← Back
BuildNYC
Office with commercial, 7-19 stories
298 5TH AVENUE
MANHATTAN · BIN 1015791
💬 Discuss this project
1913Year Built
7Stories
O6Building Class
C5-2Zoning
24,192 sfGross Floor Area
8Units
0 Active ViolationsFISP: SAFE
Office with commercial, 7-19 stories · Owner of record: 298 Fifth Ave · 4,100 sf lot · 5.9 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofRobert Chicken9p · 1 filing · 16 docs
Floor 7Robert Chicken11p · 1 filing · 16 docs
Floor 6Robert Chicken8p · 1 filing · 16 docs
Floor 5Robert Chicken14p · 2 filings · 20 docs
Floor 4Robert Chicken14p · 2 filings · 20 docs
Floor 3Robert Chicken27p · 3 filings · 20 docs
Floor 2Robert Chicken26p · 3 filings · 20 docs
Floor 1Robert Chicken33p · 4 filings · 20 docs
CellarRobert Chicken26p · 3 filings · 20 docs
Site & exteriorSidewalk shed installation10p · 1 filing · 7 docs
Filed — no permit issuedRobert Chicken45p · 3 filings · 12 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
HRC7007/08/2026
156 Fifth Avenue203/21/2026
298 5 AVE203/21/2026
298 Fifth Ave103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MJ Expeditng Service2003/21/2026
Municipal Building Consultants303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JW ContractorGeneral Contractor603/21/2026
Soho ContractingScaffold403/21/2026
CK Plumbing & MechanicalPlumbing307/08/2026
Cardone Concretespecialty_contractor203/21/2026
David Turner ArchitectGeneral Contractor203/21/2026
RPJ ElectricElectrical103/21/2026
Avon Plumbing & HeatingFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Sead Engineering2665506/25/2024
David Turner Architect3829203/03/2023
Building Lifecycle
All (130)Filed (19)Permit Issued (10)Signed Off (3)Facade (FISP) (12)Violation (38)Inspection (4)Objection (14)Special Inspection (30)
12/18/2025
Objection raised — Scope
12/18/2025
Objection resolved — Addressed
12/18/2025
Special inspection requirement — Interior lighting power
12/18/2025
Special inspection requirement — Energy Code Compliance Inspections
12/18/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
12/18/2025
Special inspection requirement — Lighting controls
12/18/2025
Special inspection requirement — Fire-Resistance Rated Construction
12/18/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
12/18/2025
Special inspection requirement — Maintenance information
12/12/2025
Filed — Alteration CO
HEREWITH FILE TO AMEND CERTIFICATE OF OCCUPANCY TO CONVERT FIRST AND SECOND FLOOR TO EATING AND DRINKIRING (A2) ESTABLISHMENT.
M00897413-P2
09/22/2025
Special inspection requirement — Interior lighting power
09/22/2025
Special inspection requirement — Lighting controls
09/22/2025
Special inspection requirement — Maintenance information
09/22/2025
Special inspection requirement — Fire-Resistance Rated Construction
09/22/2025
Special inspection requirement — Energy Code Compliance Inspections
09/22/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
09/22/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
07/31/2025
Special inspection requirement — Public Assembly Emergency Lighting
JAEJUN RYU
07/21/2025
Filed — No Work
M01101740-P1
07/21/2025
Filed — Alteration CO
HEREWITH FILE TO AMEND CERTIFICATE OF OCCUPANCY TO CONVERT FIRST AND SECOND FLOOR TO EATING AND DRINKIRING (A2) ESTABLISHMENT.
M00897413-P1
06/13/2025
Special inspection requirement — Public Assembly Emergency Lighting
JAEJUN RYU
02/11/2025
Objection resolved — Addressed
01/28/2025
Objection raised — Energy
01/14/2025
Objection resolved — Addressed
12/13/2024
Objection raised — Scope
12/02/2024
Objection resolved — Addressed
12/02/2024
Objection resolved — Addressed
12/02/2024
Objection resolved — Addressed
12/02/2024
Objection resolved — Addressed
11/23/2024
Filed — Alteration
INSTALLATION OF A NON-ILLUMINATED BUSINESS ACCESSORY SIGN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01132222-I1
10/24/2024
Filed — No Work
M01101740-I1
08/11/2024
Filed — Alteration
M01078524-I1
06/26/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
INHWAN CHANG
06/26/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
INHWAN CHANG
06/26/2024
Special inspection requirement — Energy Code Compliance Inspections
JAEJUN RYU
06/26/2024
Special inspection requirement — Final
JAEJUN RYU
06/26/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
06/26/2024
Special inspection requirement — Maintenance information
JAEJUN RYU
06/26/2024
Special inspection requirement — HVAC-R and service water heating equipment
JAEJUN RYU
06/26/2024
Special inspection requirement — Lighting controls
JAEJUN RYU
06/26/2024
Special inspection requirement — HVAC-R and service water heating system controls
JAEJUN RYU
06/26/2024
Special inspection requirement — Interior lighting power
JAEJUN RYU
06/26/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
INHWAN CHANG
06/26/2024
Special inspection requirement — Energy Code Compliance Inspections
JAEJUN RYU
06/26/2024
Special inspection requirement — HVAC-R and service water heating system controls
JAEJUN RYU
06/26/2024
Special inspection requirement — HVAC-R and service water heating equipment
JAEJUN RYU
06/25/2024
Filed — Alteration
HEREWITH FILE PLANS FOR INTERIOR RENOVATION OF EXISTING COMMERCIAL SPACE. NEW PLUMBING FIXTURES FOR CELLAR TO 3RD FLOOR AND MODIFY/NEW SPRINKLER HEADS FOR CELLAR, 001 &002 FLOORS ONLY. INTERIOR WORK FILE SEPARATELY. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
M00824148-P2
06/25/2024
Filed — Alteration
HEREWITH FILE PLANS FOR INTERIOR RENOVATION OF AN EXISTING COMMERCIAL STORE. NEW RESTAURANT TO BE ESTABLISHED. NON-LOAD BEARING PARTITIONS, NEW FINISHES, NEW MECH HVAC AND DUCT WORK ASSOCIATED WITH NEW RESTAURANT. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
M00825355-P1
05/09/2024
Permit issued — Plumbing
M00824148-I1-PL
12/21/2023
Permit issued — Mechanical Systems
M00825355-I1-GC-CX
12/19/2023
Permit issued — Plumbing
M00824148-I1-PL
11/16/2023
Permit issued — Plumbing
M00824148-I1-EW-SP
10/25/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/25/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
10/16/2023
Filed — Alteration
HEREWITH FILE PLANS FOR INTERIOR RENOVATION OF EXISTING COMMERCIAL SPACE. NEW PLUMBING FIXTURES FOR CELLAR TO 3RD FLOOR AND MODIFY/NEW SPRINKLER HEADS FOR CELLAR, 001 &002 FLOORS ONLY. INTERIOR WORK FILE SEPARATELY. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
M00824148-P1
08/21/2023
Signed off — Alteration
New Handicap Access Ramp
M00849378-I1
08/18/2023
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
07/26/2023
Objection raised — Admin
07/26/2023
Objection raised — Fire_Protection
07/26/2023
Objection raised — Structural
Latest 60 of 130 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedCK Plumbing & Mechanical05/09/2024
DOB NOWMechanical SystemsPermit IssuedJW Contractor12/21/2023
DOB NOWPlumbingPermit IssuedCK Plumbing & Mechanical12/19/2023
DOB NOWSprinklersPermit IssuedAvon Plumbing & Heating11/16/2023
DOB NOWGeneral ConstructionSigned-offCardone Concrete04/25/2023
DOB NOWMechanical SystemsPermit IssuedJW Contractor03/29/2023
DOB NOWPlumbingPermit IssuedCK Plumbing & Mechanical03/03/2023
DOB NOWMechanical SystemsSigned-offDavid Turner Architect02/28/2023
DOB NOWSidewalk ShedSigned-offSoho Contracting06/24/2019
DOB NOWSidewalk ShedSigned-offSoho Contracting11/21/2018
BISOTISSUEDUnique Iron Works07/02/2021
BISOTISSUEDSoho Contracting06/27/2019
BISOTISSUEDSoho Contracting02/06/2019
BISSPISSUEDPeter Plumbing Associates06/17/2016
BISPLISSUEDPeter Plumbing Associates06/17/2016
BISMHISSUEDTri State Construction of06/14/2016
BISOTISSUEDTri State Construction of06/10/2016
BISOTISSUEDTri State Construction of06/10/2016
BISEQISSUEDJ & N Construction Group05/29/2012
BISOTISSUEDJ & N Construction Group05/29/2012
BISOTISSUEDWonder Works Construction02/23/2006
BISOTISSUEDWonder Works Construction02/15/2006
BISEQISSUEDOutdoor Installation09/23/2005
BISEQISSUEDRockledge Scaffold11/08/2002
BISEQISSUEDA.G. Gustom Construction04/25/2001
BISOTISSUEDA.G. Custom Construction02/20/2001
BISOTISSUEDA.G. Custom Construction10/20/2000
BISOTISSUEDPlanned Management Construction05/18/1999
BISOTISSUED526 3rd Avenue Realty10/23/1998
BISFBISSUEDDual Fuel Plumbing & Heating06/29/1998
BISMHISSUEDHRC04/11/1997
BISEQISSUEDSpring Interprises07/19/1996
BISEQISSUEDUSA General Construction03/28/1996
BISOTISSUEDUSA General Construction03/28/1996
BISOTISSUEDNagel Roofing07/20/1995
1 project · most recent 06/25/2024
Associated Ducts and Piping Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
06/25/2024Permit IssuedJW ContractorAssociated Ducts and Piping, Heating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric MLZ-KP09NA 9,000 BTU · Ahu ×8
MXZ-SM48NAMHZ 48,000 BTU · Condensing Unit ×2
Johnson Controls TIAH060B22M 60,000 BTU · Ahu ×2
TVAHP060B21S 60,000 BTU · Condensing Unit ×2
Russell RLH215L44 14,130 BTU · Condensing Unit ×2
Tecumseh AWAR2512ZXNKM 11,000 BTU · Condensing Unit ×2
Ventilation
Panasonic FV-0510VS1 100 CFM · Exhaust Fan ×6
Ducts & Piping
Naks 85B3-6000-FF 6,000 CFM · Exhaust Fan ×2
1 project · most recent 06/25/2024
FiledStatusContractorScope
06/25/2024Permit IssuedAvon Plumbing & Heating104 heads
1 project · most recent 06/25/2024
Water/Sanitary
FiledStatusContractorScope
06/25/2024Permit IssuedCK Plumbing & MechanicalWater/Sanitary
3 projects · most recent 02/23/2023
General Wiring Lighting
FiledStatusContractorScope
02/23/2023Permit IssuedY.S. ElectricGeneral Wiring, Lighting
06/02/2022CompleteJas Electrical ServicesGeneral Wiring
11/18/2018CompletePalant Electrical Contracting—
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
10/25/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/25/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
08/18/2023Pass-Final General Construction Non-Directive 14PassView ↗
05/26/2023Fail-Final General Construction Non-Directive 14FailView ↗
▾Special Inspection Requirements (DOB NOW) — 57
DateRequirementInspectorRole
12/18/2025Interior lighting power—energy_progress
12/18/2025Energy Code Compliance Inspections—progress
12/18/2025Structural Stability – Alterations of existing buildings—special
12/18/2025Lighting controls—energy_progress
12/18/2025Fire-Resistance Rated Construction—progress
12/18/2025Fire-Resistant Penetrations and Joints—special
12/18/2025Maintenance information—energy_progress
09/22/2025Interior lighting power—energy_progress
09/22/2025Lighting controls—energy_progress
09/22/2025Maintenance information—energy_progress
09/22/2025Fire-Resistance Rated Construction—progress
09/22/2025Energy Code Compliance Inspections—progress
09/22/2025Fire-Resistant Penetrations and Joints—special
09/22/2025Structural Stability – Alterations of existing buildings—special
07/31/2025Public Assembly Emergency LightingJAEJUN RYUprogress
06/13/2025Public Assembly Emergency LightingJAEJUN RYUprogress
06/26/2024Structural Stability – Alterations of existing buildingsINHWAN CHANGspecial
06/26/2024Fire-Resistant Penetrations and JointsINHWAN CHANGspecial
06/26/2024Energy Code Compliance InspectionsJAEJUN RYUprogress
06/26/2024FinalJAEJUN RYUprogress
06/26/2024HVAC-R and service water piping design and insulation—energy_progress
06/26/2024Maintenance informationJAEJUN RYUenergy_progress
06/26/2024HVAC-R and service water heating equipmentJAEJUN RYUenergy_progress
06/26/2024Lighting controlsJAEJUN RYUenergy_progress
06/26/2024HVAC-R and service water heating system controlsJAEJUN RYUenergy_progress
Latest 25 of 57.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Robert ChickenRestaurant / Food ServiceCellar, Floors 1–7, Roof
Project M00897413 Alteration CO · Approved · 07/18/2023
Project M00824148 Alteration · Permit Entire · 02/08/2023
Project M00825355 Alteration · Permit Entire · 02/08/2023
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 181 on file (BIS + DOB NOW)
▸Plans & Drawings19
▸DOB NOWPlans/Sketch13
09/05/2026M00102394-I1Request digital key ↗
08/31/2026M00831679-I1Request digital key ↗
08/31/2026M00831679-P1Request digital key ↗
Showing 3 of 13 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly3
08/22/2026M01101740-I1Request digital key ↗
08/22/2026M01101740-P1Request digital key ↗
08/22/2026M01101740-P2Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed3
09/05/2026M00102394-I1Request digital key ↗
08/15/2026M00102394-P1Request digital key ↗
08/15/2026M00102394-P2Request digital key ↗
▸Applications & Permits24
▸BISPLAN / WORK APPROVAL APPLICATION14
11/18/2021123533701Open ↗
10/17/2018123533701Open ↗
09/18/2018123533701Open ↗
Showing 3 of 14 on file for this type
▸BISWORK PERMIT APPLICATION10
07/06/2021123533701Open ↗
06/27/2019123533701Open ↗
02/06/2019123533701Open ↗
Showing 3 of 10 on file for this type
▸Seals & Professional Certifications69
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION17
09/18/2018123533701Open ↗
05/22/2017122763571Open ↗
05/22/2017122763571Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature17
09/05/2026M00102394-I1Open ↗
09/05/2026M00102394-P2Open ↗
09/05/2026M00102394-P1Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWProgress Inspector Seal & Signature15
09/02/2026M00824148-P2Open ↗
09/02/2026M00824148-P2Open ↗
09/01/2026M00824148-P1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature14
09/02/2026M00824148-P2Open ↗
09/02/2026M00824148-P2Open ↗
09/01/2026M00824148-P1Open ↗
Showing 3 of 14 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
06/21/2016122734201Open ↗
06/07/2012121092361Open ↗
04/04/2012121028011Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM2
06/07/2012121092361Open ↗
04/04/2012121028011Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
06/21/2016122734201Open ↗
▸Trade Schedules & Equipment7
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE7
09/30/2016122734201Open ↗
09/27/2016122734201Open ↗
09/20/2016122734201Open ↗
Showing 3 of 7 on file for this type
▸Safety & Tenant Protection2
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
10/17/2018123533701Open ↗
▸BISTenant Protection Plan and Notes1
09/18/2018123533701Open ↗
▸Environmental & Asbestos10
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/13/2026M00825355-I1Open ↗
08/13/2026M00824148-P3Open ↗
08/13/2026M00824148-P2Open ↗
Showing 3 of 6 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
09/18/2018123533701Open ↗
06/21/2016122734201Open ↗
04/20/2016122763571Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
04/04/2012121028011Open ↗
▸Energy Compliance12
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS7
09/18/2018123533701Open ↗
05/22/2017122763571Open ↗
03/30/2017122734201Open ↗
Showing 3 of 7 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS4
12/10/2021123533701Open ↗
05/22/2017122763571Open ↗
03/30/2017122734201Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026M00831679-I1Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: RESPONSIBILITY1
12/10/2021123533701Open ↗
▸Approvals, Objections & Sign-offs12
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST7
12/13/2021123533701Open ↗
05/22/2017122763571Open ↗
03/30/2017122734201Open ↗
Showing 3 of 7 on file for this type
▸BISADMINISTRATIVE OBJECTIONS3
06/21/2016122734201Open ↗
06/07/2012121092361Open ↗
04/04/2012121028011Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
12/17/2012121092361Open ↗
▸BISSUPERSEDING LETTER1
07/06/2021123533701Open ↗
▸Cost, Insurance & Ownership12
▸BISCOST AFFIDAVIT12
12/10/2021123533701Open ↗
12/10/2021123533701Open ↗
09/18/2018123533701Open ↗
Showing 3 of 12 on file for this type
▸Filing & Intake Forms13
▸BISADDITIONAL INFORMATION6
11/23/2021123533701Open ↗
10/17/2018123533701Open ↗
12/07/2016122763571Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING COVER SHEET6
09/18/2018123533701Open ↗
06/21/2016122734201Open ↗
04/20/2016122763571Open ↗
Showing 3 of 6 on file for this type
▸BISBOROUGH INTAKE FORM1
07/06/2021123533701Open ↗