| Owner | Filings | Most Recent |
|---|---|---|
| Brickstone Group | 8 | 10/20/2026 |
| Mount Pisgah Baptist Church | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/07/2026 | $1.4M | — | MOUNT PISGAH BAPTIST CHURCH → JET BRICKS LLC | $636/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CQ&J | 4 | 10/15/2026 |
| McHenery Testing Lab | 1 | 07/23/2026 |
| Thomas C Tung P.E | 1 | 06/27/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| WM Arch | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Morell Builders | General Contractor | 3 | 10/20/2026 |
| Empire City Construction | Scaffold | 2 | 09/13/2026 |
| Plumbing P & H | Plumbing | 1 | 07/28/2026 |
| Vip Fire Sprinkler | Fire Protection | 1 | 07/14/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Simon | 7555 | 1 | 06/17/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | Morell Builders | 10/19/2026 |
| DOB NOW | Structural | Permit Issued | Morell Builders | 10/13/2026 |
| DOB NOW | Supported Scaffold | Signed-off | Empire City Construction | 09/11/2026 |
| DOB NOW | Plumbing | Permit Issued | Plumbing P & H | 07/27/2026 |
| DOB NOW | Supported Scaffold | Signed-off | Empire City Construction | 07/23/2026 |
| DOB NOW | Sprinklers | Permit Issued | Vip Fire Sprinkler | 07/13/2026 |
| DOB NOW | General Construction | Permit Issued | Morell Builders | 05/07/2026 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/15/2026 | Permit Issued | Morell Builders | Heating and Air Conditioning Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/15/2026 | Permit Issued | Vip Fire Sprinkler | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/15/2026 | Permit Issued | Plumbing P & H | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/25/2026 | Permit Issued | Solar Pro Electric | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/15/2026 | Permit Issued | Morell Builders | Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/23/2026 | Signed-off | Empire City Construction | Scaffold |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/30/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/09/2026 | Maintenance information | CALVIN TRAN | energy_progress |
| 10/09/2026 | HVAC-R and service water heating system controls | CALVIN TRAN | energy_progress |
| 10/09/2026 | HVAC-R and service water piping design and insulation | CALVIN TRAN | energy_progress |
| 10/09/2026 | Shutoff dampers | CALVIN TRAN | energy_progress |
| 10/09/2026 | HVAC-R and service water heating equipment | CALVIN TRAN | energy_progress |
| 10/09/2026 | Energy Code Compliance Inspections | CALVIN TRAN | progress |
| 10/09/2026 | Duct leakage testing, insulation and design | CALVIN TRAN | energy_progress |
| 10/07/2026 | Final | CALVIN TRAN | progress |
| 10/07/2026 | Mechanical Systems | THOMAS TUNG | special |
| 07/27/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 07/27/2026 | Permanent certificate | — | energy_progress |
| 07/27/2026 | Exterior lighting power | — | energy_progress |
| 07/27/2026 | Lighting in dwelling units | — | energy_progress |
| 07/27/2026 | Fenestration areas | — | energy_progress |
| 07/27/2026 | Fenestration air leakage | — | energy_progress |
| 07/27/2026 | Insulation placement and R values | — | energy_progress |
| 07/27/2026 | Maintenance information | — | energy_progress |
| 07/27/2026 | Metering | — | energy_progress |
| 07/27/2026 | Lighting controls | — | energy_progress |
| 07/27/2026 | Interior lighting power | — | energy_progress |
| 07/27/2026 | Air barrier - visual inspection | — | energy_progress |
| 06/24/2026 | HVAC-R and service water heating equipment | CALVIN TRAN | energy_progress |
| 06/24/2026 | Energy Code Compliance Inspections | CALVIN TRAN | progress |
| 06/24/2026 | HVAC-R and service water piping design and insulation | CALVIN TRAN | energy_progress |
| 06/24/2026 | HVAC-R and service water heating system controls | CALVIN TRAN | energy_progress |