| Owner | Filings | Most Recent |
|---|---|---|
| 295 7TH AVENUE REAL ESTATE | 8 | 07/08/2026 |
| CHURA GROUP | 20 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| NEW YORK ENGINEERS LLC | 6 | 08/01/2025 |
| FM ENGINEERING, P.C. | 1 | 02/28/2025 |
| MURDOCH ENGINEERING | 1 | 01/16/2025 |
| SCOTT LASKY ARCHITECT | 1 | 07/30/2024 |
| DANIEL O'CONNOR ARCHITECTS | 1 | 12/09/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| EC BUILDING CONSULTANTS | 14 | 03/21/2026 |
| HWL ENGINEERING | 2 | 03/21/2026 |
| SEAY-YARBROUGH | 2 | 03/21/2026 |
| UNIVERSAL SIGNS SERVICE | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JPF CONSTRUCTION SERVICES | General Contractor | 6 | 03/21/2026 |
| ZL BUILDING ASSOCIATE INC | General Contractor | 3 | 03/21/2026 |
| MOTTES, STEVE | Electrical | 2 | 03/21/2026 |
| SANDHA GENERAL CONTRACTIN | Electrical | 2 | 03/21/2026 |
| WHITESTONE PLUMBING CORP | Plumbing | 2 | 07/08/2026 |
| SUK KIM | Electrical | 1 | 03/21/2026 |
| PINNACLE PLBG & HTG CORP | Plumbing | 1 | 07/08/2026 |
| UNIVERSAL SIGNS SVC | Scaffold | 1 | 07/08/2026 |
| ?SUK YOUNG KIM | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| G ENGINEERING PC | 7778 | 2 | 02/24/2025 |
| DANIEL O'CONNOR ARCHITECT | 1730 | 1 | 12/09/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | ZL BUILDING ASSOCIATE INC | 03/04/2025 |
| DOB NOW | Sign | Signed-off | UNIVERSAL SIGNS & SVC INC | 01/16/2025 |
| DOB NOW | Plumbing | Permit Issued | PINNACLE PLBG & HTG CORP | 09/19/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | JPF CONSTRUCTION SERVICES | 08/23/2024 |
| DOB NOW | General Construction | Permit Issued | JPF CONSTRUCTION SERVICES | 08/23/2024 |
| DOB NOW | Plumbing | Permit Issued | WHITESTONE PLUMBING CORP | 01/14/2021 |
| DOB NOW | Plumbing | Permit Issued | WHITESTONE PLUMBING CORP | 12/18/2020 |
| BIS | FP | ISSUED | UNIQUE FIRE SYSTEMS INC | 03/12/2019 |
| BIS | PL | ISSUED | PREMIER PIPE SOLUTIONS | 01/17/2019 |
| BIS | OT | ISSUED | KCC D+B, LLC | 12/19/2018 |
| BIS | OT | ISSUED | GRT CONSTRUCTION CORP | 08/31/2018 |
| BIS | PL | ISSUED | SIDERIS PLBG & HTG CORP | 06/28/2017 |
| BIS | FP | ISSUED | FIRE ZONE VENT & SUPP INC | 06/01/2011 |
| BIS | PL | ISSUED | JAY ELL P & H CO INC | 03/28/2011 |
| BIS | EQ | ISSUED | NEW FASHION CONSTRUCTION | 03/17/2011 |
| BIS | MH | ISSUED | NEW FASHION CONSTRUCTION | 03/17/2011 |
| BIS | MH | ISSUED | NOVA PLBG AND HTG INC | 04/10/2003 |
| BIS | PL | ISSUED | AVON PLBG & HTG INC | 04/10/2003 |
| BIS | OT | ISSUED | OUTFRONT MEDIA SIGN ERECT | 02/01/2001 |
| BIS | — | ISSUED | OUTFRONT MEDIA SIGN ERECT | 09/18/2000 |
| BIS | OT | ISSUED | OUTFRONT MEDIA SIGN ERECT | 08/04/2000 |
| BIS | OT | ISSUED | GAE SUNG SIGN CORP. | 06/19/2000 |
| BIS | PL | ISSUED | MAINLAND PLG | 02/11/1999 |
| BIS | OT | ISSUED | EAST SUN CORP | 01/20/1999 |
| BIS | EQ | ISSUED | EAST SUN CORP | 01/20/1999 |
| BIS | MH | ISSUED | TIGER AIR CONDITIONING INC | 07/22/1994 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/01/2025 | Permit Issued | JPF CONSTRUCTION SERVICES | Air Conditioning Systems, Heating Systems | Cooling Trane 4TTR3018N1 1 tons · Condensing Unit ×2 4TTR4036N1 3 tons · Condensing Unit ×2 4TTR4048N1 4 tons · Condensing Unit ×2 4TXCB003DS3+S8X1B040M2PSC 1 tons · Ahu ×2 4TXCB004DS3+S8X1A040M3PSC 3 tons · Ahu ×2 4TXCB006DS3+S8X1B060M4PSC 4 tons · Ahu ×2 Heating Econ-Air EA1-D.500-15D 1,584 CFM · Makeup Air ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/01/2025 | Permit Issued | PINNACLE PLBG & HTG CORP | Gas, Water/Sanitary |
| 12/09/2020 | Permit Issued | WHITESTONE PLUMBING CORP | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/29/2025 | Complete | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| 09/19/2024 | Permit Issued | POWER SURGE ELECTRIC, INC | General Wiring |
| 04/23/2019 | Permit Issued | ASCUATECH ELECTRICAL CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/22/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/17/2026 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 11/25/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/19/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/14/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 02/14/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/14/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/25/2025 | HVAC-R and service water heating equipment | XIONGCAI GU | energy_progress |
| 02/25/2025 | HVAC-R and service water heating system controls | XIONGCAI GU | energy_progress |
| 02/25/2025 | HVAC-R and service water piping design and insulation | XIONGCAI GU | energy_progress |
| 02/25/2025 | Mechanical Systems | XIONGCAI GU | special |
| 02/25/2025 | Fire-Resistant Penetrations and Joints | XIONGCAI GU | special |
| 02/25/2025 | Post-installed Anchors | XIONGCAI GU | special |
| 02/25/2025 | Final | XIONGCAI GU | progress |
| 02/25/2025 | Energy Code Compliance Inspections | XIONGCAI GU | progress |
| 02/24/2025 | Final | WANLONG HE | progress |
| 02/19/2025 | HVAC-R and service water heating equipment | XIONGCAI GU | energy_progress |
| 02/19/2025 | Fire-Resistant Penetrations and Joints | XIONGCAI GU | special |
| 02/19/2025 | Mechanical Systems | XIONGCAI GU | special |
| 02/19/2025 | Post-installed Anchors | XIONGCAI GU | special |
| 02/19/2025 | Energy Code Compliance Inspections | XIONGCAI GU | progress |
| 02/19/2025 | Final | XIONGCAI GU | progress |
| 02/19/2025 | HVAC-R and service water piping design and insulation | XIONGCAI GU | energy_progress |
| 02/19/2025 | HVAC-R and service water heating system controls | XIONGCAI GU | energy_progress |
| 07/18/2024 | Interior lighting power | XIONGCAI GU | energy_progress |
| 07/18/2024 | Lighting controls | XIONGCAI GU | energy_progress |
| 07/18/2024 | Energy Code Compliance Inspections | XIONGCAI GU | progress |
| 07/10/2024 | Final | XIONGCAI GU | progress |