| Owner | Filings | Most Recent |
|---|---|---|
| Strategic Capital Metropolitan | 40 | 07/08/2026 |
| 3N Holding | 9 | 03/21/2026 |
| Supermarket | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Prime Zone Building Consulting | 5 | 05/06/2025 |
| Lawrence Marek Architect | 9 | 11/18/2024 |
| Richard Wainer Architect | 2 | 11/12/2024 |
| Angelo NG & Anthony NG Architects S | 1 | 03/24/2022 |
| Wavic Engineering | 1 | 01/18/2022 |
| Paul Perdek, Prof. Engineering | 5 | 12/21/2021 |
| CNY Engineering | 1 | 09/30/2020 |
| Valjato Engineering | 1 | 12/13/2019 |
| Times Buildings Engineering Service | 1 | 09/11/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| Cherico King Architect P | 18 | 03/21/2026 |
| Prime Zone Building Consulting | 5 | 03/21/2026 |
| D R Brown | 4 | 03/21/2026 |
| AE Design Solution | 10 | 03/21/2026 |
| BMB Building Consulting | 6 | 03/21/2026 |
| Meiyun Chen | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Core Scaffold Systems | Scaffold | 9 | 07/08/2026 |
| Great City Mechanical | Fire Protection | 6 | 07/08/2026 |
| AL Saeed Construction | General Contractor | 4 | 04/09/2026 |
| L.S. Sign Co | Sign hanger | 2 | 07/08/2026 |
| Michelle Kuo | General Contractor | 2 | 07/08/2026 |
| Goodall Electric | Electrical | 2 | 03/22/2026 |
| Jem Electrical Contracting | Electrical | 2 | 03/22/2026 |
| Full Capacity Fire | Fire Protection | 2 | 07/08/2026 |
| Tri State Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Q.Y. Electric | Electrical | 1 | 03/22/2026 |
| DHC Contracting | General Contractor | 1 | 07/08/2026 |
| B Sosa Enterprises | Scaffold | 1 | 07/08/2026 |
| DPH Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Lam and Co Consulting | 8864 | 4 | 05/06/2025 |
| Cherico King Architect | 5674 | 9 | 11/18/2024 |
| Lam and Co Consulting | 8065 | 1 | 10/02/2024 |
| Prime Zone Building Consulting | 9474 | 1 | 09/30/2024 |
| W Chan Engineering | 2881 | 1 | 09/24/2024 |
| Regional Testing | 394 | 2 | 01/18/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Signed-off | Full Capacity Fire | 02/05/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | AL Saeed Construction | 04/10/2025 |
| DOB NOW | Sign | Signed-off | Weinfeld, Elliot | 11/14/2024 |
| DOB NOW | Sign | Signed-off | Weinfeld, Elliot | 11/14/2024 |
| DOB NOW | Sprinklers | Signed-off | Full Capacity Fire | 11/12/2024 |
| DOB NOW | Plumbing | Signed-off | DPH Plumbing & Heating | 10/28/2024 |
| DOB NOW | General Construction | Signed-off | AL Saeed Construction | 10/07/2024 |
| DOB NOW | Plumbing | Signed-off | DW Plumbing | 09/30/2024 |
| DOB NOW | General Construction | Signed-off | 18-15 Realty | 09/27/2024 |
| DOB NOW | Mechanical Systems | Signed-off | 18-15 Realty | 09/27/2024 |
| DOB NOW | Sprinklers | Signed-off | Joe Parziale Plumbing Co | 05/03/2023 |
| DOB NOW | Standpipe | Signed-off | Joe Parziale Plumbing Co | 05/03/2023 |
| DOB NOW | Curb Cut | Signed-off | Alexander Chan | 03/20/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | Core Scaffold Systems | 10/04/2022 |
| DOB NOW | Standpipe | Signed-off | Joe Parziale Plumbing Co | 09/15/2022 |
| DOB NOW | Supported Scaffold | Signed-off | Core Scaffold Systems | 03/04/2022 |
| DOB NOW | Standpipe | Signed-off | Joe Parziale Plumbing Co | 10/20/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | Core Scaffold Systems | 10/04/2021 |
| DOB NOW | Standpipe | Signed-off | Joe Parziale Plumbing Co | 04/29/2021 |
| DOB NOW | Supported Scaffold | Signed-off | Core Scaffold Systems | 03/15/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | Core Scaffold Systems | 10/08/2020 |
| DOB NOW | Standpipe | Signed-off | Joe Parziale Plumbing Co | 10/05/2020 |
| DOB NOW | Construction Fence | Signed-off | B Sosa Enterprises | 10/09/2018 |
| BIS | — | ISSUED | DHC Contracting | 10/07/2022 |
| BIS | PL | ISSUED | Joe Parziale Plumbing Co | 07/25/2022 |
| BIS | EQ | ISSUED | DHC Contracting | 07/18/2022 |
| BIS | — | ISSUED | DHC Contracting | 07/18/2022 |
| BIS | EQ | ISSUED | Core Scaffold Systems | 11/10/2021 |
| BIS | — | ISSUED | DHC Contracting | 10/04/2021 |
| BIS | PL | ISSUED | Joe Parziale Plumbing Co | 08/06/2021 |
| BIS | EQ | ISSUED | DHC Contracting | 07/29/2021 |
| BIS | — | ISSUED | DHC Contracting | 07/27/2021 |
| BIS | EQ | ISSUED | Core Scaffold Systems | 11/10/2020 |
| BIS | EQ | ISSUED | DHC Contracting | 09/03/2020 |
| BIS | — | ISSUED | DHC Contracting | 08/05/2020 |
| BIS | PL | ISSUED | Joe Parziale Plumbing Co | 08/05/2020 |
| BIS | OT | ISSUED | DHC Contracting | 03/11/2020 |
| BIS | OT | ISSUED | DHC Contracting | 02/12/2020 |
| BIS | PL | ISSUED | Aranda Plumbing & Heating | 06/11/2012 |
| BIS | FP | ISSUED | Mega Fire Protection | 04/13/2012 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/06/2025 | Permit Issued | AL Saeed Construction | Air Conditioning Systems, Heating Systems, Others | — |
| 08/07/2024 | — | — | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric MXZ-SM72TAM-U1 72,000 BTU · Heat Pump Outdoor ×2 Ventilation Greenheck GREENHECK 900 CFM · Kitchen Exhaust ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/07/2024 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/07/2024 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/06/2025 | Complete | Jem Electrical Contracting | General Wiring |
| 12/11/2024 | Permit Issued | Aurora Electrical Contg | — |
| 12/11/2024 | Permit Issued | Aurora Electrical Contg | — |
| 06/05/2024 | Complete | Goodall Electric | 5 meters, 3 new_meters |
| 07/19/2023 | Complete | Q.Y. Electric | General Wiring |
| 06/12/2023 | Complete | Q.Y. Electric | — |
| 08/12/2021 | Complete | Q.Y. Electric | 76 meters, 76 new_meters |
| 03/01/2021 | Complete | KJK Electric | — |
| 11/30/2020 | Complete | Y Electric | — |
| 11/02/2020 | Complete | V. Vass Electric | — |
| 10/05/2020 | Complete | V. Vass Electric | — |
| 07/05/2020 | Complete | Goodall Electric | 1 meters, 1 new_meters |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/19/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/05/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/02/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 07/03/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/13/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 12/30/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/27/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/22/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/08/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/25/2023 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 05/12/2023 | Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test | Certified | View ↗ |
| 05/12/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/12/2023 | Certified StandPipe-Fire Pump (SD)-Fire Pump Test | Certified | View ↗ |
| 05/12/2023 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 05/05/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/05/2023 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/05/2025 | Heating Systems | JICHEN SUN | special |
| 05/05/2025 | HVAC-R and service water piping design and insulation | JICHEN SUN | energy_progress |
| 05/05/2025 | Shutoff dampers | JICHEN SUN | energy_progress |
| 05/05/2025 | HVAC-R and service water heating equipment | JICHEN SUN | energy_progress |
| 05/05/2025 | Maintenance information | JICHEN SUN | energy_progress |
| 05/05/2025 | HVAC-R and service water heating system controls | JICHEN SUN | energy_progress |
| 05/05/2025 | Final | FAZAL BANGASH | progress |
| 05/05/2025 | Energy Code Compliance Inspections | JICHEN SUN | progress |
| 05/05/2025 | Tenant Protection Plan Compliance | — | special |
| 05/05/2025 | Mechanical Systems | JICHEN SUN | special |
| 11/19/2024 | Tenant Protection Plan Compliance | LAWRENCE MAREK | special |
| 11/19/2024 | Energy Code Compliance Inspections | LAWRENCE MAREK | progress |
| 11/19/2024 | Maintenance information | LAWRENCE MAREK | energy_progress |
| 11/19/2024 | HVAC-R and service water heating equipment | LAWRENCE MAREK | energy_progress |
| 11/19/2024 | HVAC-R and service water heating system controls | LAWRENCE MAREK | energy_progress |
| 11/19/2024 | HVAC-R and service water piping design and insulation | LAWRENCE MAREK | energy_progress |
| 11/19/2024 | Fire-Resistant Penetrations and Joints | LAWRENCE MAREK | special |
| 11/06/2024 | Final | Richard Wainer | progress |
| 09/30/2024 | HVAC-R and service water heating equipment | JICHEN SUN | energy_progress |
| 09/30/2024 | HVAC-R and service water piping design and insulation | JICHEN SUN | energy_progress |
| 09/30/2024 | HVAC-R and service water heating system controls | JICHEN SUN | energy_progress |
| 09/30/2024 | Tenant Protection Plan Compliance | CHI WAI CHUNG | special |
| 09/30/2024 | Energy Code Compliance Inspections | JICHEN SUN | progress |
| 09/23/2024 | Tenant Protection Plan Compliance | LAWRENCE MAREK | special |
| 09/23/2024 | Final | LAWRENCE MAREK | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Dunkin' / Baskin-Robbins | Restaurant / Food Service | Cellar, Floor 1, Roof | Project Q01115600 Project Q01081914 |