN 2054854
💬 Discuss this project
1935Year Built
2Stories
A5Building Class
R6Zoning
2,695 sfGross Floor Area
1Units
Rent Stabilized7 Active Violations ▸
One family attached or semi-detached · Owner of record: 2932 Holland · 5,217 sf lot · 0.52 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingFire ProtectionGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 3Unit 3B, Unit 3C55p · 1 filing · 20 docs
Floor 2Unit 2B, Unit 2C54p · 1 filing · 20 docs
Floor 1Unit 1, Unit 1A, Unit 1B57p · 1 filing · 20 docs
Site & exterior16p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Group USA Inc Builders303/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/06/2024$830K—UNIQUE OPPORTUNITY USA, INC → 2932 HOLLAND LLC$308/sf building
06/16/2016$235K—Private party → HMS CONSTRUCTION & MANAGEMENT GROUP INC.$87/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Vasilios Artemiou PE508/12/2025
Nikolai Katz Architect202/06/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Express Filing1403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
B&B Mechanical Plumbing & HeatingPlumbing407/08/2026
True Power Electrical ContElectrical203/21/2026
Builders Group USAGeneral Contractor204/09/2026
Target Piping NYFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF Services5616708/12/2025
Building Lifecycle
10/16/2025
Permit expired, never signed off — General Construction
The city's record still shows this permit as issued, with no sign-off on its filing
X01036882-I1-GC
08/29/2025
Signed off — Alteration CO
PLUMBING AND SPRINKLER SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #X01036882-I1
X01036882-S2
08/12/2025
Filed — Alteration CO
PLUMBING AND SPRINKLER SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #X01036882-I1
X01036882-P4
08/07/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
08/07/2025
Special inspection requirement — Sprinkler Systems
FAHAD FATEH
112 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersSigned-offTarget Piping NY11/19/2024
DOB NOWPlumbingSigned-offTarget Piping NY11/14/2024
DOB NOWMechanical SystemsSigned-offBuilders Group USA11/13/2024
DOB NOWGeneral ConstructionPermit IssuedBuilders Group USA10/16/2024
BISOTISSUEDArc HI Tect Associate11/06/2019
BISOTISSUEDAbied Construction06/19/2017
BISPLISSUEDL.L.G. Plumbing & Heating06/07/2017
BISOTISSUEDAbied Construction11/10/2016
1 project · most recent 08/12/2025
Heating and Air Conditioning Systems
FiledStatusContractorScope
08/12/2025Signed-offBuilders Group USAHeating and Air Conditioning Systems
1 project · most recent 08/12/2025
Sprinkler System
FiledStatusContractorScope
08/12/2025Signed-offTarget Piping NYSprinkler System
1 project · most recent 08/12/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
08/12/2025Signed-offTarget Piping NYGas, Storm, Water/Sanitary
2 projects · most recent 05/21/2025
General Wiring
FiledStatusContractorScope
05/21/2025CompleteTrue Power Electrical ContGeneral Wiring
02/26/2025CompleteTrue Power Electrical ContGeneral Wiring
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
03/05/2025Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
03/05/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/25/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
02/20/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/11/2025Pass-Final CND-Occupancy InspectionPassView ↗
01/14/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/26/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/29/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 41
DateRequirementInspectorRole
08/07/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
08/07/2025Sprinkler SystemsFAHAD FATEHspecial
08/07/2025Post-installed AnchorsFAHAD FATEHspecial
02/11/2025Fenestration air leakageFAHAD FATEHenergy_progress
02/11/2025Fenestration areasFAHAD FATEHenergy_progress
02/11/2025Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
02/11/2025MeteringFAHAD FATEHenergy_progress
02/11/2025Air barrier - visual inspectionFAHAD FATEHenergy_progress
02/11/2025Insulation placement and R valuesFAHAD FATEHenergy_progress
02/11/2025Electric vehicle service equipment requirementsFAHAD FATEHenergy_progress
02/11/2025Permanent certificateFAHAD FATEHenergy_progress
02/11/2025Maintenance informationFAHAD FATEHenergy_progress
02/11/2025Interior lighting powerFAHAD FATEHenergy_progress
02/11/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
02/11/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
02/11/2025Fire-Resistance Rated ConstructionFAHAD FATEHprogress
01/23/2025Post-installed AnchorsFAHAD FATEHspecial
01/23/2025Sprinkler SystemsFAHAD FATEHspecial
01/23/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
01/17/2025Ventilation and air distribution systemFAHAD FATEHenergy_progress
01/17/2025Mechanical SystemsFAHAD FATEHspecial
01/17/2025Post-installed AnchorsFAHAD FATEHspecial
01/17/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
01/17/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
01/17/2025FinalFAHAD FATEHprogress
Latest 25 of 41.